Question

In: Accounting

Section 2. Question 1 Al Hassan Engineering has won a tender to build an oil field...

Section 2. Question 1

Al Hassan Engineering has won a tender to build an oil field in the Sea of Oman. In order to transport the workers to the site, Al Hassan Engineering has identified the following two options with related cost: Option1: To buy a ship for OMR 15,000,000. Annual fixed costs will be OMR 300,000 the variable cost per journey is OMR 2,000. At the end of the 3-year project, the ship can be disposed of for OMR 10,000,000. Option2: To buy a helicopter for OMR 7,000,000. The average operating costs will be OMR 500 per trip. Maintenance costs are expected to be OMR 100,000 annually. At the end of the 3-year project, the helicopter can be sold for OMR 4,000,000. The expected cash inflow from either option is OMR 8,000,000 each year for the four year period. The expected annual demand for transporting employees offshore and back again over the next four years is forecasted as follows: Year1 1,000 journeys Year2 1,000 journeys Year3 1,000 journeys Year4 1,000 journeys Al Hassan’s weighted average cost of capital is 7%

Instructions:

a. Compare the Net Present Value (NPV) for both options.

b. Use Microsoft excel to evaluate the Internal Rate of Return (IRR) for the two options.

c. Appraise which option, if either, the company should undertake.

Solutions

Expert Solution

Year Ship Cost(a) Annual Fixed Costs(b) No.of Journeys (c ) Variable costs per journey(d) Variable costs per annum(e=c*d) Total Costs (f=a+b+e) Expected Cash Inflow(g) Expected Sale Value(h) Total Cash Inflows(i=g+h) Net Cash Flows(j=i+f) PV Factor @7%(k) PV of cash flows(l=j*k)
        -                                                                                                (15,000,000.00)                          -                                  -                                -                           -      (15,000,000.00)                          -                            -                            -   (15,000,000.00)             1.00 (15,000,000.00)
    1.00                                                                                                                      -          (300,000.00)                    1,000.00                (2,000.00)    (2,000,000.00)      (2,300,000.00)      8,000,000.00                          -        8,000,000.00      5,700,000.00             0.93      5,327,102.80
    2.00                                                                                                                      -          (300,000.00)                    1,000.00                (2,000.00)    (2,000,000.00)      (2,300,000.00)      8,000,000.00                          -        8,000,000.00      5,700,000.00             0.87      4,978,600.75
    3.00                                                                                                                      -          (300,000.00)                    1,000.00                (2,000.00)    (2,000,000.00)      (2,300,000.00)      8,000,000.00    10,000,000.00    18,000,000.00    15,700,000.00             0.82    12,815,876.67
    4.00                                                                                                                      -          (300,000.00)                    1,000.00                (2,000.00)    (2,000,000.00)      (2,300,000.00)      8,000,000.00                          -        8,000,000.00      5,700,000.00             0.76      4,348,502.71
Total                                                                                             (15,000,000.00)    (1,200,000.00)                (8,000.00) (8,000,000.00) (24,200,000.00) 32,000,000.00 10,000,000.00 42,000,000.00    17,800,000.00 NPV    12,470,082.93
Year Ship Cost(a) Annual Fixed Costs(b) No.of Journeys (c ) Variable costs per journey(d) Variable costs per annum(e=c*d) Total Costs (f=a+b+e) Expected Cash Inflow(g) Expected Sale Value(h) Total Cash Inflows(i=g+h) Net Cash Flows(j=i+f) PV Factor @7%(k) PV of cash flows(l=j*k)
        -                                                                                                   (7,000,000.00)                          -                                  -                                -                           -        (7,000,000.00)                          -                            -       (7,000,000.00)             1.00     (7,000,000.00)
    1.00                                                                                                                      -          (100,000.00)                    1,000.00                    (500.00)       (500,000.00)         (600,000.00)      8,000,000.00                          -        8,000,000.00      7,400,000.00             0.93      6,915,887.85
    2.00                                                                                                                      -          (100,000.00)                    1,000.00                    (500.00)       (500,000.00)         (600,000.00)      8,000,000.00                          -        8,000,000.00      7,400,000.00             0.87      6,463,446.59
    3.00                                                                                                                      -          (100,000.00)                    1,000.00                    (500.00)       (500,000.00)         (600,000.00)      8,000,000.00      4,000,000.00    12,000,000.00    11,400,000.00             0.82      9,305,795.80
    4.00                                                                                                                      -          (100,000.00)                    1,000.00                    (500.00)       (500,000.00)         (600,000.00)      8,000,000.00                          -        8,000,000.00      7,400,000.00             0.76      5,645,424.57
Total                                                                                                (7,000,000.00)       (400,000.00)                (2,000.00) (2,000,000.00)     (9,400,000.00) 32,000,000.00      4,000,000.00 36,000,000.00    26,600,000.00 NPV    21,330,554.81
Comparision of NPV
NPV of Ship    12,470,082.93 Since NPV of helocopter is high, 2nd option is beneficial
NPV of Helicopter    21,330,554.81
Calculation of IRR Option A Calculation of IRR Option B
Year Cash Flows(j) Year Cash Flows(j)
0 (15,000,000.00) 0    (7,000,000.00)
1      5,700,000.00 1     7,400,000.00
2      5,700,000.00 2     7,400,000.00
3    15,700,000.00 3 11,400,000.00
4      5,700,000.00 4     7,400,000.00
IRR 37% IRR 107%
Calculated using excel formula =IRR(Values). Instead we can use trail and error method Calculated using excel formula =IRR(Values). Instead we can use trail and error method
Since NPV and IRR afre more gor option B, we will select B.
Assumptions:
1. Assuming 1,000 journey sper year includes to and fro.
2. Annual fixed costs will not change according to number of trips
3. Cash Inflows were taken for each year

Related Solutions

The NCO Corporation has won a tender to drill an oil field in the Oman Sea....
The NCO Corporation has won a tender to drill an oil field in the Oman Sea. In order to transport the workers to the site, NCO has the following two options with related cost: Option1:To buy a ship for O.R 20,000,000. Annual fixed operating costs will be O.R 500,000 the variable cost per journey is O.R 1,000. At the end of the four-year project, the ship can be disposed of for O.R 12,000,000. Option2:To buy a helicopter for O.R 12,000,000....
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%. BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project...
The Birmingham Road Company (BRC) has won a tender to build a highway extension. The project will last 10 years and will generate free cash flows (FCFs) of £100 million per year for 10-years. These FCFs are after-tax but before financing costs. The unlevered (i.e., all equity) cost of capital for the project is 10% and BRC’s tax rate is 40%. BRC will finance the project with a combination of debt and equity and is considering three alternatives as regards...
QUESTION 1 Name an Australian industry related to your engineering field. What is the contribution to...
QUESTION 1 Name an Australian industry related to your engineering field. What is the contribution to the Australian GDP. N.B. Try to be as specific as possible. For example, if you are looking at mining see if you can find the contribution of a particular field. QUESTION 2 Name three of the largest companies within the industry you have discussed in question one. If you can, identify or estimate the contribution of one of those companies towards the Australian GDP....
1. A large oil company has hired you as part of their engineering team that is...
1. A large oil company has hired you as part of their engineering team that is planning all of the details for a new drill site. The crude oil will be stored in large cylindrical tanks. The following restrictions apply to the tanks you can purchase: (a) Tank heights must be in full meters i. The maximum tank height for sale is 12 meters ii. The minimum tank height for sale is 7 meters (b) All tanks have a diameter...
a. define Electromagnetic field theory and explain 2 engineering applications of electromagnetic field b.why is modulation...
a. define Electromagnetic field theory and explain 2 engineering applications of electromagnetic field b.why is modulation of waves necessary c. differences between bio- savart and amperes law
QUESTION 9 1. A 1,000-turn coil has a cross section of 7.0 cm ^ 2 and...
QUESTION 9 1. A 1,000-turn coil has a cross section of 7.0 cm ^ 2 and a length of 25 cm. Determine how much energy is stored in the coil's magnetic field when it has a current of 10.0 A. a. 0.18 J b. 0.36 J c. 0.10 J d. 28 J e. 2.8 J QUESTION 10 1. Determine which of the following types of waves is intrinsically different from the other four. a. ultraviolet radiation b. gamma rays c....
1. Suppose Al hires Joe to build him a house. At the time they signed the...
1. Suppose Al hires Joe to build him a house. At the time they signed the contract, Al valued the house at $500,000, it would cost Joe $200,000 to build the house, and they agree on a price of $300,000. After the contract is signed (but before any money changes hands), Joe’s costs go up to $350,000, and Joe considers breaching the contract. a. Would Joe’s breach be efficient overall? Why or why not? What would expectation damages be (the...
chandler Oil has 5000 barrels of crude oil 1 and 10,000 barrels of crude oil 2...
chandler Oil has 5000 barrels of crude oil 1 and 10,000 barrels of crude oil 2 available. Chandler sells gasoline and heating oil. These products are produced by blending the two crude oils together. Each barrel of crude oil 1 has a quality level of 10 and each barrel of crude oil 2 has a quality level of 5.6 Gasoline must have an average quality level of at least 8, whereas heating oil must have an average quality level of...
SECTION A (30 marks) This section consists of ONE (1) compulsory question QUESTION 1 (30 marks)...
SECTION A This section consists of ONE (1) compulsory question QUESTION 1 ABC Ltd is a wholesaler of furniture which has been in operation for ten years. It buys furniture from five major manufacturers and sells them to a range of customers. The company currently has a customer base of over 500 customers most of which are credit customers. The receivables balance comprises customers owing up to $2,000,000 to smaller balances of about $10,000, all with many different due dates...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT