The project budget baseline for XYZ is $3,500,000 with the following risks assessment: Risk Event Probability Impact Expected Value Parts delayed in Customs 40% $100,000 Strong labor training equates to quick assembly 60% ($50,000) Heat sink assembly requires rework 85% $150,000 (source: Paul Martinsen, PMP)\
3. Calculate the adjusted project budget baseline for XYZ project.
Please see the table below. Please be guided by the second row to understand the mathematics. Figures in parenthesis, if any, mean negative values. All financials are in $.
Risk Event | Probability | Impact | Expected Value |
Pi | Vi | Pi x Vi | |
Parts delayed in Customs | 40% | 100,000 | 40,000 |
Strong labor training equates to quick assembly | 60% | (50,000) | (30,000) |
Heat sink assembly requires rework | 85% | 150,000 | 127,500 |
Total | 137,500 |
Hence, the adjusted project budget baseline for XYZ project = Baseline budget + Adjustment required due to risk events = 3,500,000 + 137,500 = $ 3,637,500