Question

In: Finance

The project budget baseline for XYZ is $3,500,000 with the following risks assessment: Risk Event Probability...

The project budget baseline for XYZ is $3,500,000 with the following risks assessment: Risk Event Probability Impact Expected Value Parts delayed in Customs 40% $100,000 Strong labor training equates to quick assembly 60% ($50,000) Heat sink assembly requires rework 85% $150,000 (source: Paul Martinsen, PMP)\

3. Calculate the adjusted project budget baseline for XYZ project.

Solutions

Expert Solution

Please see the table below. Please be guided by the second row to understand the mathematics. Figures in parenthesis, if any, mean negative values. All financials are in $.

Risk Event Probability Impact Expected Value
Pi Vi Pi x Vi
Parts delayed in Customs 40%         100,000                   40,000
Strong labor training equates to quick assembly 60%          (50,000)                 (30,000)
Heat sink assembly requires rework 85%         150,000                 127,500
Total                137,500

Hence,  the adjusted project budget baseline for XYZ project = Baseline budget + Adjustment required due to risk events = 3,500,000 + 137,500 = $  3,637,500


Related Solutions

Project Risk = Probability of event * Consequences of event Let’s investigate the quantitative risk identified...
Project Risk = Probability of event * Consequences of event Let’s investigate the quantitative risk identified for a company, last year. Probability of Failure Category Probability of Failure Consequences of Failure Category Process Maturity 30% Performance = 55% Technical Complexity 25% Schedule = 75% Vendor Dependency 30% Cost = $55 Workforce Availability 10% Reliability = 20% Use the table above to answer the following questions: Please calculate the total risk factor for this project. Would you assess this level of...
Inputs to Estimate Costs include: Scope Baseline, Cost of Quality, Risk Register, OPAs Scope Baseline, Project...
Inputs to Estimate Costs include: Scope Baseline, Cost of Quality, Risk Register, OPAs Scope Baseline, Project Schedule, Risk Register, Cost Management Plan Risk Register, Cost Management Plan, Basis of Estimates, Scope Baseline Expert Judgement, Reserve Analysis, Analogous Estimating, Issue Log
pros and cons of risk probability and impact assessment, in Qualitative risk analysis?
pros and cons of risk probability and impact assessment, in Qualitative risk analysis?
Risk assessment calculations Baseline information: 40,000 units sold at a unit selling price of $100, variable...
Risk assessment calculations Baseline information: 40,000 units sold at a unit selling price of $100, variable costs of $80 per unit, fixed costs of $750,000 1. Calculate the contribution margin per unit in dollars and as a percentage 2. Prepare a financial report in the contribution margin format Calculate the breakeven point in dollars and unit sales 4. Prove the validity of the breakeven calculation by preparing a financial report using the contribution margin format 5. Calculate the performance level...
Risk assessment calculations Baseline information: 40,000 units sold at a unit selling price of $100, variable...
Risk assessment calculations Baseline information: 40,000 units sold at a unit selling price of $100, variable costs of $80 per unit, fixed costs of $750,000 1. Calculate the contribution margin per unit in dollars and as a percentage 2. Prepare a financial report in the contribution margin format Calculate the breakeven point in dollars and unit sales 4. Prove the validity of the breakeven calculation by preparing a financial report using the contribution margin format 5. Calculate the performance level...
Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative...
Make a Project of Management Risk Assessment: 1. Make a Qualitative Risk assessment 2. Make Quantitative Risk Assessment and Mitigation
Complete a qualitative risk assessment and response planning of each of the risk identified in Project...
Complete a qualitative risk assessment and response planning of each of the risk identified in Project 1: Risk Identification (at least 10 risks). Use at least 1 of each of the threat risk response strategies for your response planning. THE 10 RISKS: Risk Statement/Description Project prupose and need is not well defined. Scope creep Project schedule is not clearly defined or understood Lack of communication, causing lack of clarity and confusion No control over staff proprities Consultant or contractor delays...
Compare the following risks: Preventable risks, Strategy risks, and External risks. subject : risk management is...
Compare the following risks: Preventable risks, Strategy risks, and External risks. subject : risk management is construction
There are non-diversifiable risks such as the Beta risk of an asset, project or industry and;...
There are non-diversifiable risks such as the Beta risk of an asset, project or industry and; diversifiable risks that can be offset by a higher discount rate to offset them. What do you think?. Ratios, indices or financial indicators are classified into several categories and their interpretation and correct reading is essential in the diagnosis of a company or a corporation. This implies that its good calculation and use exonerates the financial analyst from using industry indicators or trying to...
Discus What is Qualify Risk under assessing project risks
Discus What is Qualify Risk under assessing project risks
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT