Question

In: Finance

Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...

Company B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X.
Years 0 1 2 3
Project X cash flows -$100 80 60 40

And the following information is available regarding Projects Y and Z.
Criteria Project Y Project Z
NPV $40 $67
MIRR 10% 20%
IRR 2.0% 18.7%
Regular Payback 2.23 years 1.77 years

5) Assuming the three projects X, Y & Z are independent, based on NPV criteria we choose: *

6) Assuming the three projects X, Y & Z are mutually exclusive, based on NPV criteria we choose: *

7) Assuming the three projects X, Y & Z are independent, based on MIRR criteria we choose: *

8) Assuming the three projects X, Y & Z are mutually exclusive, based on MIRR criteria we choose: *

Solutions

Expert Solution

first lets calculate NPV and MIRR of project X

NPV:

MIRR:

so NPV of project X = $52.37

MIRR = 27%

5)

if the projects are independent, we can choose the projects with positive NPV's since here all the projects have positive NPV's we can choose All three projects. i.e.,Project X , Y , Z.

6)

if the projects are mutually exclusive then only the project highest NPV can be selected.

since project Z has high NPV it should be selected.

7)

in case of independent, projects with MIRR greater than WACC can be chosen

since here all projects have MIRR greater than WACC all three projects can be selected

8)

in case of mutually exclusive projects , project with high MIRR can be selected. so answer is Project X.

(basically MIRR is not the criteria to select betwen projects because there may be conflict due to different size of the projects.)


Related Solutions

ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y...
ompany B’s WACC is 10%. It has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X. Years 0 1 2 3 Project X cash flows -$100 80 60 40 And the following information is available regarding Projects Y and Z. Criteria Project Y Project Z NPV $40 $67 MIRR 10% 20% IRR 2.0% 18.7% Regular Payback 2.23 years 1.77 years 9) If IRR for Project X is 17.95%, and the...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
Company B has three Projects it can choose from: Projects X, Y and Z. The following...
Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling at $70 per share and pay a...
"Answer all the parts in one answer" Company B has three Projects it can choose from:...
"Answer all the parts in one answer" Company B has three Projects it can choose from: Projects X, Y and Z. The following information is available regarding Project X: Years 0 1 2 3 CF -100 80 60 40 The company’s capital structure is distributed equally between debt and preferred stock and the remaining 40% goes to common stock. It has also the following information: 1- After tax cost of debt: 3%. Tax rate: 40% 2- Preferred stocks are selling...
Consider the following projects, X and Y where the firm can only choose one.
3Consider the following projects, X and Y where the firm can only choose one. Project X costs $600 and has cash flows of $400 in each of the next 2 years. Project also costs $600 and generates cash flows of $500 for the next 2 years respectively. Which investment should the firm choose the cost of capital is 25 percent? Another since both the projects have negative NPV Another, since both the projects have positive NPV Project X sine X has a higher...
Consider the following projects X and Y where the firm can choose only once. Project X...
Consider the following projects X and Y where the firm can choose only once. Project X costs $600 and has cash flows of $400 in each of the next two years. Project B also costs $ 600 and generates cash flows $500 and $275 for the next two years, respectively. Sketch a net present value profile (graphs) for each of these projects. For graphs you may use approximation Which project should the firm choose if the cost of capital is...
Consider the following projects, X and Y where the firm can only choose one. Project X...
Consider the following projects, X and Y where the firm can only choose one. Project X costs $1500 and has cash flows of $678, $652, $347, $111, $54, $16 in each of the next 6 years. Project Y also costs $1500, and generates cash flows of $738, $693, $405 for the next 3 years, respectively. WACC=9.5%. A) Draw the timelines for both projects: X and Y. B) Calculate the projects’ NPVs, IRRs, payback periods. C) If the two projects are...
Takelmer Industries has a different WACC for each of three types of projects. Lowminusrisk projects have...
Takelmer Industries has a different WACC for each of three types of projects. Lowminusrisk projects have a WACC of​ 8.00%, averageminusrisk projects a WACC of​ 10.00%, and highminusrisk projects a WACC of​ 12%. Which of the following projects do you recommend the firm​ accept? Project Level of Risk IRR A Low ​9.50% B Average ​8.50% C Average ​7.50% D Low ​9.50% E High ​14.50% F High ​17.50% G Average ​11.50% A. ​E, F, G B. ​B, C,​ E, F, G...
You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC...
You must analyze two projects, X and Y. Each project costs $10,000, and the firm’s WACC is 12%. The expected net cash flows are as follows: Project X Project Y 0 -$10,000 -$10,000 1 $6,500 $3,500 2 $3,000 $3,500 3 $3,000 $3,500 4 $1,000 $3,500 a. Calculate each project’s NPV, IRR, MIRR, payback, and discounted payback. b. Which project(s) should be accepted if they are independent? c. Which project(s) should be accepted if they are mutually exclusive? Hint: (Project-X IRR...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT