Question

In: Finance

Following are data reporting progress on a project. Work on all tasks contained in the table...

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

Task B

4,000

Yes

Yes

4,500

Task C

2,500

Yes

Yes

2,250

Task D

4,000

Yes

No

3,500

Task E

3,500

Yes

Yes

4,000

Task F

2,500

No

No

0

  1. Using the 50-50 Rule, what is earned value for this project?
  2. Using the 0-100 Rule, what is earned value for this project?
  3. Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  4. Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  5. What is the schedule performance index (SPI)?
  6. Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  7. What is the cost performance index (CPI)?
  8. If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
  9. Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Solutions

Expert Solution


Related Solutions

The employees at Table Manufacturing perform the following tasks as indicated in Table A and Table...
The employees at Table Manufacturing perform the following tasks as indicated in Table A and Table B. Employee A Roles and Responsibilities Employee B Roles and Responsibilities Reports to CFO Reports to CFO Raises capital through issuing stocks and bonds General financial accounting General managerial accounting Tax preparation Which of the following is the role of Employee A and Employee​ B?
The following table provides data for a project. Use the data to answer the following questions...
The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic Most Likely Pessimistic Expected Variance A - 6 7 14 B - 8 10 12 C A 2 3 4 D A 6 7 8 E B,C 5 5.5 9 F B,C 5 7 9 G D,E 4 6 8 H F 2.5 3 3.5 Draw a network to represent the above project. What is the critical...
Six months into the project, the client reviews the progress and issues a stop-work order. The...
Six months into the project, the client reviews the progress and issues a stop-work order. The main issues identified during their review: There were different expectations about the complexity of graphics in course development and course materials. There were different opinions about the level of marketing required (marketing a course versus the entire academy, no post-course promos, etc.). There were issues with instructors. There were instances where instructors had rescheduled on multiple occasions or cancelled. There were concerns about the...
Write a program to complete the following tasks. Record all results to a data file called "GradeSheet.dat".
 c++Write a program to complete the following tasks. Record all results to a data file called "GradeSheet.dat".(1) Read the grade sheet from attached data file, "Assignment4.dat". Print the original grade sheet.(3) Write a module to sort array GRADE[] and print the sorted grade sheet.(4) Write a module to sort array NAME[] and print the sorted grade sheet.(5) Write a module to sort array ID[] and print the sorted grade sheet.(6) Write a module to print the student's id, name, and...
Consider the table below, which includes time and activity data for a Small IT Project. All...
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project. Activity Duration (Days) Predecessor A 8 - B 10 A C 18 A D 4 A E 28 B, D F 2 C, E G 32 E H 18 B I 12 F J 2 H, G, I Draw a network diagram representing the project. MS PowerPoint or...
The following table provides the crash data for the project network . the normal activity times...
The following table provides the crash data for the project network . the normal activity times are considered to be deterministic and not probabilistic . Activity time(week) Activity Cost($) Activity Normal Crash Normal Crash a 9 7 $4,800 $6,300 b 11 9 $9,100 $15,500 c 7 5 $3,000 $4,000 d 10 8 $3,600 $5,000 e 1 1 $0 $0 f 5 3 $1,500 $2,000 g 6 5 $1,800 $2,000 h 3 3 $0 $0 i 1 1 $0 $0 j...
Complete the required tasks utilizing excel and label everything. All work must be shown On January...
Complete the required tasks utilizing excel and label everything. All work must be shown On January 1, 2021, Hobart Mfg. Co. purchased a drill press at a cost of $680,000. The drill press is expected to last 6 years and has a residual value of $80,000. During its 6-year life, the equipment is expected to produce 300,000 units of product. Units actually produced over the 6-year useful life is as follows:                   2021                        65,000 units                   2022                        60,000 units                  ...
. Complete the required tasks utilizing excel and label everything. All work must be shown FKG...
. Complete the required tasks utilizing excel and label everything. All work must be shown FKG Inc. carries the following debt and equity securities on its books at December 31, 2020. All securities were purchased during 2020. Trading Securities Company                                                                   Cost                            Fair Value, 12/31/20        Fair Value, 12/31/21 Company A Investment                                      $ 25,000                $ 13,000                                  $ 20,000 Company B Investment                                      $ 13,000                $ 20,000                                  $ 20,000 Company C Investment                                      $ 35,000                $30,000                                   $ 25,000 Available-for-Sale Securities Company...
Complete the required tasks utilizing excel and label everything. All work must be shown to receive...
Complete the required tasks utilizing excel and label everything. All work must be shown to receive credit. A 20% late penalty will be assessed for each 24 hours submitted late. Below is the activity (purchases and Sales) for inventory held by Random Creations for the month of January, 2020: Beginning Inventory: January 1, 2020 80 Units @ $50 per unit Total $ 4,000 Purchases: January 18, 2020 40 Units @ $51 per unit Total $ 2,040 January 28, 2020 40...
Consider the data contained in the table below, which lists 30 monthly excess returns to two...
Consider the data contained in the table below, which lists 30 monthly excess returns to two different actively managed stock portfolios (A and B) and three different common risk factors (1, 2, and 3). (Note: You may find it useful to use a computer spreadsheet program such as Microsoft Excel to calculate your answers.) Period Portfolio A Portfolio B Factor 1 Factor 2 Factor 3 1 1.00 % 0.00 % 0.02 % -0.99 % -1.73 % 2 7.52 6.61 6.85...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT