Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
Budget |
Begun? |
Complete? |
Actual cost |
Earned Value |
|
Task A |
3,100 |
Yes |
Yes |
3,100 |
|
Task B |
4,000 |
Yes |
Yes |
4,500 |
|
Task C |
2,500 |
Yes |
Yes |
2,250 |
|
Task D |
4,000 |
Yes |
No |
3,500 |
|
Task E |
3,500 |
Yes |
Yes |
4,000 |
|
Task F |
2,500 |
No |
No |
0 |