College Supply Company (CSC) makes three types of drinking glasses: short, medium, and tall. It presently applies overhead using a predetermined rate based on direct labor-hours. A group of company employees recommended that CSC switch to activity-based costing and identified the following activities, cost drivers, estimated costs, and estimated cost driver units for Year 5 for each activity center.
Activity | Recommended Cost Driver |
Estimated Cost |
Estimated Cost Driver Units |
||||
Setting up production | Number of production runs | $ | 36,000 | 120 | runs | ||
Processing orders | Number of orders | 46,800 | 180 | orders | |||
Handling materials | Pounds of materials | 14,000 | 7,000 | pounds | |||
Using machines | Machine-hours | 48,000 | 8,000 | hours | |||
Providing quality management | Number of inspections | 48,000 | 40 | inspections | |||
Packing and shipping | Units shipped | 40,000 | 20,000 | units | |||
$ | 232,800 | ||||||
In addition, management estimated 2,000 direct labor-hours for year 5.
Assume that the following cost driver volumes occurred in February, year 5.
Short | Medium | Tall | |||||||
Number of units produced | 900 | 600 | 500 | ||||||
Direct materials costs | $ | 5,000 | $ | 2,500 | $ | 2,000 | |||
Direct labor-hours | 90 | 110 | 110 | ||||||
Number of orders | 8 | 8 | 5 | ||||||
Number of production runs | 1 | 4 | 9 | ||||||
Pounds of material | 400 | 700 | 200 | ||||||
Machine-hours | 600 | 400 | 200 | ||||||
Number of inspections | 2 | 1 | 2 | ||||||
Units shipped | 900 | 600 | 400 | ||||||
Direct labor costs were $20 per hour.
Required:
a. Compute a predetermined overhead rate for
year 5 for each cost driver recommended by the employees. Also
compute a predetermined rate using direct labor-hours as the
allocation base.
b. Compute the production costs for each product
for February using direct labor-hours as the allocation base and
the predetermined rate computed in requirement
a.
c. Compute the production costs for each product
for February using the cost drivers recommended by the employees
and the predetermined rates computed in requirement
a. (Note: Do not assume that total
overhead applied to products in February will be the same for
activity-based costing as it was for the labor-hour-based
allocation.)
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. | |||||||
Part a | |||||||
Recommended by Employee: | |||||||
a | b | a/b | |||||
Activity | Recommended | Estimated | Estimated Cost | Predetermined | |||
Cost Driver | Cost | Driver Units | Overhead rate | ||||
Setting up production | Number of production runs | $ 36,000 | 120 | runs | $ 300 | ||
Processing orders | Number of orders | $ 46,800 | 180 | orders | $ 260 | ||
Handling materials | Pounds of materials | $ 14,000 | 7,000 | pounds | $ 2 | ||
Using machines | Machine-hours | $ 48,000 | 8,000 | hours | $ 6 | ||
Providing quality management | Number of inspections | $ 48,000 | 40 | inspections | $ 1,200 | ||
Packing and shipping | Units shipped | $ 40,000 | 20,000 | units | $ 2 | ||
Total | $ 232,800 | ||||||
Based on Direct Labor hours: | |||||||
Estimated Overhead | a | $ 232,800 | |||||
Estimated Direct Labor Hours | b | 2,000 | |||||
Predetermined Overhead rate | a/b | $ 116.40 | |||||
Part b | |||||||
Short | Medium | Tall | |||||
Direct materials costs | $ 5,000 | $ 2,500 | $ 2,000 | ||||
Direct labor cost | $20*Direct labor hours | $ 1,800 | $ 2,200 | $ 2,200 | |||
Overhead | $116.40* Direct labor hours | $ 10,476 | $ 12,804 | $ 12,804 | |||
Product Cost | $ 17,276 | $ 17,504 | $ 17,004 | ||||
Part c | |||||||
Short | Medium | Tall | |||||
Direct materials costs | $ 5,000 | $ 2,500 | $ 2,000 | ||||
Direct labor cost | $20*Direct labor hours | $ 1,800 | $ 2,200 | $ 2,200 | |||
Overhead | $ 10,980 | $ 9,480 | $ 8,800 | ||||
Product Cost | $ 17,780 | $ 14,180 | $ 13,000 | ||||
Activity | Predetermined | Short | Medium | Tall | |||
Overhead rate | Activity | Overhead | Activity | Overhead | Activity | Overhead | |
Setting up production | $ 300 | 1 | $ 300 | 4 | $ 1,200 | 9 | $ 2,700 |
Processing orders | $ 260 | 8 | $ 2,080 | 8 | $ 2,080 | 5 | $ 1,300 |
Handling materials | $ 2 | 400 | $ 800 | 700 | $ 1,400 | 200 | $ 400 |
Using machines | $ 6 | 600 | $ 3,600 | 400 | $ 2,400 | 200 | $ 1,200 |
Providing quality management | $ 1,200 | 2 | $ 2,400 | 1 | $ 1,200 | 2 | $ 2,400 |
Packing and shipping | $ 2 | 900 | $ 1,800 | 600 | $ 1,200 | 400 | $ 800 |
Total | $ 10,980 | $ 9,480 | $ 8,800 | ||||