Question

In: Accounting

there are presently (2) projects available to shrewsberry limited,however the company only has cash available of...

there are presently (2) projects available to shrewsberry limited,however the company only has cash available of one of them.
                       Project R.            Project S
investment. 900000.            600000
Depreciation straight line    straight line
cost of capital 14%.                       14%
lifespan.        5 years.                    5 years     
residual         84000.                     nil    
net profit.         
year 1.              56000.                  7000
year 2                80000                 7000
year 3                102000.              7000
year 4.                130000               7000
year 5.                152000               7000
required:
1.1 calculate the accounting rate of return for project R.
1.2 Calculate the payback period for both projects.
1.3 calculate the net present value for both projects
1.4 which project should the company choose and why?

Solutions

Expert Solution

Answer is given below

Accounting rate of return has been given based initial investment as well as average investment


Related Solutions

Exercise 11-9 Preference Ranking of Investment Projects [LO11-3] Oxford Company has limited funds available for investment...
Exercise 11-9 Preference Ranking of Investment Projects [LO11-3] Oxford Company has limited funds available for investment and must ration the funds among four competing projects. Selected information on the four projects follows:    Project Investment Required Net Present Value Life of the Project (years) Internal Rate of Return (percent) A $900,000       $319,400     6           21%      B $770,000       $464,050     11           22%      C $750,000       $338,750     6           24%      D $950,000     $207,050...
A company is evaluating two independent projects for capital investment purposes. If the company has only...
A company is evaluating two independent projects for capital investment purposes. If the company has only $85 million to invest, and its required return is 10 percent by how much the company’s value will increase? All values are in millions. Project 1 Project 2 0 -50 -50 1 30 0 2 25 0 3 20 0 4 20 150 A) 52.45 million B) 26.62 million C) 79.07 million D) 60.77 million E) 45.33 million
Use of Limited Resources Northern Production Company has 200 labor-hours available. There is no limit on...
Use of Limited Resources Northern Production Company has 200 labor-hours available. There is no limit on machine-hours. Northern can sell all of Y it wants, but it can only sell 45 units and 20 units of X and Z, respectively. Product X Product Y Product Z Contribution margin per unit $30 $20 $24 Labor-hours per unit 4 5 4 Required: To maximize profits, how many units of each product should Northern produce? Product X Product Y Product Z Contribution margin...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 14 percent. Year          Project F         Project G 0 –$133,000    –$203,000    1 61,000    41,000    2 49,000    56,000    3 59,000    89,000    4 54,000    119,000    5 49,000    134,000    a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Calculate the NPV for...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 10 percent. Year Project F Project G 0 −$195,000 −$298,000 1 98,400 71,600 2 86,300 94,500 3 81,600 123,600 4 72,000 166,800 5 64,800 187,200 Calculate the payback period for both projects. Calculate the NPV for both projects. Which project, if any, should the company accept?
The following three projects are available but because of resource limitations, only one can be done....
The following three projects are available but because of resource limitations, only one can be done. The Do Nothing option is also available and the company MARR is 15%. F0 F1 F2 F3 F4 F5 A -$10,000 $5,000 $2,000 $2,500 $3,000 $3,100 B -$7,000 $2,000 $2,500 $3,000 $2,000 $1,000 C -$6,000 $2,000 $2,000 $2,500 $2,750 $3,000 a) Which project should be selected using ROR incremental analysis? b) Which project should be selected using present worth incremental analysis?
A company. has a project available with the following cash flows: Year Cash Flow 0 −$34,310...
A company. has a project available with the following cash flows: Year Cash Flow 0 −$34,310 1 12,780 2 14,740 3 20,150 4 11,420 If the required return for the project is 8.6 percent, what is the project's NPV?
A company. has a project available with the following cash flows: Year Cash Flow 0 −$31,910...
A company. has a project available with the following cash flows: Year Cash Flow 0 −$31,910 1 13,080 2 14,740 3 20,850 4 12,020 If the required return for the project is 9.6 percent, what is the project's NPV?
A company. has a project available with the following cash flows: Year Cash Flow 0 −$31,430...
A company. has a project available with the following cash flows: Year Cash Flow 0 −$31,430 1 13,140 2 14,740 3 20,990 4 12,140 If the required return for the project is 9.8 percent, what is the project's NPV? $8,619.88 $29,580.00 $15,557.89 $19,396.85 $16,972.24
contains a list of available investment projects and their respective cash flows. Using a cost of...
contains a list of available investment projects and their respective cash flows. Using a cost of capital of 10%, please answer the following questions: 1- Find the payback period, net present value and internal rate of return for each project. (Using excel to do this will save you a lot of time). 2- Based on the results, identify conflicts in ranking the above projects based on the IRR and NPV approaches, i.e. a project that has a higher rank using...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT