A company. has a project available with the following cash
flows: Year Cash Flow 0 −$34,310 1 12,780 2 14,740 3 20,150 4
11,420 If the required return for the project is 8.6 percent, what
is the project's NPV?
A company. has a project available with the following cash
flows:
Year
Cash Flow
0
−$31,430
1
13,140
2
14,740
3
20,990
4
12,140
If the required return for the project is 9.8 percent, what is the
project's NPV?
$8,619.88
$29,580.00
$15,557.89
$19,396.85
$16,972.24
Your company has a project available with the following cash
flows: Year Cash Flow 0 −$81,100 1 21,500 2 25,000 3 30,800 4
26,000 5 19,800 If the required return is 14 percent, should the
project be accepted based on the IRR?
Blinding Light Co. has
a project available with the following cash flows:
Year
Cash Flow
0
−$32,830
1
8,390
2
10,130
3
14,540
4
16,170
5
11,180
What is the project's IRR?
Multiple Choice
23.32%
24.25%
20.15%
24.87%
22.39%
Living Colour Co. has a project available with the following
cash flows:
Year
Cash Flow
0
−$34,110
1
8,150
2
9,810
3
13,980
4
15,850
5
10,700
If the required return for the project is 8.5 percent, what is
the project's NPV?
Blinding Light Co. has a project available with the following
cash flows:
Year
Cash Flow
0
−$35,390
1
7,910
2
9,490
3
13,420
4
15,530
5
10,220
What is the project's IRR?
Living Colour Co. has a project available with the following
cash flows: Year Cash Flow 0 −$32,510 1 8,450 2 10,210 3 14,680 4
16,250 5 11,300 If the required return for the project is 9.5
percent, what is the project's NPV?
$28,380.00
$15,296.43
$14,499.75
$6,206.31
$13,384.38
Filter Corp. has a project available with the following cash
flows:
Year Cash Flow 0 −$14,000 1 6,200 2 7,500 3 4,900 4 4,500 What
is the project's IRR?
Guerilla Radio Broadcasting has a project available with the
following cash flows : Year Cash Flow 0 −$15,700 1 6,400 2 7,700 3
4,500 4 4,100 What is the payback period?
A project has the following cash flows: Year Cash Flow 0 $
40,000 1 – 19,000 2 – 30,000 What is the IRR for this project? What
is the NPV of this project, if the required return is 11 percent?
What is the NPV of the project if the required return is 0 percent?
What is the NPV of the project if the required return is 22
percent?