In: Finance
The following three projects are available but because of resource limitations, only one can be done. The Do Nothing option is also available and the company MARR is 15%. F0 F1 F2 F3 F4 F5 A -$10,000 $5,000 $2,000 $2,500 $3,000 $3,100 B -$7,000 $2,000 $2,500 $3,000 $2,000 $1,000 C -$6,000 $2,000 $2,000 $2,500 $2,750 $3,000 a) Which project should be selected using ROR incremental analysis? b) Which project should be selected using present worth incremental analysis?
a) ROR = average cash inflow / cash outflow
| Cash flows | |||
| Year | A | B | C | 
| 0 | -$10,000 | -$7,000 | -$6,000 | 
| 1 | $5,000 | $2,000 | $2,000 | 
| 2 | $2,000 | $2,500 | $2,000 | 
| 3 | $2,500 | $3,000 | $2,500 | 
| 4 | $3,000 | $2,000 | $2,750 | 
| 5 | $3,100 | $1,000 | $3,000 | 
| ROR | 31.20% | 30.00% | 40.83% | 
Project C should be chosen as it has the highest ROR.
b) Present worth = sum of present values of all cash flows
| Cash flows | Cost of capital | PV of cash flows | |||||
| Year | A | B | C | A | B | C | |
| 0 | -$10,000 | -$7,000 | -$6,000 | $1 | -$10,000 | -$7,000 | -$6,000 | 
| 1 | $5,000 | $2,000 | $2,000 | $0.870 | $4,347.83 | $1,739.13 | $1,739.13 | 
| 2 | $2,000 | $2,500 | $2,000 | $0.756 | $1,512.29 | $1,890.36 | $1,512.29 | 
| 3 | $2,500 | $3,000 | $2,500 | $0.658 | $1,643.79 | $1,972.55 | $1,643.79 | 
| 4 | $3,000 | $2,000 | $2,750 | $0.572 | $1,715.26 | $1,143.51 | $1,572.32 | 
| 5 | $3,100 | $1,000 | $3,000 | $0.497 | $1,541.25 | $497.18 | $1,491.53 | 
| NPV | $760.41 | $242.72 | $1,959.06 | ||||
On basis of present worth, project C should be chosen as it has the highest NPV.