Question

In: Civil Engineering

Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running...

Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running bond pattern for the above referenced building 300 feet long, 200 feet wide and 12 feet high. Calculate only the brick units and the mortar required.

a. Total area of wall openings: 650 SF

b. Brick waste factor: 5%

c. Mortar required per 100 SF: 7.2CF/CSF

d. Mortar waste factor: 40% e. Productivity Rates: 12.0 Mason-hours/1000 brick and 13.0 Laborer-hours/1000 brick

f. Wage Rates: Masons – $28.00/hr and Laborers - $22.00/hr

g. Material Costs: Brick - $615/M and Mortar - $140/CY

GROSS WALL AREA SF /1 NET WALL AREA SF - ?

TOTAL BRICK REQUIRED BRK /1 BRICK MATERIAL COST $ LS - ?

TOTAL MORTAR REQUIRED CF /1 MORTAR MATERIAL COST $ LS - ?

TOTAL MATERIAL COST $ LS /1 MASON HOURS REQUIRED HRS - ?

LABORER HOURS REQUIRED HRS - ?

TOTAL LABOR COST $ LS - ?

TOTAL COST $ - ?

Solutions

Expert Solution

Solution as follows:

Given Data

Bricks per SF

=

6.75 bricks/SF

Brick waste factor

=

5%

Length of Building

=

300 feet

Width of Building

=

200 feet

Height of Building

=

12 feet

Total area of wall openings

=

650 SF

Mortar required per 100 SF

=

7.2 CF/CSF

Mortar waste factor

=

40%

Productivity Rates Mason

=

12.0 Mason-hours/1000 brick

Wage Rates Mason

=

$28.00/hr

Productivity Rates Labor

=

13.0 Laborer-hours/1000 brick

Wage Rates Labor

=

$22.00/hr

Material cost – brick

=

$615/M

Material cost – Mortar

=

$140/CY

Note – CSF stands for 100 Square feet

M Stand for 1000 numbers

Step 1: Calculation of total contact area of wall

Area of long walls = 2 x 300 x 12 = 7200 SF

Area of short walls = 2 x 200 x 12 = 4800 SF

Less openings = 650 SF

Total area = 7200 + 4800 – 650 = 11350 SF

Step 2: Calculation of Required quantity of bricks

Total Area = 11350 SF

Bricks per SF = 6.75

Brick Quantity = 11350 x 1.125 = 76612.50

Add Waste @ 5% of 76612.50 = 3830.63

Total Quantity of bricks required = 76612.50 + 3830.63 = 80,443.13 say 80,443 bricks

Step 3: Calculation of Required quantity of Mortar:

Total Area = 11350 SF

Mortar per CSF (1 CSF=100SF) = 7.2 CF

Mortar Quantity = 11350 x 7.2/100 = 817.20

Add Waste @ 40% of 817.20 = 326.88

Total Quantity of Mortar required = 817.20 + 326.88 = 1144.08 cubic feet

Since 1 CY = 27 CF

Total quantity of mortar required in CY = 1144.08/27 = 42.37 cubic yards

Step 4: Calculation of Required man-hours of mason:

Productivity Rates Mason = 12.0 Mason-hours/1000 Bricks

Total bricks to be installed = 76612.50

Required Mason Hours = 76612.50 x 12/1000 = 919.35 Hours

Step 5: Calculation of Required man-hours of labor:

Productivity Rates Labor = 13.0 Laborer-hours/1000 Bricks

Total bricks to be installed = 76612.50

Required Labor Hours = 76612.50 x 13/1000 = 995.96 Hours

Step 6: Cost Estimate of Wall:

Cost estimate prepared in below table:

Sl. No.

Particulars

Unit Cost

Quantity

Unit

Amount

1

Bricks

$0.615

80,443.00

Each

$49,472.45

2

Mortar

$140.00

42.37

CY

$5,931.80

3

Mason

$28.00

919.35

hours

$25,741.80

4

Labor

$22.00

995.96

hours

$21,911.12

Total cost for the job

$ 103,057.17

if you have any doubts pls comments below , i will be there to help you , don't forget to rate its help me alot, please dont give the down rating it will be effects me if you have any doubt i will definitely clarify.

thank you ... !!


Related Solutions

Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following...
Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following information: a. Size of the building: 32 feet long and 18 feet wide b. Spacing of floor joists: 2 feet on center c. Double joist on ends plus joist header and footer d. Size of floor joists: 18 feet long of 2x8 lumber e. Productivity Rate: Lumber - 20 crew-hrs/MBFM and Plywood - 12 crew-hrs/MSF f. Crew’s Wage Rate: $27.50/wk-hr g. Material Costs: Lumber...
Calculate the total foot board measure and calculate the total cost for furnishing and installing the...
Calculate the total foot board measure and calculate the total cost for furnishing and installing the following pieces of dimensional lumber: a. 270 – 2 x 4 – 8’0” 550 – 2 x 6 – 16’0” 1,820 – 2 x 4 – 12’0” 500 – 2 x12 – 16’0” b. Productivity Rate: Lumber - 15 crew-hrs/MBFM c. Crew’s Wage Rate: $26.75/wk-hr d. Material Costs: Lumber - $550/MBFM TOTAL BOARD REQUIRED BFM -? TOTAL MATERIAL COST $ LS - ? CREW...
 Estimate a Total Benefit and Total Cost formula for your product. In Excel, produce a...
 Estimate a Total Benefit and Total Cost formula for your product. In Excel, produce a chart that shows both functions with 50 data points (i.e. A=1…50). You decide what is A in your case (i.e. number of workers, hours of labor, etc. This is important because is going to determine your costs and profit).
Shatner Inc. has decided to use the high-low method to estimate the total cost and the...
Shatner Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost. The data for various levels of production are as follows: Units Produced Total Costs 5,945 $436,240 3,820 415,670 1,845 280,440 a. Determine the variable cost per unit and the total fixed cost. Variable cost: (Round to the nearest dollar.) $ per unit Total fixed cost: $ b. Based on part (a), estimate the total cost...
Ziegler Inc. has decided to use the high-low method to estimate the total cost and the...
Ziegler Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost. The data for various levels of production are as follows: Units Produced Total Costs 1,260 $221,760 2,610 277,690 4,060 344,960 a. Determine the variable cost per unit and the total fixed cost. Variable cost: (Round to the nearest dollar.) $ per unit Total fixed cost: $ b. Based on part (a), estimate the total cost...
A cost accountant has derived the following data on the weekly output of standard size boxes...
A cost accountant has derived the following data on the weekly output of standard size boxes from a factory. Week Output (thousands) Total cost (thousand dollars) 1 20 60 2 2 25 3 4 26 4 23 66 5 18 49 6 14 48 7 10 35 8 8 18 9 13 40 (a) Determine the regression equation from which we can predict the total cost in terms of the weekly production. (4%) (b) In the following week it is...
A company would like to estimate its total cost equation. It has collected 48 months of...
A company would like to estimate its total cost equation. It has collected 48 months of monthly production output and corresponding total production costs. The collected data is in the file Production Cost Data Only.xlsx. Recall that TOTAL COST = Fixed Costs + Variable Cost per Unit *Output. Use the data to estimate a function that describes total cost for this company. (Round answers to 2 decimal places) State the estimated total cost function. What is the estimated Fixed Cost...
A company would like to estimate its total cost equation. It has collected 48 months of...
A company would like to estimate its total cost equation. It has collected 48 months of monthly production output and corresponding total production costs.  The collected data is in the file Production Cost Data Only.xlsx. Recall that TOTAL COST = Fixed Costs + Variable Cost per Unit *Output. Use the data to estimate a function that describes total cost for this company. (Round answers to 2 decimal places) Develop a scatterplot of the two variables: monthly output and monthly total costs....
A friend owns a hotel that gets a lot of seasonal business. The average total cost per day of running the hotel is $75
A friend owns a hotel that gets a lot of seasonal business. The average total cost per day of running the hotel is $75. She tells you that during the off-season (when there are a lot of empty rooms), she had someone offer her $70 for a room. She indignantly tells you she turned the offer down since it was less than her average cost. Was that a good decision? Explain your answer in detail.
Difference between Means, Sample size selection. Explain Confidence Interval for a Mean, Total, Proportion, Standard Deviation....
Difference between Means, Sample size selection. Explain Confidence Interval for a Mean, Total, Proportion, Standard Deviation. Methods of Selecting Random Samples.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT