Question

In: Civil Engineering

Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following...

Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following information:

a. Size of the building: 32 feet long and 18 feet wide

b. Spacing of floor joists: 2 feet on center

c. Double joist on ends plus joist header and footer

d. Size of floor joists: 18 feet long of 2x8 lumber

e. Productivity Rate: Lumber - 20 crew-hrs/MBFM and Plywood - 12 crew-hrs/MSF

f. Crew’s Wage Rate: $27.50/wk-hr

g. Material Costs: Lumber - $550/MBFM and Plywood - $1,100/MSF

TOTAL BOARD REQUIRED BFM -?

TOTAL PLYWOOD REQUIRED SF - ?

LUMBER MATERIAL COST $ LS -?

PLYWOOD MATERIAL COST $ LS -?

TOTAL MATERIAL COST $ LS -?

TOTAL LABOR COST $ LS - ?

TOTAL COST $ LS - ?

Solutions

Expert Solution

Step 1: Calculation of length of joists along the short edge:

Given Data:

· Size of the building: 32’ x 18’

· Spacing of floor joists: 2’ O.C.

· Double joist on ends plus joist header and footer

· Size of floor joists: 18’ x 2” x 8”

Total number of joists including end joists = 15 + 2 x 2 = 19 numbers

Length of each joist = 18’

Total Length = 19 x 18 = 342 ft

Step 2: Calculation of length of joist header and footer:

Given Data:

· Size of the building: 32’ x 18’

· Spacing of floor joists: 2’ O.C.

· Double joist on ends plus joist header and footer

· Size of floor joists: 18’ x 2” x 8”

Length of each header and footer = Length of building = 32’

Header and footer will be provided one at each end.

Hence total length of joist header and footer = 2 x 2 x 32 = 128 ft

Step 3: Total Board Feet measure (BFM) and MBFM (Thousand Board feet measure) of lumber:

Given Data:

· Length of floor joists along short edge= 342’

· Length of joists for header and footer = 128’

1 Board feet = 1 ft x 1 ft x 1 in

Hence,

Total MBFM = BFM/1000 = 626.67/1000 = 0.6267 MBFM

Step 4: Calculation of Square feet (SF) and MSF (Thousand Square feet) of plywood:

Given Data:

· Size of the building: 32’ x 18’

SF of plywood = Plan area of building = 32 x 18 = 576 SF

Total MSF = SF/1000 = 576/1000 = 0.5760 MSF

Step 5: Calculation of required crew hours:

Given Data,

· Total quantity Lumber = 0.6267 MBFM

· Total quantity plywood = 0.5760 MSF

· Productivity Rate Lumber - 20 crew-hrs/MBFM

· Productivity Rate Plywood - 12 crew-hrs/MSF

Required crew hours for lumber fixing = 20 x 0.6267 = 12.53 hours

Required crew hours for plywood fixing = 12 x 0.576 = 6.91 hours

Total crew hours = 12.53 + 6.91 = 19.44 hours

Step 3: Cost Estimate:

Given Data:

· Crew’s Wage Rate: $27.50/wk-hr

· Material Costs Lumber - $550/MBFM

· Material Costs Plywood - $1,100/MSF

Cost estimate prepared in below table:

Sl. No.

Particulars

Unit Cost

Quantity

Unit

Amount

1

Material Lumber

$550.00

0.6267

MBFM

$344.69

2

Material Plywood

$1,100.00

0.5760

MSF

$633.60

3

Labor for fixing lumber and plywood

$27.50

19.44

hr

$534.60

Total cost for the job

$1,512.89

if you have any doubts pls comments below , i will be there to help you , don't forget to rate its help me alot, please dont give the down rating it will be effects me if you have any doubt i will definitely clarify.

thank you ... !!


Related Solutions

Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running...
Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running bond pattern for the above referenced building 300 feet long, 200 feet wide and 12 feet high. Calculate only the brick units and the mortar required. a. Total area of wall openings: 650 SF b. Brick waste factor: 5% c. Mortar required per 100 SF: 7.2CF/CSF d. Mortar waste factor: 40% e. Productivity Rates: 12.0 Mason-hours/1000 brick and 13.0 Laborer-hours/1000 brick f. Wage Rates:...
Calculate the total foot board measure and calculate the total cost for furnishing and installing the...
Calculate the total foot board measure and calculate the total cost for furnishing and installing the following pieces of dimensional lumber: a. 270 – 2 x 4 – 8’0” 550 – 2 x 6 – 16’0” 1,820 – 2 x 4 – 12’0” 500 – 2 x12 – 16’0” b. Productivity Rate: Lumber - 15 crew-hrs/MBFM c. Crew’s Wage Rate: $26.75/wk-hr d. Material Costs: Lumber - $550/MBFM TOTAL BOARD REQUIRED BFM -? TOTAL MATERIAL COST $ LS - ? CREW...
Given the following total cost schedule of a firm, derive the total fixed cost and total...
Given the following total cost schedule of a firm, derive the total fixed cost and total variable cost schedules of the firm, and from them derive the average fixed cost, average variable cost, average total cost, and marginal cost schedules of the firm. Q1. Answer question above using the table below: Quantity TC($) TFC TVC AFC AVC   ATC MC 0 1 2 3 4 5    Q 0 1 2 3 4 5 TC $30 50 60 81 118 180
1. Given the following information: a. Parent sells Sub inventory with a cost of $45,000 for...
1. Given the following information: a. Parent sells Sub inventory with a cost of $45,000 for $55,000. Sub then sells this inventory to outsiders for $70,000. b. Parent sells Sub inventory with a cost of $15,000 for $20,000, which remains on hand in Sub’s ending inventory. a.Calculate unrealized profits . b.Pass eliminating entry in both the cases: 1.Parent sells to Sub and Sub to Outsider 2. Parent sells to Sub, but Sub not yet to Outsider c.How would it effect...
Advanced financial accounting: Given the following information:- 1-Parent sells Sub inventory with a cost of $45,000...
Advanced financial accounting: Given the following information:- 1-Parent sells Sub inventory with a cost of $45,000 for $55,000.  Sub then sells this inventory to outsiders for $70,000. 2-Parent sells Sub inventory with a cost of $15,000 for $20,000, which remains on hand in Sub’s ending inventory. Calculate unrealized profits . a-Pass eliminating entry in both the cases: b-Parent sells to Sub and Sub to Outsider c- Parent sells to Sub, but Sub not yet to Outsider d-How would it effect Parents...
Consider total cost and total revenue, given in the following table: In the final column, enter...
Consider total cost and total revenue, given in the following table: In the final column, enter profit for each quantity. (Note: If the firm suffers a loss, enter a negative number in the appropriate cell.) Problems and Applications Q4 Ball Bearings, Inc., faces costs of production as follows: Quantity Total Fixed Costs Total Variable Costs (Dollars) (Dollars) 0 100 0 1 100 50 2 100 70 3 100 90 4 100 140 5 100 200 6 100 360 Complete the...
The total and marginal cost functions for a typical sub-bituminous coal producer are: T C =...
The total and marginal cost functions for a typical sub-bituminous coal producer are: T C = 75, 000 + 0.1Q 2 MC = 0.2Q where Q is measured in railroad cars per year. The industry consists of 55 identical producers. The market demand curve is: QD = 140, 000 − 425P where P is the price per carload. The market can be regarded as competitive. (a) Calculate the short run equilibrium price and quantity in the market. Calculate the quantity...
 Estimate a Total Benefit and Total Cost formula for your product. In Excel, produce a...
 Estimate a Total Benefit and Total Cost formula for your product. In Excel, produce a chart that shows both functions with 50 data points (i.e. A=1…50). You decide what is A in your case (i.e. number of workers, hours of labor, etc. This is important because is going to determine your costs and profit).
Given the following data       Output        Total cost output total cost 0 6 1 14 2 20...
Given the following data       Output        Total cost output total cost 0 6 1 14 2 20 3 24 4 32 5 45 6 60 What is the value of total fixed cost? _______ What is the value of total variable cost when output= 4? _______ What is the value of average total cost when output equals 6?______ What is the marginal cost of the fifth unit?_______ AT what level of output is marginal cost at its minimum value? _____
ou are given the following total cost and total benefit curves regarding a lumber development project....
ou are given the following total cost and total benefit curves regarding a lumber development project. TB = 400Q − 2Q2 TC = 20Q (c) Compute the total costs, total benefits, and net benefits in optimum. (d) Compute and interpret the benefit/cost ratio. What policy recommendation would you make regarding the initiation of the project? (e) Present your solution graphically. (f) Now assume that both benefits and costs occur once a year for three years (and are identical in each...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT