Question

In: Civil Engineering

Calculate the total foot board measure and calculate the total cost for furnishing and installing the...

Calculate the total foot board measure and calculate the total cost for furnishing and installing the following pieces of dimensional lumber:

a. 270 – 2 x 4 – 8’0” 550 – 2 x 6 – 16’0” 1,820 – 2 x 4 – 12’0” 500 – 2 x12 – 16’0”

b. Productivity Rate: Lumber - 15 crew-hrs/MBFM

c. Crew’s Wage Rate: $26.75/wk-hr

d. Material Costs: Lumber - $550/MBFM

TOTAL BOARD REQUIRED BFM -?

TOTAL MATERIAL COST $ LS - ?

CREW HOURS REQUIRED HRS -?

TOTAL LABOR COST $ LS -?

TOTAL COST $ LS - ?

Solutions

Expert Solution

Step 1: Total Board Feet measure (BFM) and MBFM (Thousand Board feet measure) of lumber:

1 Board feet = 1 ft x 1 ft x 1 in

Hence,

Total BFM = 1440 + 8800 + 14560 + 16000 = 40,800 BFM

Total MBFM = 40,800/1000 = 40.8 MBFM

Step 2: Calcualtion of required crew hours:

Given Data,

· Productivity Rate: Lumber - 15 crew-hrs /MBFM

· Total quantity = 40.8 MBFM

Required crew hours = 15 x 40.8 = 612.00 Crew hours

Step 3: Cost Estimate of Lumbers:

Cost estimate prepared in below table:

Sl. No.

Particulars

Unit Cost

Quantity

Unit

Amount

1

Material

$550.00

40.80

MBFM

$22,440.60

2

Labor

$26.75

612.00

hr

$16,371.00

Total cost for the job

$38,811.00

if you have any doubts pls comments below , i will be there to help you , don't forget to rate its help me alot, please dont give the down rating it will be effects me if you have any doubt i will definitely clarify.

thank you ... !!


Related Solutions

Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running...
Estimate the total cost for furnishing and installing standard size brick (6.75 bricks/SF) in a running bond pattern for the above referenced building 300 feet long, 200 feet wide and 12 feet high. Calculate only the brick units and the mortar required. a. Total area of wall openings: 650 SF b. Brick waste factor: 5% c. Mortar required per 100 SF: 7.2CF/CSF d. Mortar waste factor: 40% e. Productivity Rates: 12.0 Mason-hours/1000 brick and 13.0 Laborer-hours/1000 brick f. Wage Rates:...
Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following...
Estimate the total cost for furnishing and installing floor joist and plywood sub-flooring given the following information: a. Size of the building: 32 feet long and 18 feet wide b. Spacing of floor joists: 2 feet on center c. Double joist on ends plus joist header and footer d. Size of floor joists: 18 feet long of 2x8 lumber e. Productivity Rate: Lumber - 20 crew-hrs/MBFM and Plywood - 12 crew-hrs/MSF f. Crew’s Wage Rate: $27.50/wk-hr g. Material Costs: Lumber...
You're considering installing a 4-foot-high by 8-foot-wide picture window in a north-facing wall (no solar gain)...
You're considering installing a 4-foot-high by 8-foot-wide picture window in a north-facing wall (no solar gain) that now has a total R (specific thickness of material) value of 23. As a compromise between initial cost and energy savings, you've chosen a standard double-glazed window with the value of R is 2.0. As a result of installing this window, how much more oil will you burn in a 6-month winter heating season with an average outdoor temperature of 25F and an...
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the...
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the mean annual sales per square foot was $390 with a standard deviation of $45.83. Suppose you take a random sample of 49 Foot Locker stores operating last year. There is a 16% probability that the sample mean annual sales per square foot is at most $______. a. 435.3717 b. 344.6283 c. None of the answers is correct d. 383.5183 e. 396.4817
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the...
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the mean annual sales per square foot was $410 with a standard deviation of $54.38. Suppose you take a random sample of 36 Foot Locker stores operating last year. There is a 3% probability that the sample mean annual sales per square foot is at most $______. a. None of the answers is correct b. 307.7656 c. 512.2344 d. 427.0391 e. 392.9609
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the...
Foot Locker uses sales per square foot as a measure of store productivity. Last year, the mean annual sales per square foot was $370 with a standard deviation of $38.54. Suppose you take a random sample of 64 Foot Locker stores operating last year. There is a 86% probability that the sample mean annual sales per square foot is at least $______. a. None of the answers is correct b. 375.2029 c. 364.7971 d. 328.3768 e. 411.6232
Give examples of how to calculate total revenue, total cost, variable cost, fixed cost, marginal cost,...
Give examples of how to calculate total revenue, total cost, variable cost, fixed cost, marginal cost, ATC, AFC, and AVC. What is the water-diamond paradox?
1. Calculate the weighted unit cost per square foot for the project data shown below, and...
1. Calculate the weighted unit cost per square foot for the project data shown below, and determine the cost of a 30,000-sf project. 2. Determine the relationship between unit cost and size for the project data above, and use it to estimate the cost of a 25,000-sf project. 3. Use the time and location indices presented during Class10 to estimate the cost of a building that contains 48,000 sf of floor area. The building is to be constructed 3 years...
I'm having trouble calculating total cost. The question is: Calculate the total cost for next February...
I'm having trouble calculating total cost. The question is: Calculate the total cost for next February when 1,300 tons are expected to be extracted. I understand that trucking and hauling will be 144,970, and I also add 20,000 for depreciation, im not sure about the other costs and how to add. Antioch Extraction, which mines ore in Montana, uses a calendar year for both financial-reporting and tax purposes. The following selected costs were incurred in December, the low point of...
From the following information on costs of production, calculate Total Fixed Cost, Total Variable Cost, Average...
From the following information on costs of production, calculate Total Fixed Cost, Total Variable Cost, Average Variable Cost, and Marginal Cost. I also need to graph the total cost curves as well as the average and marginal cost curves. TC = TFC + TVC so for Q=1 TC=30, assume TFC=20 so TVC=10 (20+10=30); continue with logic about FC, it is independent of output, so it would be an incremental 20 with each additional level of output, TVC for each Q...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT