Question

In: Civil Engineering

Need a good explanationIf a new railroad embankment is to be constructed in an area...

If a new railroad embankment is to be constructed in an area that restricts how wide its base may be, name some of the design alternatives you would consider to limit the embankment width at its base.

Solutions

Expert Solution

Alternative 1 : Move the entire railway yard area to some other location where hydrogeological conditions were more acceptable. This alternative wouid not be attractive at this late stage of design because fresh land negotiations and other permit requirements would delay the project.

Alternative 2: Rearrange the railway yard configuration by avoiding the area where bedrock is at shallow depths and has high piezometric pressures. This meant the railway yard would be relocated along the eastern boundary of the property and extend northwards beyond the existing railway yard limits.

Alternative 3: Raise the elevation of the entire railway yard. This would avoid cutting into high pressured bedrock surface and would also provide enough surcharge to counteract piezometric pressures in the bedrock. Local trafficability problems in soft areas due to water could be solved by providing proper drainage and gravel blanket over geotextile fabric.


Related Solutions

A road embankment will be constructed using clayey sand from a local borrow excavation. The embankment...
A road embankment will be constructed using clayey sand from a local borrow excavation. The embankment has a volume of 100,000 cubic meters. Specifications require the soil to be compacted to at least 95 percent of the maximum dry density obtained in a Standard Proctor test (i.e., relative compaction, RC greater than or = 95%). It is estimated that the as-constructed embankment will be at an average RC of 97% since the contractor must meet or exceed this specification. Standard...
You suspect that a railroad embankment is unstable and exhibiting a slip failure. To confirm this...
You suspect that a railroad embankment is unstable and exhibiting a slip failure. To confirm this and to monitor the conditions, what instrumentation and testing do you consider using and why? What soil exploration would you consider?
A water harvesting pond is to be constructed by constructing an embankment across a narrow valley....
A water harvesting pond is to be constructed by constructing an embankment across a narrow valley. The top width of the embankment is kept at 3.6 m. using the information in the Table Q8, and taking the upstream and downstream side slopes as 3:1 and 2:1 respectively, a settlement allowance of 12.5%: .       Fill up the table and estimate the earth volume required to construct the dam. Show sample calculations only. .     Sketch the plan view, longitudinal section and centre...
1A. Identify a new project that has been constructed in your area. Who was the lead...
1A. Identify a new project that has been constructed in your area. Who was the lead design firm? Identify the subconsultants/designers hired by this firm. Identify the training and/or registration of the key designers that were used on the project. B.Within the Architecture-Engineering-Construction (AEC) industry you hear the terms project Manager and program Manager used. Do some research and describe the difference. C. Visit a job site and identify the trades that are presently working there. Write up a description...
A new, wide highway embankment is planned across a relatively recent deposit of doubly-drained, saturated clay...
A new, wide highway embankment is planned across a relatively recent deposit of doubly-drained, saturated clay soil with cv = 5E-8 m2/sec. The settlement analysis of the 10 m thick clay layer yielded an estimated consolidation settlement of 800 mm for the new embankment loading. Determine and plot the settlement of the clay layer (as measured at the ground surface) at 0, 0.49, 3.12, 6.39, 13.44, and 18.44 years.
A raft is constructed of wood having a density of 6.00x102 kg/m3. Its surface area is...
A raft is constructed of wood having a density of 6.00x102 kg/m3. Its surface area is 5.50 m2 and its volume is 0.55 m3. When the raft is placed in fresh water, to what depth h is the raft submerged by its weight? The density of fresh water is 1000 kg/m3. Hint: Use Newton’s second to sum the forces (Buoyancy and weight) that are in equilibrium.
In Railroad Geotechnical Engineering, please give a correct answer and good explanation Define “Critical Speed” related...
In Railroad Geotechnical Engineering, please give a correct answer and good explanation Define “Critical Speed” related to a train inducing a large ground-borne vibration.
A new bridge is to be constructed over the East River in New York City. Two...
A new bridge is to be constructed over the East River in New York City. Two structural possibilities exist: the support could be in the shape of a parabola or the support could be in the shape of a semi-ellipse. The space between the supports needs to be 1050 feet. The height at the center of the arch needs to be 350 feet. Determine the equation of a parabola with these characteristics. (Hint: Place the vertex of the parabola at...
Managers of the New Hope and Ivyland Short Line Railroad conducted and experiment in which they...
Managers of the New Hope and Ivyland Short Line Railroad conducted and experiment in which they reduced fares by about 28% for approximately a year to estimate the price elasticity of demand. This large fare reduction resulted in essentially no change in the railroad’s revenues. Take a face value, what seemed to be the price elasticity of demand?
A new highway is to be constructed with two alternative designs. Design A calls for a...
A new highway is to be constructed with two alternative designs. Design A calls for a concrete pavement costing $90 per foot with a 20-year life; two paved ditches costing $3 per foot each; and three box culverts every mile, each costing $9,000 and having a 20-year life. Annual maintenance will cost $1,800 per mile; the culverts must be cleaned every five years at a cost of $450 each per mile. Design B calls for a bituminous pavement costing $45...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT