Question

In: Economics

Suppose that an electricity provider would build a power plant at the cost of $50 million....

Suppose that an electricity provider would build a power plant at the cost of $50 million. Once the plant is built, it would cost the plant $0.07 per kilowatt hour of electricity that it produces. Over its lifetime, the plant is expected to generate 100 million kilowatt hours. Suppose that the regulators believe that the investors who put up capital to build the plant should be able to recoup its investment plus a 300% return throughout the life of the plant. Calculate the price per kilowatt hour that the regulators should allow the plant operators should charge.

Solutions

Expert Solution

As investors want torecoup their investment plus a 300% return on investment would mean that they want a total of $200 million to be recovered from this investment plus the plant also has to cover its electricity production costs which comes out to be $7 million for 100 million kilowatt hours(KWH) produced. Thus, the plant would have to recover atleast(with great emphasis on atleast) $207 million over the lifetime of the firm which will come out to be $2.07 per kilowatt hour to be charged from customers to recover all the costs .

the plant should charge atleast $2.07/KWH.


Related Solutions

Namibia power company Ltd (Nam power) is a provider of electricity power and has 30 September...
Namibia power company Ltd (Nam power) is a provider of electricity power and has 30 September as its year-end. Its functional currency is Namibian dollar On 1 July 2016, Nam Power ordered goods from at a cost of €75 000. The goods were shipped on 16 July 2016 to the destination point and were received in Windhoek on 1 August 2016. The suppliers invoice was settled on 31 October 2016. The transactions were done on CIF basis. The following exchange...
A power plant that supplies a community with electricity costs $1 billion to build, lasts 25 years, and has an annual operating cost of $0.2 billion
A power plant that supplies a community with electricity costs $1 billion to build, lasts 25 years, and has an annual operating cost of $0.2 billion; it costs $0.1 billion to decommission the plant at the end of its lifetime (25 years). (Assume that the construction costs and the operating costs are paid at the beginning of the period, and that the decommissioning cost is paid at the end of the life of the plant.) The annual discount rate is...
A proposed nuclear power plant will cost $1.7 billion to build and then will produce cash...
A proposed nuclear power plant will cost $1.7 billion to build and then will produce cash flows of $250 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $850 million. What is project NPV if the discount rate is 5%? What if it is 18%? (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Enter your answers in billions rounded to 3 decimal places.)...
A proposed nuclear power plant will cost $2.9 billion to build and then will produce cash...
A proposed nuclear power plant will cost $2.9 billion to build and then will produce cash flows of $370 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $970 million. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Enter your answers in billions rounded to 3 decimal places.) a. What is project NPV if the discount rate is 4%? b. What if the...
A proposed nuclear power plant will cost $1.9 billion to build and then will produce cash...
A proposed nuclear power plant will cost $1.9 billion to build and then will produce cash flows of $270 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $870 million. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Enter your answers in billions rounded to 3 decimal places.) a. What is project NPV if the discount rate is 4%? b. What if the...
An auto plant that costs $50 million to build can produce a new line of cars...
An auto plant that costs $50 million to build can produce a new line of cars that will produce net cash flow of $35 million per year if the line is successful, but only $1 million per year if it is unsuccessful. You believe that the probability of success is about 20 percent. The auto plant is expected to have a life of 12 years and the opportunity cost of capital is 10 percent. What is the expected net present...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity...
If a coal-fired power plant burns 2 kg of coal to produce electricity, and the electricity is used to power an elevator motor that is 60% efficient, how high can the elevator and passengers be lifted up if their total mess is 1500 kg? and then How many human workers using muscle power('energy servants") would be needed to lift the elevator up to the same height, if they had one minute to do so? Assuming that one energy servant is...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four...
            The Fukushima Power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15 In the following, all the future costs and earnings have been adjusted to their present worth: If a...
Consider the case of a power plant that, in the process of generating electricity, it also...
Consider the case of a power plant that, in the process of generating electricity, it also emits noxious pollutants. It has been argued that this situation represents a market failure. a. Briefly explain, using a graph, what are the economic foundations of this argument? b. Using the graph in (a) show what are the economic implications of this case c. What economic mechanism would you suggest to correct for this market failure? d. In general, why market forces, do not...
A power plant is planning construction of a new plant to generate electricity four years hence...
A power plant is planning construction of a new plant to generate electricity four years hence and must decide now between a small, medium, or large-sized plant. The exact size needed is uncertain because future demands can only be estimated. Forecasters have estimated future demands and their likelihoods as follows: Level of Demand Probability High 0.30 Medium 0.55 Low 0.15             In the following, all the future costs and earnings have been adjusted to their present worth: The capacity of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT