Develop a Gantt Chart based on Table below.
On the same Gantt chart, use a legend to show the project plan
and the (actual) project progress.
Discuss the significance of the two paths or what they mean to
the project.
Activity
immediate predecessors
normal time
budget
organizational unit
percent complete
A
-
4
$90
U1
100
B
A
2
$35
U2
100
C
A
6
$75
U2
40
D
B
3
$60
U1
80
E
C
10
$80
U1
0...
discuss how using a Gantt chart in a project charter can be an
effective method in project management. Please provide a case study
to demonstrate your point. OR, this can be based on experience. If
you are basing this on experience, you will need to be able to cite
the project and share its details.
1. What is the difference between a Gantt chart and a PERT chart in
the production management?
2. How is the marketing concept tied to the relationship and social
eras of marketing?
3. What are the Marketing mix and how does business apply them into
the markets?
Draw a Gantt chart for A Computerised Administrative System.
It Is a new project for a computerised Human Resource
Information system. The company is switching to paper less.
A WBS has to be created/invented for the new project
Compare the main strengths and weaknesses of the Gantt chart and
PERT for project management, and give your opinion on which you
believe is the most effective for project management.
For the following processes, given the description, draw the
Gantt chart and paste the picture in the answer doc. What is the
waiting time and turnaround time of each process and what is the
average waiting time and turnaround time.
Preemptive SJF
Process
AT
BT(millisecs)
P1
1
1
P2
0
2
P3
5
3
P4
4
4
P5
3
5
Discuss (in a paragraph below) the benefits of using a GANTT
chart for managing a project.
Outline the six main steps of the PERT method for project
management.
Explain why it is important to consider project budgets and
other resources in project design.
1. What are the strengths and weaknesses of using a Gantt chart
for representing a project plan? How about a Network diagram and a
PERT diagram? When they should be used ? Is one method “better”
than the other? Should we combine them together?
Please No handwritten work.