Question

In: Finance

Roads Ltd is a construction company that builds roads and related civil projects. The company recently...

Roads Ltd is a construction company that builds roads and related civil projects. The company recently faced increased calls from investors to pay dividends due to the perceived lack of new profitable projects in a low growth economy. The company has, in spite of weak business sentiment, maintained a stable profit margin. At a recent meeting, the board resolved to adopt a residual approach to dividend payments. You have been tasked with recommending the dividend that should be paid at the end of the 2018 financial year. The company expects to have earnings available to common shareholders of R 60 million and it will have five million shares in issue at the end of the financial year. Its project schedule for the next financial year is as follows: Project A B C D IRR 18% 15% 14% 11% Cost (Rm) 20 15 21 16 The company has a WACC of 8% and a target debt ratio of 60%. Required: Determine the amount of earnings available to common shareholders that could be paid out as a divided according to the residual policy. Create a brief report for the board showing the projects that would be undertaken and also determine the dividend that could be paid.

Solutions

Expert Solution

To The Board of Directors,

Roads Ltd.

Sub : Capital Projects investment for next year and Dividend payment as per residual policy

Dear Madam/Sirs,

As we are going through the review of or dividend distribution policy for 2018 end , we have gone through the potential investment projects for next year that need equity investment. We have 4 projects with IRR over WACC of 8% and we maintain the Debt Equity Ratio of 60:40 for the investment in the projects. The summary of the projecst and the Equity investments required are availble in the working below. After fulfilling the Equity investment needs , we will have R31.2M residual income available for the common stock holders . The EPS in the residual approach will be R6.24 per common share.

Submitted for your review of the working and approval of the residual dividend payout .

Yours sincerely

XYZ.

Working :

FY 2018: Amount in Rm
Earnings Available for Common Shareholders                              60
Project schedule for next financial Year Project A   Project B Project C Project D   Total
IRR 18% 15% 14% 11%
Investment Required (Cost Rm)                              20 15 21 16                   72.00
Required Investment from Equity @40%(Rm)                           8.00                           6.00                          8.40                               6.40                   28.80
WACC of Capital Investment =8%
As the IRR of all the Projects are above the cost of capital , all the projects should be accepted for investment.
The Equity Investment required for the projects=                        28.80
Surplus Income available for Common Shareholders after meeting the Capital Investment needs=Rm                        31.20
Common shares outstanding in million                                5
EPS = (R )                           6.24

Related Solutions

CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion...
CCS is a construction company that builds roads in the Northwest Territories (NWT). CCS uses the percentage-of-completion method and measures completion on the basis of kilometres completed. In November 20X9, CCS signed an agreement with the NWT government to build 50 kilometres of new road for a total cost of $40 million. The contract would likely take three years to complete and would start in the spring of 20X10. Over the next three years, 15 kilometres were completed in 20X10,...
Provide 3 areas in Engineering Grand Challenges that are highly RELATED to Civil Engineering or Construction...
Provide 3 areas in Engineering Grand Challenges that are highly RELATED to Civil Engineering or Construction Engineering Management fields. Why are they associated with CECEM?
Friendly Cabinet Makers is a company that builds cabinets for houses. The company recently employed a...
Friendly Cabinet Makers is a company that builds cabinets for houses. The company recently employed a new building technique that is supposed to save time over the old method which had a mean of 6.5 hours. Friendly Cabinet Makers wants to determine if the new method actually saves time. A random sample was taken of number of hours to build a cabinet. At the .05 significance level, can Friendly Cabinet Makers conclude that the new method is faster? Using the...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 – B 10 – C 1 – D 8 B E 10 B F 9 B G 3 A, D H 7 A, D J 3 F K 8 E, H L 4 C, J How long the project will take?    State the...
The Charming City Construction Company is considering six projects. The projects, the number of supervisors and...
The Charming City Construction Company is considering six projects. The projects, the number of supervisors and the number of workers required for each project, and the expected profits for each project are given below. Project 1 2 3 4 5 6 ________________________________________________________________ Supervisors Required 5 4 6 3 4 2 Workers Required 15 24 35 22 26 32 Profit (in thousands of dollars) 210 290 330 240 300 200 The objective is to maximize the company's total expected profit subject...
Joe is the sole director and shareholder of Homes Building Pty Ltd, a company that builds...
Joe is the sole director and shareholder of Homes Building Pty Ltd, a company that builds prestigious homes in Perth, Western Australia by mainly using sub-contractors and a few employees. Joe knew that due to the downturn in the building industry, the company’s business was in trouble. For the last 6 to 8 months, Joe had been making late payments to his sub-contractors and had accrued $200,000 in overdue payments. Joe had also missed some payments to the Australian Taxation...
QUESTION 1: CONSTRUCTION/CIVIL FRAUD A major infrastructure company, Mega Construction Corp. had been awarded a road...
QUESTION 1: CONSTRUCTION/CIVIL FRAUD A major infrastructure company, Mega Construction Corp. had been awarded a road construction contract by the government. For execution of the project, the company had sub-divided the geographies and execution areas and invited bids for the sub-contracting. The company had publicized a whistle-blower policy and received a complaint from one of the bidders about possible collusion between certain bidders. The matter was sought to be investigated by the management of the company. As the company’s fraud...
6. The Charming City Construction Company is considering six projects. The projects, the number of supervisors...
6. The Charming City Construction Company is considering six projects. The projects, the number of supervisors and the number of workers required for each project, and the expected profits for each project are given below.                                                                                       Project                                                                  1           2           3           4           5           6            ________________________________________________________________             Supervisors Required                 5            4           6           3           4           2           Workers Required                      15          24         35         22        26         32           Profit (in thousands of dollars) 210        290       330       240      300      200...
6. The Charming City Construction Company is considering six projects. The projects, the number of supervisors...
6. The Charming City Construction Company is considering six projects. The projects, the number of supervisors and the number of workers required for each project, and the expected profits for each project are given below.                                                                                       Project                                                                  1           2           3           4           5           6            ________________________________________________________________             Supervisors Required                 5            4           6           3           4           2           Workers Required                      15          24         35         22        26         32           Profit (in thousands of dollars) 210        290       330       240      300      200...
Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry....
Construction codes and specifications Discuss the importance of documentation in the construction and civil engineering industry. What method(s) are used to ensure proper documentation during construction?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT