Question

In: Accounting

Net Present Value ApproachB7:H23 Time Period 0 1 2 3 4 5 Cash Flow Purchase Price...


Net Present Value ApproachB7:H23
Time Period 0 1 2 3 4 5
Cash Flow
Purchase Price $      (70,000)
Labor Savings 20,000 20,000 20,000 20,000 20,000
Paint Savings 2,000 2,000 2,000 2,000 2,000
Maintenance -1000 (1,000) (1,000) (1,000) (1,000) (1,000)
Residual Value 5,000 5,000
Total Cash Flow $      (70,000) 21,000 21,000 21,000 21,000 26,000
PV Factor 1 0.893 0.797 0.712 0.636 0.567
Total Cash Flow $      (70,000) $        18,753 $      16,737 $        14,952 $       13,356 $        14,742
Required Rate of Return 12%=0.12
NPV $          8,540 NPV Using Excel (show formula): $          8,540
IRR IRR Using Excel (show formula): Can you please write out how to find IRR? Thank you so much

Solutions

Expert Solution

Net Present Value ApproachB7:H23
Time Period 0 1 2 3 4 5
Cash Flow
Purchase Price -70,000
Labor Savings 20,000 20,000 20,000 20,000 20,000
Paint Savings 2,000 2,000 2,000 2,000 2,000
Maintenance -1000 -1,000 -1,000 -1,000 -1,000 -1,000
Residual Value 5,000 5,000
Total Cash Flow -70,000 21,000 21,000 21,000 21,000 26,000
PV Factor 1 0.893 0.797 0.712 0.636 0.567
Total Cash Flow -70,000 18,753 16,737 14,952 13,356 14,742
Required Rate of Return 12%
NPV 8,540 NPV Using Excel (show formula): $          8,540
IRR 16.68% IRR Using Excel (show formula): Can you please write out how to find IRR? Thank you so much
Formula of IRR = IRR(C11:H11)
Without formula we can calculate as below,
IRR : IRR Means with a particular Percentage rate , At that point the present value become the zero
CALCULATION OF THE Cash Flow OF THE PROJECT
Years Cash Flows
0 -$70,000
1 $21,000
2 $21,000
3 $21,000
4 $21,000
5 $26,000
Total
CALCULATION OF THE IRR OF THE INVESTMENT
First we calculate randomly present value with @ 16% discounting rate
Years Cash Flows PVF @ 16% Present Value
0 -$70,000                         1.0000 -$70,000
1 $21,000.00 0.86207 $18,103
2 $21,000.00 0.74316 $15,606
3 $21,000.00 0.64066 $13,454
4 $21,000.00 0.55229 $11,598
5 $26,000.00 0.47611 $12,379
Net Present Value = $1,140.73
With PVF with 16 % we are getting Positive = $1,140.73
so this is not an IRR of the investment
Than we calculate randomly present value with @ 17% discounting rate
Years Cash Flows PVF @ 17% Present Value
0 -$70,000                         1.0000 -$70,000
1 $21,000.00 0.85470 $17,949
2 $21,000.00 0.73051 $15,341
3 $21,000.00 0.62437 $13,112
4 $21,000.00 0.53365 $11,207
5 $26,000.00 0.45611 $11,859
Net Present Value = -$533.17
With PVF with 17 % we are getting Negative = -$533.17
so this is not an IRR of the investment
In the given case the pv with 16% is coming to postive means the present value is more
then 16 % but with 17 % Present value cash flow become negative so the prese-nt value
is between 16% and 17 %
So the differecne in both % net present value is = $1,140.73 - -$533.17
Total is become = $1,673.91
So , the difference % = $1,140.73 "/"By $1,673.91
So , the difference % = 0.68
So, the IRR = 16.68%

Related Solutions

Calculate Payback period, Net Present Value and Benefit Cost Ratio Period 0 1 2 3 4...
Calculate Payback period, Net Present Value and Benefit Cost Ratio Period 0 1 2 3 4 5 Year 2,019 2020 2021 2022 2023 2024 Cash Flows -30,000 11,000 x .8929 = 9821.9 14,000 x .7972 = 11,160.8 10,000 x .7118= 7,118 7,000 x .6335 = 4434.5 12,000 x .5674 = 6808.8
What is the Net Present Value of the following cash flow stream? Year Cash Flow 0...
What is the Net Present Value of the following cash flow stream? Year Cash Flow 0 -$489 1 $363 2 $192 3 $161 4 $256 Assume an interest rate of 13% Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. If your answer is negative, enter your answer as a negative number rounded off to two decimal points.
Time    Cash flow 0    -165,000 1 56,500 2    67,400 3    45,600 4...
Time    Cash flow 0    -165,000 1 56,500 2    67,400 3    45,600 4 29,800 5 7,500 Suppose your firm is considering investing in Project K with the cash flows shown in the table. Assume that the required rate of return on projects of this risk class is 7.5 percent, and that the maximum allowable payback and discounted payback statistics for the project are 3.0 and 3.6 years, respectively. Which of the following statements is (are) correct? (x)...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5
  Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000...
Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000 $2,200 $3,300 $2,500 $2,500 $2,300 $2,100 A. Payback The company requires all projects to payback within 3 years. Calculate the payback period. Should it be accepted or rejected? B. Discounted Payback Calculate the discounted payback using a discount rate of 10%. Should it be accepted or rejected? C. IRR Calculate the IRR for this project. Should it be accepted or rejected? D. NPV Calculate...
The present value of a perpetuity, with the first cash flow paid in 4 years time,...
The present value of a perpetuity, with the first cash flow paid in 4 years time, is equivalent to receiving $100,000 in 15 years time. The perpetuity and the lump sum are of equivalent risk and have a required rate of return of 10%. What is the annual cash flow associated with the perpetuity?
Year Cash Flow 0 $0 1 $250 2 $400 3 $500 4 $600 5 $600 What...
Year Cash Flow 0 $0 1 $250 2 $400 3 $500 4 $600 5 $600 What is the present (Year 0) value if the opportunity cost (discount) rate is 10 percent? Add an outflow (or cost) of $1,000 at Year 0. What is the present value (or net present value) of the stream?
Year Cash Flow 0 –$ 15,900 1 7,930 2 9,490 3 8,970 4 7,210 5 –...
Year Cash Flow 0 –$ 15,900 1 7,930 2 9,490 3 8,970 4 7,210 5 – 3,580 Required: The company uses an interest rate of 12 percent on all of its projects. Calculate the MIRR of the project using all three methods. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) MIRR Discounting approach % Reinvestment approach % Combination approach %
Time Cash Flow 0         (362,000) 1           103,000 2           108,000 3     &nb
Time Cash Flow 0         (362,000) 1           103,000 2           108,000 3           116,000 4           133,000 5           142,000 What are the investment’s payback period, IRR, and NPV, assuming the firm’s WACC is 12%?- show working how you get these calculation. If the firm requires a payback period of less than 3 years, should this project be accepted? Be sure to justify your choice. Based on the IRR and NPV rules, should this project be accepted? Be sure...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT