Question

In: Finance

Consider the following cash flows: Year 0 1 2 3 4 5 6 Cash Flow -$10,000...

Consider the following cash flows:

Year 0 1 2 3 4 5 6

Cash Flow -$10,000 $2,200 $3,300 $2,500 $2,500 $2,300 $2,100

A. Payback The company requires all projects to payback within 3 years. Calculate the payback period. Should it be accepted or rejected?

B. Discounted Payback Calculate the discounted payback using a discount rate of 10%. Should it be accepted or rejected?

C. IRR Calculate the IRR for this project. Should it be accepted or rejected?

D. NPV Calculate the NPV for this project at a rate of 10%. Should it be accepted or rejected?

E. PI Calculate the Profitability Index (PI) for this project. Should it be accepted or rejected?

There are two common formulas for the profitability Index:

PV of Future Cash Flows/Initial Cost, accept if PI > 1.0 or NPV/ Initial Cost, accept if PI > 0

Solutions

Expert Solution

A. Payback Period = ( Last Year with a Negative Cash Flow ) + [( Absolute Value of negative Cash Flow in that year)/ Total Cash Flow in the following year)]

= 3 + (2000 / 2500)

= 3.80 Years

The payback period is 3.80 Years

Since  the company requires all projects to payback within 3 years, and the actual payback period is more than 3 years, hence the project must be rejected.

Hence the correct answer is rejected.

B.

Discounted Payback Period =

( Last Year with a Negative Cumulative Cash Flow ) + [( Absolute Value of negative Cumulative Cash Flow in that year)/ Total Present Cash Flow in the following year)]

= 4 + (908.26 / 1718.69)

= 4.53 Years

Hence the Discounted Payback Period is 4.53 years

Since  the company requires all projects to payback within 3 years, and the actual discounted payback period is more than 3 years, hence the project must be rejected.

Hence the correct answer is rejected.

C.

Let the IRR be x.

Now , Present Value of Cash Outflows=Present Value of Cash Inflows

10000= 2200/(1.0x) +3300/ (1.0x)^2 +2500/(1.0x)^3+ $ 2500/(1.0x)^4 + $ 2300/(1.0x)^5 +$ 2100/(1.0x)^6   

Or x= 13.20%

Hence the IRR is 13.20%

Since the IRR is more than the cost of capital, the project must be accepted.

D.  NPV of Project = Present Value of Cash Inflow - Present Value of cash Outflow

= [ $2200 * 1/(1.10) ^ 1 + 3300* 1/(1.10) ^2+2500* 1/(1.10) ^3+2500* 1/(1.10) ^4+ 2300* 1/(1.10) ^5+2100* 1/(1.10) ^6] - $ 10,000

= $ 926.61

Hence the NPV is $ 926.61

Since the NPV is positive, the project must be accepted.


Related Solutions

Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5...
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5
  Consider the cash flow for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: ($1000), 100, 600, 700, 900, 300 Project B: ($1000), 900, 700, 500, 300, 300 The cost of capital for both projects is 10% 1. Find NPV, IRR and profitability index (PI) of projects A and B. 2. If projects A and B are mutually exclusive, which project would you select 3. Find the crossover rate for projects A and B
These are the cash flows. Year 0 1 2 3 4 5 6   Revenue 3.2000 4.0000...
These are the cash flows. Year 0 1 2 3 4 5 6   Revenue 3.2000 4.0000 5.6000 5.6000 4.0000 2.4000   Expenses .7200 .9000 1.2600 1.2600 .9000 .5400   Depreciation .9500 .9500 .9500 .9500 .9500 .9500   Pretax profit 1.5300 2.1500 3.3900 3.3900 2.1500 .9100   Tax .5355 .7525 1.1865 1.1865 .7525 .3185   Net income .9945 1.3975 2.2035 2.2035 1.3975 .5915   OCF 1.9445 2.3475 3.1535 3.1535 2.3475 1.5415      Cash flow investment −5.7000 .4362    Change in NWC −.3200 −.0800 −.1600 0.0000 .1600 .1600 .2400...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
Consider the following cash flows:    Year Cash Flow 0 $-28,400       1 15,300       2...
Consider the following cash flows:    Year Cash Flow 0 $-28,400       1 15,300       2 13,600       3 10,000          Requirement 1: What is the profitability index for the above set of cash flows if the relevant discount rate is 8 percent? (Do not round intermediate calculations. Round your answer to 3 decimal places (e.g., 32.161).)      Profitability index       Requirement 2: What is the profitability index if the discount rate is 13 percent? (Do not round...
Consider the following investment cash flows: Year Cash Flow 0 ($16,000) 1 3,000 2 4,000 3...
Consider the following investment cash flows: Year Cash Flow 0 ($16,000) 1 3,000 2 4,000 3 5,000 4 6,000 5 7,000 a. What is the return expected on this investment measured in dollar terms if the opportunity cost is 6%. b. What is the return on this investment measured in percentage terms? c. Is the investment profitable? Explain your answer.
Use these cash flows to answer the following questions: Year 0 1 2 3 4 5...
Use these cash flows to answer the following questions: Year 0 1 2 3 4 5 6 A (4,000) 800 1,400 1,300 1,200 1,100 1,000 B (2,000) 700 1,300 1,200 0 0 0 a. Calculate the NPV for projects A and B using a 20 percent discount rate (write the calculate keys that you use to get the answer). b Calculate the Equivalent Annual Annuity (EAA) for projects A and B using a 20 percent discount rate (write the calculate...
Consider the following cash flows: Year Cash Flow 2 $ 22,000 3 40,000 5 58,000 Assume...
Consider the following cash flows: Year Cash Flow 2 $ 22,000 3 40,000 5 58,000 Assume an interest rate of 8.8 percent per year. If today is Year 0, what is the future value of the cash flows five years from now? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) Future value        ? If today is Year 0, what is the future value of the cash flows ten years from now? (Do not...
4. A project has the following cash flows Year Cash Flow 0 58000 1 -34000 2...
4. A project has the following cash flows Year Cash Flow 0 58000 1 -34000 2 -45000 a) What is the IRR for this project? If the required rate of return is 12%, should the firm accept the project? b) What is the NPV for this project? What is the NPV for the project if the required rate of return is 0%? 24%? What is going on here? Sketch the NPV profile to help with your answer
Year Promisedcash flows Expectedcash flows 1 6 5 2 6 5 3 6 5 4 6...
Year Promisedcash flows Expectedcash flows 1 6 5 2 6 5 3 6 5 4 6 5 5 6 5 6 6 5 7 6 5 8 6 5 9 6 5 10 106 95 What is the present value today of promised cash flows at 6%? If the price of the bond is 80, what is the yield to maturity of the bond using the promised cash flows? What is the present value today of the expected cash flows...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT