Question

In: Operations Management

A project manager has been asked to support an internal project request by developing a business...

  1. A project manager has been asked to support an internal project request by developing a business case.

What kind of information is the person expected to provide in the document?

a The detailed information from a business standpoint to determine whether bidding for the customer project will be successful.

b The detailed information from a project management standpoint to determine whether the project will be successful.

c The detailed information from a technical standpoint to determine whether the project will be successful.

d The necessary information from a business standpoint to determine whether the project is worth the investment.

2 You found the following earned value analysis information for a project that was recently closed-out:

SPI = 0.7, CPI = 1.0

a The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

b The project's deliverables have all been finished. The project came in behind schedule but on budget.

c The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

d The project's deliverables have all been finished. The project came in on schedule but over budget.

3 Which should be included in a requirements management plan?

a The document should trace requirements to project scope / WBS deliverables.

b It should describe how requirements activities will be planned, tracked, and reported.

c It should trace high-level requirements to more detailed requirements.

d It should trace requirements to business needs, opportunities, goals, and objectives.

4 In a traditionally drawn decision tree, a circle represents ___________.

a a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown.

b a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown.

c a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.

d a decision to which an expected monetary value may be assigned to calculate the most likely pay-off.

Solutions

Expert Solution

Question 1: A project manager has been asked to support an internal project request by developing a business case.
What kind of information is the person expected to provide in the document?

Answer: The necessary information from a business standpoint to determine whether the project is worth the investment.

Snippets: A project manager evaluates the project documentation and prepares a necessary information from a business standpoint. The evaluation determines whether the designated project is worth the time and investment.

Question 2: You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0

Answer: The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

Snippets: The Schedule Performance Index (SPI) measures schedule efficiency of a project and if the SPI is greater than 1 than it implies the project is on time. And Cost Performance Index (CPI) measures cost efficiency of a project and if the CPI is greater or equal to 1 than it implies that the project is right on budget. Here SPI = 0.7, which means the project is behind schedule and CPI = 1 indicates that project is on budget.

Question 3: Which should be included in a requirements management plan?

Answer: It should describe how requirements activities will be planned, tracked, and reported.

Snippets: Requirements Management Plan should describe the requirement activities which are to be planned, tracked and reported.

Question 4: In a traditionally drawn decision tree, a circle represents ___ .

Answer: A chance to which an expected monetary value may be assigned to calculate the most likely pay-off.

Snippets: Typically there are two nodes one is Chance node and another is Decision node. And a circle represents a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.


Related Solutions

As a programmer in a java project, you have been asked by your project manager to...
As a programmer in a java project, you have been asked by your project manager to describe the most efficient way to store the following assigned numbers 10,20,30,1000,200,350 for an operation which involves on calculation such as sum and average.
You are an analyst at a bank that has been asked to look into a project...
You are an analyst at a bank that has been asked to look into a project that is being undertaken by ABC Corp with a life of 10 years. The project will return cash flows of $2 million every year for 5 years and 4 million for the remaining 5 years after an initial investment of $10 million. The firm has a beta of 0.5 and the expected return of the market is 11%. There are currently 20000 shares outstanding...
Imagine that you are project engineer that has been asked to project (forecast) a cash flow...
Imagine that you are project engineer that has been asked to project (forecast) a cash flow for a new project. What would you do for the following: a. Can the forecasts be biased in any way? b. If so, in what direction and why do you think that’s the case? c. How can a manager and/or their firm neutralize the bias?
What if you were a project engineer that has been asked to project (forecast) a cash...
What if you were a project engineer that has been asked to project (forecast) a cash flow for a new project. What would you do for the following: a. Can the forecasts be biased in any way? b. If so, in what direction and why do you think that’s the case? c. How can a manager and/or their firm neutralize the bias?
is the new manager of the materials storeroom for Parr Manufacturing. Mary has been asked to...
is the new manager of the materials storeroom for Parr Manufacturing. Mary has been asked to estimate future monthly purchase costs for part​ #696, used in two of Parr​'s products. Mary has purchase cost and quantity data for the past 9 months as​ follows: Month Cost of Purchase Quantity Purchased January $12,675 2,720 parts February 12,110 2,820 March 17,426 4,095 April 15,825 3,724 May 13,025 2,912 June 14,022 3,321 July 15,290 3,688 August 10,094 2,262 September 14,970 3,552 Estimated monthly...
You have been asked to replace the project manager who was heading up your firm’s new...
You have been asked to replace the project manager who was heading up your firm’s new compensation and benefits system. One of the reasons the project manager is being replaced is because the project schedule had the wrong resources assigned (e.g., resources who do not fully understand compensation and benefits). You have been asked to solve this problem quickly by either replacing the resources or getting the resources up-to-speed on compensation and benefits. Present your recommendation for solving this critical...
for a project internal to your company the business objectives of the project are defined by...
for a project internal to your company the business objectives of the project are defined by : a) the sponser b) the project manager c) the project team d) costumers and the market place
You are a member in a project team and the project manager asked you to purchase...
You are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (Lenovo ThinkPad T series, Core i7, 2 Tera Storage, 32 GB Ram, 15.6" size, NVIDIA® graphics). How do you set your procurement management to do that?
you are a member in a project team and the project manager asked you to purchase...
you are a member in a project team and the project manager asked you to purchase 4 laptops with certain specifications (lenovo thinkpad T series,core i7,2 tera storage ,32 GB Ram ,15.6 size , NVIDIA graphics ) how do you set your procurement management to do that?
A project manager receives a change request from the customer. The change requires adding a new...
A project manager receives a change request from the customer. The change requires adding a new filtration system to the project in place of a cleaner bag. When the project manager evaluates the change, it is most important that she consider the impact on the: Sponsor Project constraints Communications management plan Subsequent work packages Conduct Procurements is a part of which process group? Monitoring and controlling Planning Initiating Executing A project manager is completing the WBS with the project team,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT