What kind of information is the person expected to provide in the document?
a The detailed information from a business standpoint to determine whether bidding for the customer project will be successful.
b The detailed information from a project management standpoint to determine whether the project will be successful.
c The detailed information from a technical standpoint to determine whether the project will be successful.
d The necessary information from a business standpoint to determine whether the project is worth the investment.
2 You found the following earned value analysis information for a project that was recently closed-out:
SPI = 0.7, CPI = 1.0
a The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
b The project's deliverables have all been finished. The project came in behind schedule but on budget.
c The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
d The project's deliverables have all been finished. The project came in on schedule but over budget.
3 Which should be included in a requirements management plan?
a The document should trace requirements to project scope / WBS deliverables.
b It should describe how requirements activities will be planned, tracked, and reported.
c It should trace high-level requirements to more detailed requirements.
d It should trace requirements to business needs, opportunities, goals, and objectives.
4 In a traditionally drawn decision tree, a circle represents ___________.
a a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown.
b a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown.
c a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.
d a decision to which an expected monetary value may be assigned to calculate the most likely pay-off.
Question 1: A project manager has been asked to
support an internal project request by developing a business
case.
What kind of information is the person expected to provide in the
document?
Answer: The necessary information from a business standpoint to determine whether the project is worth the investment.
Snippets: A project manager evaluates the project documentation and prepares a necessary information from a business standpoint. The evaluation determines whether the designated project is worth the time and investment.
Question 2: You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.7, CPI = 1.0
Answer: The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
Snippets: The Schedule Performance Index (SPI) measures schedule efficiency of a project and if the SPI is greater than 1 than it implies the project is on time. And Cost Performance Index (CPI) measures cost efficiency of a project and if the CPI is greater or equal to 1 than it implies that the project is right on budget. Here SPI = 0.7, which means the project is behind schedule and CPI = 1 indicates that project is on budget.
Question 3: Which should be included in a requirements management plan?
Answer: It should describe how requirements activities will be planned, tracked, and reported.
Snippets: Requirements Management Plan should describe the requirement activities which are to be planned, tracked and reported.
Question 4: In a traditionally drawn decision tree, a circle represents ___ .
Answer: A chance to which an expected monetary value may be assigned to calculate the most likely pay-off.
Snippets: Typically there are two nodes one is Chance node and another is Decision node. And a circle represents a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.