Question

In: Finance

Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).)

Project D
Time: 0 1 2 3 4 5
Cash flow: –$12,400 $3,490 $4,460 $1,800 $0 $1,280

Solutions

Expert Solution

Ans 0 (zero)

Since the amount cannot be recovered during the lifetime of the project.

Year Project Cash Flows (i) DF@ 12% (ii) PV of Project A ( (i) * (ii) ) Cumulative Cash Flow
0 -12400 1                           (12,400.00)              (12,400.00)
1 3490 0.893                              3,116.07                (9,283.93)
2 4460 0.797                              3,555.48                (5,728.44)
3 1800 0.712                              1,281.20                (4,447.24)
4 0 0.636                                           -                  (5,728.44)
5 1280 0.567                                  726.31                (3,720.93)
NPV                             (3,720.93)

Related Solutions

Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$11,000 $3,350 $4,180 $1,520 $300 $1,000 Discounted payback period _______ years Should the project be accepted or...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero). PROJECT D: TIME               0                    1                     2                      3                4              5 Cash Flow    $ -11,800          $3,430             $4,340           $1,680             $0          $1,160 Discounted Payback Period = Should this be rejected...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow –$2,900 $1,240 $1,050 $1,090 $680 $480 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100 Calculate discounted payback period in years
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,200 $960 $840 $880 $540 $340 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,600 $720 $660 $700 $420 $220
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,200 $960 $840 $880 $540 $340
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,700 $760 $690 $730 $440 $240
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,400 $640 $600 $640 $380 $180 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,400 $1,040 $900 $940 $580 $380 Should the project be accepted or rejected? Discounted payback period______ years accepted rejected
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT