Question

In: Finance

Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...

Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project C
Time: 0 1 2 3 4 5
Cash flow: –$1,400 $640 $600 $640 $380 $180

Should the project be accepted or rejected?

  • accepted

  • rejected

Solutions

Expert Solution

Discounted payback period

Discounted Payback period is nothing but the length of time taken for the initial cost of a project to equalise the discounted value of expected cashflows or the time taken to break-even from the amount of investment.

Discounted payback period for Project C

Present value factor of the cash flow may be calculated using the formula

PV= ( CF) / (1+r)^n

Where PV = Present value of cash flows
CF = Cash flows
   r = interest rate per period
   n = period of cash flow

Project C Years Cash flow 1/(1+r)^n PV = CF * 1/(1+r)^n Cumulative PV
1 640 0.93 598.13 598.13
2 600 0.87 524.06 1122.19
3 640 0.82 522.43 1644.62
4 380 0.76 289.90 1934.52
5 180 0.71 128.34 2062.86

As you can see from the cumulative PV column, it is understood the initial cost of Project C has been recovered in 3 years, but still not the entire amount of discounted cash flows is allocated for investment. Thus the initial initial investment was recovered during 2 years and part of the third year and the discounted payback period may be calculated as follows:

Payback period = (2+( (1644.62 – 1400)/1644.62))

Payback period =(2+0.148740) = 2.15 years

Thus the discounted payback period is 2.15 years


Related Solutions

Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,700 $760 $690 $730 $440 $240
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 7 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,400 $1,040 $900 $940 $580 $380 Should the project be accepted or rejected? Discounted payback period______ years accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow –$2,900 $1,240 $1,050 $1,090 $680 $480 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100 Calculate discounted payback period in years
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,200 $960 $840 $880 $540 $340 Should the project be accepted or rejected? accepted rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$1,600 $720 $660 $700 $420 $220
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow: –$2,200 $960 $840 $880 $540 $340
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$12,400 $3,490 $4,460 $1,800 $0 $1,280
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero). PROJECT D: TIME               0                    1                     2                      3                4              5 Cash Flow    $ -11,800          $3,430             $4,340           $1,680             $0          $1,160 Discounted Payback Period = Should this be rejected...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "0" (zero).) Project D Time: 0 1 2 3 4 5 Cash flow: –$11,000 $3,350 $4,180 $1,520 $300 $1,000 Discounted payback period _______ years Should the project be accepted or...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT