Question

In: Accounting

BlayCo's standard and actual costs per unit for the most recent period, during which 600 units...

BlayCo's standard and actual costs per unit for the most recent period, during which 600 units were actually produced, are given below:

Standard Quantity/Hours:   Materials- 4 feet per unit, Labor -unit 2 hours, Variable MOH- 2 hours per unit

Standard Price/Rate: Materials $2.00 per feet, Labor-$8.00foot per hour, Variable MOH- $3.00 per hour

Actual Quantity/Hours: Materials -1,000 feet, Labor-800 hours, Variable MOH- 800 hours

Actual Total Cost: Materials-$1,500, Labor-$4,000, Variable MOH-$2,000

Required (show your work): From the foregoing information, compute the following variances. Show whether the variance is favorable (F) or unfavorable (U):

Thank you.

Solutions

Expert Solution

Solution:

All the variances are calculated as below:

Direct Material Price Variance

Actual Price ($1,500 / 1,000 feet)

$1.50

per foot

Standard Price

$2.00

per foot

Variance or Difference in Price

$0.50

per foot

x Actual Quantity PURCHASED/USED

1,000

foot

Direct Material Price Variance

$500

Favorable

Direct Material Quantity/Efficiency/Usage Variance

Standard Quantity Allowed for actual production:

Actual Production/Activity

600

Units

x Allowed Standard Quantity Per Unit

4

feet

Total Standard Quantity Allowed for actual production (SQAP)

2,400

feet

Actual Quantity USED

1,000

feet

Variance or Difference in Quantity

1,400

feet

x Standard Price (SP)

$2.00

per lbs

Material Quantity/Efficiency Variance

$2,800

Favorable

Labor Rate Variance

Actual Hourly Rate ($4,000 / 800 hours)

$5.00

Per Hour

Standard Hourly Rate

$8.00

Per Hour

Variance or Difference in Rate

$3.00

Per Hour

x Actual Labor Hours worked

800

Hours

Labor Rate Variance

$2,400

Favorable

Labor Quantity / Efficiency Variance

Standard Hours Allowed for actual production:

Actual Production

600

Units

x Allowed Standard Hours Per Unit

2.000

hours

Total Standard Hours Allowed for actual production (SHAP)

1,200

hours

Actual Labor Hours Worked

800

hours

Variance or Difference in Hours

400

hours

x Standard Hourly Rate (SHR)

$8.00

per hour

Labor Efficiency Variance

$3,200

Favorable

Variable Overhead Rate/Spending/Cost Variance

Actual Hourly Variable Overhead Rate ($2,000 / 800 hours)

2.50

Per Hour

Standard Hourly Variable Overhead Rate

3.00

Per Hour

Variance or Difference in Rate

0.50

Per Hour

x Actual Hours Worked

800

Hours

Variable Overhead Rate/Spending Variance

$400

Favorable

Variable Overhead Efficiency/Quantity Variance

Standard Hours Allowed for actual production:

Actual Production

600

Pools

x Allowed Standard Hours Per Unit

2

Hours

Total Standard Hours Allowed for actual production (SHAP)

1200

Hours

Actual Hours Worked (AH)

800

Hours

Variance or Difference in Hours

400

hours

x Standard Hourly Variable Overhead Rate

$3.00

per hour

Variable Overhead Efficiency Variance

$1,200

Favorable

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you


Related Solutions

Lido Company's standard and actual costs per unit for the most recent period, during which 400...
Lido Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Standard Actual Materials: Standard: 2 metres. at $1.50 per metre $3.00 Actual: 2.1 metres at $1.60 per metre $3.36 Direct labour: Standard: 1.5 hrs. at $6.00 per hr. 9.00 Actual: 1.4 hrs. at $6.50 per hr. 9.10 Variable overhead: Standard: 1.5 hrs. at $3.40 per hr. 5.10 Actual: 1.4 hrs. at $3.10 per hr. 4.34 Total unit...
Orville Company’s standard and actual costs per unit are provided below for the most recent period....
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 1200 units were actually produced. Standard Actual Materials:      Standard: 2-6 metres at $2.30 per m. $5.98      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 2.2 hrs. at $7.90 per hr. 17.38      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 2.2 hrs. at $4.60 per hr. 10.12      Actual: 1.7...
Orville Company’s standard and actual costs per unit are provided below for the most recent period....
Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 1200 units were actually produced.   Standard Actual Materials:      Standard: 2-6 metres at $2.30 per m. $5.98      Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour:      Standard: 2.2 hrs. at $7.90 per hr. 17.38      Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead:      Standard: 2.2 hrs. at $4.60 per hr. 10.12      Actual: 1.7 hrs. at $4.20 per hr. 7.14...
A company has the following actual and standard production measures during the period:                 Actual units...
A company has the following actual and standard production measures during the period:                 Actual units produced    390                 Actual materials purchased and used      2,583 lbs                 Actual materials price     $9 per lb                 Actual labor hours           1430                 Actual labor rate               $21.4 per hour                 Actual variable overhead              $ 7,950                 Standard materials per unit         6 lbs                 Standard materials purchased and used $8.6 per lb                 Standard labor hours per unit     3                 Standard labor rate         $22.5 per...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.64 Actual Costs Direct materials 2,700 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is a.$458 favorable b.$458 unfavorable c.$1,188 unfavorable d.$1,188 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.74 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $17,900 Total fixed cost, $7,800 The total factory overhead cost variance is a.$1,780 favorable b.$2,964 favorable c.$596 unfavorable d.$1,780 unfavorable
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours)3 hours per unit at $0.74 per hour Variable overhead3 hours per unit at $1.93 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,200 The variable factory overhead controllable variance is a.$2,820 favorable b.$3,525 favorable c.$3,525 unfavorable d.$0
During the current period, McLaughlin Company sold 60,000 units of product at $30 per unit. At...
During the current period, McLaughlin Company sold 60,000 units of product at $30 per unit. At the beginning of the period, there were 10,000 units in inventory and McLaughlin Company manufactured 50,000 units during the period. The manufacturing costs and selling and administrative expenses were as follows: Total Cost Number of Units Unit Cost Beginning inventory: Direct materials.....................................$ 67,000 10,000 $ 6.70 Direct labor........................................ 155,000 10,000 15.50 Variable factory overhead...........................18,000 10,000 1.80 Fixed factory overhead............................. 20,000 10,000 2.00 Total ....
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units...
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.73 per hour Variable overhead 3 hours per unit @ $2.03 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $8,100 The amount of the fixed factory overhead volume variance is $1,110 unfavorable $1,387 unfavorable $1,110 favorable $0 Q2: The standard costs and...
Q . A company is maufacturing 5000 units for the period. Actual and standard direct materials...
Q . A company is maufacturing 5000 units for the period. Actual and standard direct materials information are: - Standard Costs: 1.5 pounds per unit; purchase price is 0.78 per pound. Actual Costs: 8000 pounds purchased and used; purchase price is 0.75 per pound. Find material price variance. Also tell if it's favourable or unfavourable. Q. A company is maufacturing 5000 units for the period. Actual and standard direct materials information are: - Standard Costs: 1.5 pounds per unit; purchase...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT