In: Accounting
BlayCo's standard and actual costs per unit for the most recent period, during which 600 units were actually produced, are given below:
Standard Quantity/Hours: Materials- 4 feet per unit, Labor -unit 2 hours, Variable MOH- 2 hours per unit
Standard Price/Rate: Materials $2.00 per feet, Labor-$8.00foot per hour, Variable MOH- $3.00 per hour
Actual Quantity/Hours: Materials -1,000 feet, Labor-800 hours, Variable MOH- 800 hours
Actual Total Cost: Materials-$1,500, Labor-$4,000, Variable MOH-$2,000
Required (show your work): From the foregoing information, compute the following variances. Show whether the variance is favorable (F) or unfavorable (U):
Thank you.
Solution:
All the variances are calculated as below:
Direct Material Price Variance |
||
Actual Price ($1,500 / 1,000 feet) |
$1.50 |
per foot |
Standard Price |
$2.00 |
per foot |
Variance or Difference in Price |
$0.50 |
per foot |
x Actual Quantity PURCHASED/USED |
1,000 |
foot |
Direct Material Price Variance |
$500 |
Favorable |
Direct Material Quantity/Efficiency/Usage Variance |
||
Standard Quantity Allowed for actual production: |
||
Actual Production/Activity |
600 |
Units |
x Allowed Standard Quantity Per Unit |
4 |
feet |
Total Standard Quantity Allowed for actual production (SQAP) |
2,400 |
feet |
Actual Quantity USED |
1,000 |
feet |
Variance or Difference in Quantity |
1,400 |
feet |
x Standard Price (SP) |
$2.00 |
per lbs |
Material Quantity/Efficiency Variance |
$2,800 |
Favorable |
Labor Rate Variance |
||
Actual Hourly Rate ($4,000 / 800 hours) |
$5.00 |
Per Hour |
Standard Hourly Rate |
$8.00 |
Per Hour |
Variance or Difference in Rate |
$3.00 |
Per Hour |
x Actual Labor Hours worked |
800 |
Hours |
Labor Rate Variance |
$2,400 |
Favorable |
Labor Quantity / Efficiency Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
600 |
Units |
x Allowed Standard Hours Per Unit |
2.000 |
hours |
Total Standard Hours Allowed for actual production (SHAP) |
1,200 |
hours |
Actual Labor Hours Worked |
800 |
hours |
Variance or Difference in Hours |
400 |
hours |
x Standard Hourly Rate (SHR) |
$8.00 |
per hour |
Labor Efficiency Variance |
$3,200 |
Favorable |
Variable Overhead Rate/Spending/Cost Variance |
||
Actual Hourly Variable Overhead Rate ($2,000 / 800 hours) |
2.50 |
Per Hour |
Standard Hourly Variable Overhead Rate |
3.00 |
Per Hour |
Variance or Difference in Rate |
0.50 |
Per Hour |
x Actual Hours Worked |
800 |
Hours |
Variable Overhead Rate/Spending Variance |
$400 |
Favorable |
Variable Overhead Efficiency/Quantity Variance |
||
Standard Hours Allowed for actual production: |
||
Actual Production |
600 |
Pools |
x Allowed Standard Hours Per Unit |
2 |
Hours |
Total Standard Hours Allowed for actual production (SHAP) |
1200 |
Hours |
Actual Hours Worked (AH) |
800 |
Hours |
Variance or Difference in Hours |
400 |
hours |
x Standard Hourly Variable Overhead Rate |
$3.00 |
per hour |
Variable Overhead Efficiency Variance |
$1,200 |
Favorable |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you