Question

In: Accounting

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows:

Standard Costs

Fixed overhead (based on 10,000 hours)3 hours per unit at $0.74 per hour

Variable overhead3 hours per unit at $1.93 per hour

Actual Costs

Total variable cost, $18,000

Total fixed cost, $8,200

The variable factory overhead controllable variance is

a.$2,820 favorable

b.$3,525 favorable

c.$3,525 unfavorable

d.$0

Solutions

Expert Solution

Solution to question

Cost Variance is basically comprised of two elements namely, Volume variance & Rate Variance. Volume Variance depends upon change in volume whereas rate variance depends upon change in budgeted & Actual Rate. A controllable variance depends on the rate portion.

Calculation of Variable Factory Overhead Controllable Variance: -

Note 1: - Analysis of data

            Budgeted: - 2500 Units @ 3 hrs. per unit at $ 1.93 per hour

              Actual: -     2500 Units for $ 18,000

Therefore, Variable factory overhead controllable variance =

            = Budgeted cost for Actual output – Actual Cost

            = (2500 Units x 3 hours per unit x $ 1.93) – $ 18,000

            = $ 14,475 - $ 18,000

            = $ 3525 A

            Where A = Adverse or unfavourable

Department managers are responsible for controlling variable factory overhead variance.


Related Solutions

The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.74 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $17,900 Total fixed cost, $7,800 The total factory overhead cost variance is a.$1,780 favorable b.$2,964 favorable c.$596 unfavorable d.$1,780 unfavorable
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units...
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.73 per hour Variable overhead 3 hours per unit @ $2.03 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $8,100 The amount of the fixed factory overhead volume variance is $1,110 unfavorable $1,387 unfavorable $1,110 favorable $0 Q2: The standard costs and...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.64 Actual Costs Direct materials 2,700 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is a.$458 favorable b.$458 unfavorable c.$1,188 unfavorable d.$1,188 favorable
Factory Overhead Controllable Variance Tip Top Corp. produced 2,500 units of product that required 6 standard...
Factory Overhead Controllable Variance Tip Top Corp. produced 2,500 units of product that required 6 standard hours per unit. The standard variable overhead cost per unit is $2.4 per hour. The actual variable factory overhead was $36,830. Determine the variable factory overhead controllable variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $   Factory Overhead Volume Variance Tip Top Corp. produced 3,500 units of product that required 1.5...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced.
  Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 units of product were as follows: Standard Costs Actual Costs Direct materials 9,400 lb. at $5.20 9,300...
Applying Factory Overhead Salinger Company estimates that total factory overhead costs will be $175,000 for the...
Applying Factory Overhead Salinger Company estimates that total factory overhead costs will be $175,000 for the year. Direct labor hours are estimated to be 25,000. a. For Salinger Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. If required, round your answer to two decimal places. $ per direct labor hour b. During August, Salinger Company accumulated 590 hours of direct labor costs on Job 40 and 840 hours on Job 42. Determine the...
Applying Factory Overhead Darling Company estimates that total factory overhead costs will be $493,000 for the...
Applying Factory Overhead Darling Company estimates that total factory overhead costs will be $493,000 for the year. Direct labor hours are estimated to be 29,000. a. For Darling Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. $ per direct labor hour b. During May, Darling Company accumulated 640 hours of direct labor costs on Job 200 and 890 hours on Job 305. Determine the amount of factory overhead applied to Jobs 200 and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT