Question

In: Accounting

The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...

The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows:

Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.74 per hour
Variable overhead 3 hours per unit at $2.06 per hour
Actual Costs
Total variable cost, $17,900
Total fixed cost, $7,800

The total factory overhead cost variance is

a.$1,780 favorable

b.$2,964 favorable

c.$596 unfavorable

d.$1,780 unfavorable

Solutions

Expert Solution

Hi, Friend...

Hope you are also doing well.

I have tried to give the best possible answer. If you have any doubts, please mention in the comment section. I'll definitely respond in early possible time.

Ans:

Total factory overhead cost variance is: d. $1,780 unfavourable

Workings:

Total factory overhead cost variance = fixed factory overhead variance (i) + variable factory overhead variance (ii)

= $1,184 unfavourable + $596 unfavourable

= $1,780 unfavourable.

(i) Calculation of fixed factory overhead variance:

formula = standard fixed overhead rate per hour x (standard hour for actual output - budgeted hour)

= $.74 x [(2800 x 3) - 10,000]

= $.74 x (1,600)

= $1,184 unfavourable

(ii) Calculation of variable factory overhead variance:

formula = standard variable cost - actual variable cost

= (2,800 unit x 3 hour per unit x $2.06 per hour) - $17,900

= $17,304 - $17,900

=$596 unfavourable

Thanks, Dear... Have a Wonderful Day... Keep Social Distancing.


Related Solutions

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours)3 hours per unit at $0.74 per hour Variable overhead3 hours per unit at $1.93 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,200 The variable factory overhead controllable variance is a.$2,820 favorable b.$3,525 favorable c.$3,525 unfavorable d.$0
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units...
Q1: The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.73 per hour Variable overhead 3 hours per unit @ $2.03 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $8,100 The amount of the fixed factory overhead volume variance is $1,110 unfavorable $1,387 unfavorable $1,110 favorable $0 Q2: The standard costs and...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units...
The standard costs and actual costs for direct materials for the manufacture of 2,700 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.64 Actual Costs Direct materials 2,700 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is a.$458 favorable b.$458 unfavorable c.$1,188 unfavorable d.$1,188 favorable
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced.
  Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,000 machine hours per year, which represents 25,000 units of output. Annual budgeted fixed factory overhead costs are $250,000 and the budgeted variable factory overhead cost rate is $4 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 7,200 units of product were as follows: Standard Costs Actual Costs Direct materials 9,400 lb. at $5.20 9,300...
Applying Factory Overhead Salinger Company estimates that total factory overhead costs will be $175,000 for the...
Applying Factory Overhead Salinger Company estimates that total factory overhead costs will be $175,000 for the year. Direct labor hours are estimated to be 25,000. a. For Salinger Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. If required, round your answer to two decimal places. $ per direct labor hour b. During August, Salinger Company accumulated 590 hours of direct labor costs on Job 40 and 840 hours on Job 42. Determine the...
Applying Factory Overhead Darling Company estimates that total factory overhead costs will be $493,000 for the...
Applying Factory Overhead Darling Company estimates that total factory overhead costs will be $493,000 for the year. Direct labor hours are estimated to be 29,000. a. For Darling Company, determine the predetermined factory overhead rate using direct labor hours as the activity base. $ per direct labor hour b. During May, Darling Company accumulated 640 hours of direct labor costs on Job 200 and 890 hours on Job 305. Determine the amount of factory overhead applied to Jobs 200 and...
The company uses a single plantwide factory overhead rate. The budgeted Factory Overhead Costs for the...
The company uses a single plantwide factory overhead rate. The budgeted Factory Overhead Costs for the year are $1,400,000 and allocates factory overhead based on direct labor hours. The company plans to make 100,000 shirts and 50,000 pairs of pants. It takes 2 direct labor hours to make a shirt and 3 direct labor hours to make a pair of pants. What are the total number of direct labor hours? What is the single plantwide factory overhead rate? Answers should...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT