According to Larson and Gray in Project Management: The Managerial Process, the project scope is essential...

According to Larson and Gray in Project Management: The Managerial Process, the project scope is essential for integrating all elements of the project management plan. Discuss the elements that should be included in the scope statement.Provide References.

Solutions

Expert Solution

Various elements that should be included in the project scope statement are listed as follows:

  • Project objectives
  • Deliverables
  • Milestones
  • Technical requirements
  • Limits and exclusions
  • Reviews with customer

Project Objectives:

Any project planning starts with the objective. Thus, while defining project scope first step is to define major objectives in term of which customers needs will be achieved and how and when.

For example,

Develop a Web and Mobile Application for online shopping company in four months within the budget of $1 million.

Deliverables:

After defining project objective, next step is to define deliverables over the life of project. Deliverables are the phase by phase expected output of project in terms of time, quantity and/or estimated cost.

For example, deliverables of application development project are as follows:

Phase

Deliverables

Early

Listing application specifications and logical relationships between elements of application.

Date:

Cost:

Second

Software coding and technical manual for both mobile and web application.

Date:

Cost:

Third

Prototype testing of the Application

Date:

Cost:

Fourth

Review and Improvement in Application

Date:

Cost:

Fifth

Final Test and approval of the Application

Date:

Cost:

Milestones:

Milestones represent significant events that occur in project life cycle. This helps project manager to evaluate the progress of actual project performance. The Milestone schedule estimates completion of the important segments of work in terms of time, cost, and resources for the project. Important segment of works are identified on the basis of deliverables defined in project scope.

For example, the prototype testing will be done by consultant and finished by May 15.

Technical Requirements:

The customer may define the technical requirements for efficient and effective performance of the product or service. Project scope should also include the technical requirements of product or service delivered by projects.

For example, for web and mobile application, number of items that will be displayed on the screen. Time it will take to complete payment process.

Exclusions:

Exclusions are the limits of the scope of project. It explains what the project will not accomplish or produce.

Reviews with customer:

Final and most important part of project scope is the review with the customer of the above elements. It is important that customer should understand and agree with the defined elements. If any recommendations are given by customers, they have to be implemented and scope elements have to be revised.


Related Solutions

According to Larson and Gray in Project Management: The Managerial Process, the project scope is essential...
According to Larson and Gray in Project Management: The Managerial Process, the project scope is essential for integrating all elements of the project management plan. Discuss the elements that should be included in the scope statement.Provide References.
1. Briefly describe ‘scope’, ‘deliverable’, and ‘project scope management’.
1. Briefly describe ‘scope’, ‘deliverable’, and ‘project scope management’.
What is NOT included in the project scope management processes:
What is NOT included in the project scope management processes: plan scope management collect requirements define scope create WBS legal judgement
NETWORK SYSTEM MANAGEMENT. Given the following attributes in a project management:  Project scope & feasibility...
NETWORK SYSTEM MANAGEMENT. Given the following attributes in a project management:  Project scope & feasibility  Documentation  Project planning  Testing and piloting  Risk minimisation Discuss briefly each of them and on how would you use them as the IT manager for the company. Provide a details information support your discussion. Remarks: Total 50 Marks for this questions.
Define strategic management and explain the scope of SM. What are the essential differences between Strategic...
Define strategic management and explain the scope of SM. What are the essential differences between Strategic and Operation Management. Strategy relies on understanding internal and external contexts, explain why this is necessary.
Project Scope Management Questions Only On a project to develop an inventory control system, the project...
Project Scope Management Questions Only On a project to develop an inventory control system, the project manager is working on creating the scope management plan. He realizes that this plan must include items such as how the WBS will be created and how the scope of work will be accomplished and measured. All of the following statements are true about the scope management plan except: A. It will not change after approval. B. It may be based on organizational forms...
How does project scope, project budget and earned value management conpare and contrast?
How does project scope, project budget and earned value management conpare and contrast?
Question 1 (50 marks) Given the following attributes in a project management • Project scope &...
Question 1 Given the following attributes in a project management • Project scope & feasibility • Documentation • Project planning • Testing and piloting • Risk minimization Discuss briefly each of them and on how would you use them as the IT manager for the company. Provide a details information support your discussion. [50 marks] Guideline: Plan and deploy a project and Integrate with this 5 elements. Example: Wi-Fi project, infrastructure project, server project and etc… Students are expected to:...
** (a) (i) What is Managerial Economics? (ii) What is the scope of Managerial Economics? (iii)...
** (a) (i) What is Managerial Economics? (ii) What is the scope of Managerial Economics? (iii) As a CEO of a company, of what relevance is Managerial Economics to you? (b) Define and give an example of each of the following demand terms and concepts and illustrate diagrammatically a change in each. (i) Demand (ii) Normal good (iii) Inferior good (iv) Substitute good (v) Complementary good (c) The market demand for brand X has been estimated as Qx= 1,500 –...
It is essential that project managers not only have a strong understanding of project management concepts...
It is essential that project managers not only have a strong understanding of project management concepts and available tools but also learn from past experience to avoid pitfalls in the future. In doing so, project managers can recognize areas of improvement in ongoing projects and implement procedures to enhance efficiency based on knowledge and lessons learned. Additionally, project managers can be mindful of these actions while planning for future projects. After reading the case study that you did not select...