Question

In: Operations Management

Explain each question based on project management and The Critical-Chain Approach. How is time wasted in...

Explain each question based on project management and The Critical-Chain Approach.

  1. How is time wasted in the management of projects?
  2. Distinguish between project and feeder buffers?
  3. Why are buffers not the same as slack?

Solutions

Expert Solution

1. How time is wasted in Management of Projects:

Procrastination: Suppose you as a manager called a meeting with your team and other members, but you did't able to reach or attend the meeting.You posponded it for later and again missed. This is called as Procrastination which is a time loss during any working project.

Delegation: This indicates taking all decisions by yourself ( As a project manager )without delegating to your team members or juniors which lead to time loss even for small decision and time loss also occur , if concern is not available for providing decisions.

Resource Availability : During the start of the project its assumed that all the required resources are available, but in actual is not , non availability of required resources at perticular instant leads to a huge delay in the project work.

Early Task Completion: If a team member completed his/her task early , still have to wait for other as the next precedding process or work is not completed.

2. Distinguish between project and feeder buffers:

Project Buffer : This the extra time or say tolerence which is kept at last stage for project completion as any delay in the project will consume this buffer time and do not effect the project completion date.

Feeder Buffer: This is the extra time or buffer which included between the process or say between the process in the critical chain. if an process or feeding in the critical chain is delayed, The feeder buffer will be consumed and thus which will not effect the overall critical chain performance.

3.Why are buffers not the same as slack:

Slack : Slack is the difference between the Planned time of completion of the project and the actual time of the completion of the project.

Buffers: It is the extra time alloted either at the end of the critical chain or during feeding process in the critical chain process.


Related Solutions

________ is typically not referred to as a buffer type in critical chain project management. a....
________ is typically not referred to as a buffer type in critical chain project management. a. resource buffer b. free buffer c. feeding buffer d. project buffer A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of...
Explain the fundamental concept of supplies chain management and illustrates critical of the process
Explain the fundamental concept of supplies chain management and illustrates critical of the process
Explain the fundamental concept of supply chain management and its critical components of the process.
Explain the fundamental concept of supply chain management and its critical components of the process.
Describe the differences between value delivery network and value chain. Explain how each are critical to...
Describe the differences between value delivery network and value chain. Explain how each are critical to successful marketing planning.
why project management is critical
why project management is critical
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following....
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following. Assess the reasons for using lean thinking (suitable examples), what are the benefits from Suppliers to end users?
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following....
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following. Why Companies adopted Lean Thinking and JIT model?
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following....
Logestics Management Ch7 "Just-in-time and the agile supply chain" Based on this chapter answer the following. Discuss major types of Waste, companies has to keep in mind during production.
Please write a detailed paragraph on each questions based on the knowledge in Supply Chain Management!...
Please write a detailed paragraph on each questions based on the knowledge in Supply Chain Management! 1. Discuss three key design/operating considerations when implementing lean in a retail environment. 2. Describe three benefits from implementing a decentralized, low-coordination procurement model.
QUESTION FOUR [30] Project supply chain management is a set of proactive responses to many challenges...
QUESTION FOUR [30] Project supply chain management is a set of proactive responses to many challenges created by people from different organisations working together on projects. The project organisation may start with assessing the need to outsource part of the project work. Contracting is commonly used to specify and manage supplier-buyer relationships. With reference to this: 4.1 Discuss the enablers of the purchasing and supply chain functions related to a project. (16) 4.2 Discuss the supplier evaluation and selection process....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT