Question

In: Finance

•You are looking at a new project and you have estimated the following cash flows: Year...

•You are looking at a new project and you have estimated the following cash flows:

Year 0: CF = -$150,000

Year 1-2: CF = $80,000

Year 3-4: CF = $50,000

Year 5-6: CF = $30,000

Year 7: CF = -$180,000

Your cost of capital is 10%

Please calculate NPV and IRR, and decide whether we should take this project?

Solutions

Expert Solution

Project
Discount rate 10.000%
Year 0 1 2 3 4 5 6 7
Cash flow stream -150000 80000 80000 50000 50000 30000 30000 -180000
Discounting factor 1.000 1.100 1.210 1.331 1.464 1.611 1.772 1.949
Discounted cash flows project -150000.000 72727.273 66115.702 37565.740 34150.673 18627.640 16934.218 -92368.461
NPV = Sum of discounted cash flows
NPV Project = 3752.78
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR is the rate at which NPV =0
IRR 17.14%
Year 0 1 2 3 4 5 6 7
Cash flow stream -150000.000 80000.000 80000.000 50000.000 50000.000 30000.000 30000.000 -180000.000
Discounting factor 1.000 1.171 1.372 1.607 1.883 2.205 2.583 3.026
Discounted cash flows project -150000.000 68297.046 58306.081 31110.415 26559.368 13604.448 11614.295 -59491.653
NPV = Sum of discounted cash flows
NPV Project = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 17.14%

Accept project as NPV is positive and IRR> cost of capital


Related Solutions

A capital budget project is estimated to have the following after-tax cash flows, by year: 0...
A capital budget project is estimated to have the following after-tax cash flows, by year: 0 1 2 3 4 -$35,000 $13,000 $15,000 $17,000 $19,000 Use the information in the table above for the following questions 11a. through 11f. The company utilizes a discount rate of 9% to evaluate capital projects. You may have rounding errors in your calculations so choose the closest answer. 1. Find NPV, IRR, MIRR, and PI for the project shown above 2. Find Payback and...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0 -5,300 1 1,325 2 2,148 3 2,209 what is the IRE for the project 2)you've estimated the following cash flows (in$) for 2 projects: A. B. C.    year. ProjectA. ProjectB 0. -78 -261 1 15 50 2 21 73 3 29 82 4 35 127 the required return is 7% for both projects What is the IRR for project B? What is the...
Costco, Inc. is conducting a new project with the following estimated cash flows. The initial outlay...
Costco, Inc. is conducting a new project with the following estimated cash flows. The initial outlay is estimated to be ​$1,950,000​, and the incremental cash flows generated by this project would be ​$650,000 per year for 7 years. The estimated required rate of return of the project is 6​%. a. Calculate the NPV. b. Calculate the PI. c. Calculate the IRR. d. Should this project be​ accepted?
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,200 -7,800 1 1,325 1,325 2 2,148 2,148 3 3,640 7,360 The required return for both projects is 8%. 1. What is the IRR for project A? 2. What is the IRR for project B? 3. Which project seems better according to the IRR method? 4. What is the NPV for project A? 5. What is the NPV for project B?...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,700 -8,550 1 1,325 1,325 2 2,148 2,148 3 4,325 8,384 The required return for both projects is 8%. What is the IRR for project A? What is the IRR for project B? Which project seems better according to the IRR method? Project A Project B What is the NPV for project A? What is the NPV for project B? Which...
1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The...
1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 8 percent. Year 0: ($700,000) Year 1: $400,000 Year 2: $400,000 Year 3: $400,000 2. What is the project’s net present value? A. $186,897 B. $197,619 C. $208,225 D. $324,538 E. $330,839 Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 9 percent. Year...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project...
You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -29 -45 1 30 45 2 40 50 3 50 50 The appropriate discount rate is 9%. Part 1 What is the NPV of project A (in $ million)? Part 2 What is the NPV of project B (in $ million)?
​(Discounted payback period​) You are considering a project with the following cash​ flows: YEAR   PROJECT CASH...
​(Discounted payback period​) You are considering a project with the following cash​ flows: YEAR   PROJECT CASH FLOW 0   -40,000 1   15,000 2   15,000 3   15,000 4   15,000 If the appropriate discount rate is 12 ​percent, what is the​ project's discounted payback​ period? The​ project's discounted payback period is ___ years.  ​(Round to two decimal​ places.)
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at...
Risky Business is looking at a project with the following estimated cash​ flow: Initial investment at start of​ project: ​$10,000,000 Cash flow at end of year​ one: ​$1,700,000 Cash flow at end of years two through​ six: ​$2,000 each year Cash flow at end of years seven through​ nine: ​$2,040,000 each year Cash flow at end of year​ ten: ​$1,569,231 Risky Business wants to know the payback​ period, NPV,​ IRR, MIRR, and PI of this project. The appropriate discount rate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT