Question

In: Finance

1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The...

1. Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 8 percent.

Year 0: ($700,000)

Year 1: $400,000

Year 2: $400,000

Year 3: $400,000

2. What is the project’s net present value?

A. $186,897

B. $197,619

C. $208,225

D. $324,538

E. $330,839

Chronic Pain Clinic has estimated the following cash flows associated with a new project. The project cost of capital (discount rate) is 9 percent.

Year 0: ($850,000)
Year 1: $400,000
Year 2: $400,000
Year 3: $400,000

What is the project’s internal rate of return?

A. 18.5 percent

B. 19.4 percent

C. 20.6 percent

D. 23.8 percent

E. 24.4 percent

3. Assume a project has the following expected cash flows:

Year 0: ($350,000)
Year 1: $125,000
Year 2: $130,000
Year 3: $170,000
Year 3: $200,000

What is the project’s payback (payback period)?

A. 2.20 years

B. 2.45 years

C. 2.54 years

D. 2.62 years

E. 3.05 years

Solutions

Expert Solution

2. Answer is E

In order to calculate NPV, we need to calculate the sum of all cashlfows discounted at time, t = 0, by 8%

CF0 = -700,000, CF1 = 400,000, CF2 = 400,000, CF3 = 400,000

NPV = -700000 + 370370.4 + 342935.5 + 317532.9 = 330838.79

Project's IRR = 19.4%

In order to calculate this, you need to calculate 'r' in the NPV formula (mentioned above), such that NPV = 0. Manual calculations for IRR are lengthy and should be avoided. Use Excel or Financial calculator to calculate the same.

In Excel, you can use IRR function with cashflows (having appropriate signs - positive for inflow and negative for outflow) as arguments.

3. Answer is C

For calculating the payback, you need to calculate the number of years it would take you to earn back your invested amount.

So, adding cashflows in year 1 and year 2 = $255,000. They would need $95000 more to complete their re-earning of invested amount. But, in year 3, cashflow occuring is $170,000 which is more than that we require.

So, by extrapolation, if company earns $170,000 in that year, it would earn 95,000 in = 95000/170000 = 0.56 years

This implies, total payback = 2 Years + 0.56 year = 2.56 years This is closest to 2.54 years in options)


Related Solutions

Costco, Inc. is conducting a new project with the following estimated cash flows. The initial outlay...
Costco, Inc. is conducting a new project with the following estimated cash flows. The initial outlay is estimated to be ​$1,950,000​, and the incremental cash flows generated by this project would be ​$650,000 per year for 7 years. The estimated required rate of return of the project is 6​%. a. Calculate the NPV. b. Calculate the PI. c. Calculate the IRR. d. Should this project be​ accepted?
•You are looking at a new project and you have estimated the following cash flows: Year...
•You are looking at a new project and you have estimated the following cash flows: Year 0: CF = -$150,000 Year 1-2: CF = $80,000 Year 3-4: CF = $50,000 Year 5-6: CF = $30,000 Year 7: CF = -$180,000 Your cost of capital is 10% Please calculate NPV and IRR, and decide whether we should take this project?
Which of the following cash flows is NOT an incremental cash flow associated with a project...
Which of the following cash flows is NOT an incremental cash flow associated with a project to dig a new gold mine? Select one: a. The cost of taking on new employees who will be hired to work on the mine site. b. The cost of land which will be purchased for the new mine. c. The cost of mining equipment which will be purchased for the new mine. d. The cost of an environmental impact study which has been...
How are cash flows for a project estimated?
How are cash flows for a project estimated?
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0...
1)you've estimated the following cash flows (in$) for a project A. B year. cash flow 0 -5,300 1 1,325 2 2,148 3 2,209 what is the IRE for the project 2)you've estimated the following cash flows (in$) for 2 projects: A. B. C.    year. ProjectA. ProjectB 0. -78 -261 1 15 50 2 21 73 3 29 82 4 35 127 the required return is 7% for both projects What is the IRR for project B? What is the...
Question #1) Cash Payback Period A project has estimated annual net cash flows of $28,000. It...
Question #1) Cash Payback Period A project has estimated annual net cash flows of $28,000. It is estimated to cost $165,200. Determine the cash payback period. Round your answer to one decimal place. years Question #2) Average Rate of Return Determine the average rate of return for a project that is estimated to yield total income of $773,760 over six years, has a cost of $748,800, and has a $83,200 residual value. Round to the nearest whole number. %
A project has the following cash flows:
A project has the following cash flows:YearCash Flow0–$16,60017,30028,60037,100   a.What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)b.What is the NPV at a discount rate of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)c.What is the NPV at a discount rate of 19 percent? (A negative answer should be indicated by a minus sign. Do...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $ 39,500 1 – 18,500 2 – 29,500    What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)      IRR %    What is the NPV of this project, if the required return is 11 percent? (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2...
A project has the following cash flows:
A project has the following cash flows:    Year Cash Flow 0 $64,000 1 –30,000 2 –48,000    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 12 percent?    c. NPV at 0 percent?    d. NPV at 24 percent?
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT