In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.50 | 28,000 | units |
Sprockets | 0.10 | 47,000 | units |
Additional information about the company follows:
Hubs require $33 in direct materials per unit, and Sprockets require $12.
The direct labor wage rate is $11 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 27,000 | 125 | 100 | 225 |
Special processing (machine-hours) | $ | 166,500 | 3,700 | 0 | 3,700 |
General factory (organization-sustaining) | $ | 42,200 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Requirement 1
Activity Cost Pool | Activity rate (A/B) | |
Machine setups | $ 120.00 | Per Setup |
Special processing | $ 45.00 | Per machine hours |
Working
Calculation of Activity rates | |||||
Activity Cost Pool | Activity driver | Overhead Cost (A) | Expected Activity (B) | Activity rate (A/B) | |
Machine setups | Number of Setup | $ 27,000.00 | 225 | $ 120.00 | Per Setup |
Special processing | Number of machine hours | $ 166,500.00 | 3700 | $ 45.00 | Per machine hours |
Requirement 2
Hubs | Sprockets | |
Direct material | $ 33.00 | $ 12.00 |
Direct labor | $ 5.50 | $ 1.10 |
Overheads | $ 6.48 | $ 0.26 |
Total Cost per unit | $ 44.98 | $ 13.36 |
Working
Cost assigned to Hubs | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Machine setups | $ 120.00 | 125.00 | $ 15,000.00 |
Special processing | $ 45.00 | 3,700.00 | $ 166,500.00 |
Total Overheads assigned | $ 181,500.00 | ||
Production | 28,000.00 | ||
Overhead cost per unit | $ 6.48 |
.
Cost assigned to Sprockets | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Machine setups | $ 120.00 | 100 | $ 12,000.00 |
Special processing | $ 45.00 | 0 | $ - |
Total Overheads assigned | $ 12,000.00 | ||
Production | 47,000.00 | ||
Overhead cost per unit | $ 0.26 |