In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
| Direct Labor-Hours per Unit  | 
Annual Production  | 
||
| Hubs | 0.60 | 20,000 | units | 
| Sprockets | 0.20 | 54,000 | units | 
Additional information about the company follows:
Hubs require $36 in direct materials per unit, and Sprockets require $15.
The direct labor wage rate is $17 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
| Estimated | Activity | ||||
| Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
| Machine setups (number of setups) | $ | 35,235 | 145 | 116 | 261 | 
| Special processing (machine-hours) | $ | 220,500 | 4,900 | 0 | 4,900 | 
| General factory (organization-sustaining) | $ | 98,400 | NA | NA | NA | 
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
| 
 Activity Cost Pool  | 
 Overhead cost  | 
 Total Activity  | 
 Activity Rate Answer  | 
|
| 
 [A]  | 
 [B]  | 
 [C = A/B]  | 
||
| 
 Machine setups  | 
 $35,235  | 
 261  | 
 $135.000  | 
 per setup  | 
| 
 Special processing  | 
 $220,500  | 
 4900  | 
 $45.00  | 
 per MH  | 
| 
 Hubs  | 
 Sprockets  | 
|||
| 
 Answer  | 
 Working  | 
 Answer  | 
 Working  | 
|
| 
 Direct materials  | 
 $ 36.00  | 
 [given]  | 
 $ 15.00  | 
 [given]  | 
| 
 Direct labor  | 
 $ 10.20  | 
 0.60 DLHs x $ 17  | 
 $ 3.40  | 
 0.20 DLHs x $ 17  | 
| 
 Overhead  | 
 $ 12.00  | 
 [ (145 x$ 135) + (4900 x $45)]/20000 units]  | 
 $ 0.29  | 
 [ (116 x $ 135) / 54000]  | 
| 
 Unit cost  | 
 $ 58.20  | 
 $ 18.69  | 
||