In: Accounting
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.80 | 16,000 | units |
Sprockets | 0.40 | 41,000 | units |
Additional information about the company follows:
Hubs require $21 in direct materials per unit, and Sprockets require $15.
The direct labor wage rate is $15 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 16,065 | 85 | 68 | 153 |
Special processing (machine-hours) | $ | 144,000 | 4,800 | 0 | 4,800 |
General factory (organization-sustaining) | $ | 258,800 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Solution
Fogerty Company
Determination of the unit product cost of each product according to the ABC System:
Cost per unit - |
||
Hubs |
Sprockets |
|
Direct materials |
$21 |
$15 |
Direct labor |
$12 |
$6 |
Overhead cost |
$9.56 |
$0.17 |
unit product cost |
$42.56 |
$21.17 |
Direct labor rate per unit is as follows,
Hubs - $15 x 0.80 DLH = $12 per unit
Sprockets = $15 x 0.40 DLH = $6 per unit
Workings –
Determination of the overhead cost assigned to each product:
Cost Pool |
Estimated overhead cost |
activity measure |
Activity rate |
|
Machine setups |
$16,065 |
153 setups |
16,065/153 = $105 |
$105 per setup |
Special processing |
$144,000 |
4,800 machine hours |
144,000/4,800 = $30 |
$30 per machine hour |
Since the activity measure for general factory is not provided in the question, no overhead is allocated to the two products, Hubs and Sprockets.
Explanation: Under ABC method, costs are assigned to products based on the activity base, activity usage and activity rates. For, general factory, the information about activity base and usage are not provided in the question, hence this cost is not assigned to the two products.
Overhead assigned to each product
Hubs |
||||
Cost Pool |
Activity measure |
Activity rate |
overhead assigned |
|
Machine setups |
85 Setups |
$105 |
$8,925 |
|
Special processing |
4,800 machine hours |
$30 |
$144,000 |
|
Total overhead assigned |
$152,925 |
|||
number of units |
16,000 |
|||
overhead cost per unit |
$9.56 |
|||
Sprockets |
||||
Cost Pool |
Activity measure |
Activity rate |
overhead assigned |
|
Machine setups |
68 setups |
$105 |
$7,140 |
|
Special processing |
0 |
$25 |
0 |
|
Total overhead assigned |
$7,140 |
|||
number of units |
41,000 |
|||
overhead cost per unit |
$0.17 |