Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.90 | 10,000 | units |
Sprockets | 0.50 | 49,000 | units |
Additional information about the company follows:
Hubs require $32 in direct materials per unit, and Sprockets require $11.
The direct labor wage rate is $16 per hour.
Hubs require special equipment and are more complex to manufacture than Sprockets.
The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 30,420 | 130 | 104 | 234 |
Special processing (machine-hours) | $ | 105,000 | 4,200 | 0 | 4,200 |
General factory (organization-sustaining) | $ | 278,500 | NA | NA | NA |
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Activity Cost Pool |
Overhead cost |
Total Activity |
Activity Rate |
|
[A] |
[B] |
[C = A/B] |
||
Machine setups |
$30,420 |
234 |
$130.000 |
per setup |
Special processing |
$105,000 |
4200 |
$25.00 |
per MH |
Hubs |
Sprockets |
|||
Answer |
Working |
Answer |
Working |
|
Direct materials |
$ 32.00 |
[given] |
$ 11.00 |
[given] |
Direct labor |
$ 14.40 |
0.90 DLHs x $ 16 |
$ 8.00 |
0.50 DLHs x $ 16 |
Overhead |
$ 12.19 |
[(130 x $130)+(4200 x $25)]/10000 |
$ 0.28 |
[(104 x $130)+(0 x $25)]/49000 |
Unit cost |
$ 58.59 |
Answer |
$ 19.28 |
Answer |