Question

In: Operations Management

A producer of pottery is considering the addition of a new plant to absorb the backlog...

A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have the following cost structures as shown in the table. The producer knows there is a big order or order contract that will be awarded by the giant retail WalWal. The producer is not certain as what capacity production is to produce. It all depends on WalWal’s contract. The producer has also been informed, the first batch of pottery is required to ship in a very tight time frame from the first production run. The producer decides to plan ahead and select the best production process to set up for manufacturing.
  

Process 1

Process 2

Process 3

Ann. Fixed Cost $

2,891

4,898

10,014

variable cost $/unit

0.91

0.65

0.51

  
The producer wants you to help them to identify at what range of production quantity (Q) for Process 1, Process 2, and Process 3 is best to adopt.

Enter Q range with whole number and use signs such as <= and >= to describe greater or less than equal to. Ex. 1234 < Q <= 5678

a) The range of annual Q for which Process 1 is best to use is:  

b) The range of annual volume for which Process 2 is best to use is:  

c) The range of annual volume for which Process 3 is best to use is:

Solutions

Expert Solution

Process 1 Process 2 Process 3
Ann. Fixed Cost $ 2,891 4,898 10,014
variable cost $/unit 0.91 0.65 0.51

We need to compare the total cost of these three processes to find the quantity range for which each process is best

Total cost = Fixed cost + Variable cost * No. of units produced

Total cost for 1 unit produced

Process 1 = 2891+0.91*1 = 2891.91

Process 2 = 4898+0.65*1 = 4898.65

Process 3 = 10014+0.51*1 = 10014.51

For 1 unit Process 1 is best as it has the lowest total cost.

The cost will be lowest to a point where any of the other two processes would have an equal total cost. From that point Process 1 would have a higher total cost than the other process.

To find the point process 2 and 3 should be compared with process 1 to find the point at which each one would have equal total cost with process 1

Comparing Process 1 and 2

Let the unit be x at which these two processes would have the equal total cost.

The total cost of P1 = 2891+0.91x

The total cost of P2 = 4898+0.65x

2891+0.91x = 4898+0.65x

=> 0.91x - 0.65x = 4898 - 2891

=> x = (4898 - 2891)/(0.91 - 0.65) = 7719.23

At 7720 units process 2 has a lower cost than process 1

Now comparing Process 1 and Process 3:

The unit at which these two would have equal cost = (10,014-2,891)/(0.91-0.51) = 17807.5

At 17808 process 3 would have a lower total cost than process 1

Now, calculating the total cost of process 2 and 3 at 17808

Process 2 = 4898+0.65*17808 = 16473.2

Process 3 = 10014+0.51*17808 = 19096.08

Though Process 3 has lower cost than Process 1, process 2 is lowest at 17808 units. Hence process 3 is not best at this point and process 2 continues to be the best after 7719.23 and till 17808. (the upper limit is yet to be found)

Hence, Process 1 is best for the unit range of 1 to 7719.23

The lower limit of quantity range for Process 2 is known which is 7719.23 but to find the upper limit, we need to find the quantity at which process 2 stops being best and process 3 becomes best

The quantity at which process 2 and 3 have equal total cost = (10014-4898)/(0.65-0.51) = 36542.86

At 36543 units Process 2 would have a higher total cost than the process 3.

Hence Process 2 is best for a quantity range of 7719.23 to 36542.86

Process 3 has lowest cost for a range of 36542.86 and more.

a) The range of annual Q for which Process 1 is best to use is: 0 < Q <= 7719.23

b) The range of annual volume for which Process 2 is best to use is: 7719.23 < Q <= 36542.86

c) The range of annual volume for which Process 3 is best to use is: 36542.86 < Q and more


Related Solutions

A producer of pottery is considering the addition of a new plant to absorb the backlog...
A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have the following cost structures as shown in the table. The producer knows there is a big order or order contract that will be awarded by the giant retail WalWal. The producer is not certain as what capacity production is to produce. It all depends on WalWal’s contract. The producer has also been...
A producer of pottery is considering the addition of a new plant to absorb the backlog...
A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have fixed costs of $13,450 per month and variable costs of $1.06 per unit produced. Each item is sold to retailers at a price that averages $1.23 a) The volume per month is required in order to break even =  (in whole number) b) The profit or loss would be realized on a monthly...
A producer of pottery is considering the addition of a new plant to absorb the backlog...
A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have fixed costs of $10,456 per month and variable costs of $0.79 per unit produced. Each item is sold to retailers at a price that averages $0.92 a) The volume per month is required in order to break even =  (in whole number)    b) The profit or loss would be realized on a...
A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists
A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have fixed costs of $9,200 per month and variable costs of 70 cents per unit produced. Each item is sold to retailers at a price that averages 90 cents.a. What volume per month is required in order to break even?b. What profit would be realized on a monthly volume of 61,000 units? 87,000...
A producer of plastic mugs is considering the addition of a new plant to absorb the...
A producer of plastic mugs is considering the addition of a new plant to absorb the backlog of demand that now exists. The primary location being considered will have fixed costs of $12,000 per month and variable costs of 60 cents per unit produced. Each item is sold to retailers at a price that averages 82 cents. (please Show work) a) What sales volume per month is required in order for the producer to break even? b) What profit would...
Blue Ridge Mill, was considering the addition of new on-site long-wood woodyard. The addition would have...
Blue Ridge Mill, was considering the addition of new on-site long-wood woodyard. The addition would have two primary benefits: to eliminate the need to purchase short-wood from an outside supplier and create the opportunity to sell short-wood on the open market as a new market for Worldwide Paper Company (WPC). The new woodyard would allow the Blue Ridge Mill not only to reduce its operating costs but also to increase its revenues. The proposed woodyard will utilise new technology that...
Microwave Oven​ Programming, Inc. is considering the construction of a new plant. The plant will have...
Microwave Oven​ Programming, Inc. is considering the construction of a new plant. The plant will have an initial cash outlay of ​$12 ​million, and will produce cash flows of ​$4 million at the end of year​ 1, $ 5 million at the end of year​ 2, and ​$3 million at the end of years 3 through 5. What is the internal rate of return on this new​ plant?
A manufacturer of air filter systems for industrial facilities, is considering the addition of a new...
A manufacturer of air filter systems for industrial facilities, is considering the addition of a new system to its current product line. The following data has been forecasted: Years 2012 2013 2014 2015 Depreciation 30,000 35000 40000 45000 EBIT 100,000 125,000 150,000 175,000 Investment in Operating Assets 30,000 40,000 50,000 60,000 The market value of the firm's debt is $500,000 and it has $150,000 in marketable securities. The company also has 10,000 of preferred stocks that just paid an annual...
You are considering opening a new plant. The plant will cost $103.9 million up front and...
You are considering opening a new plant. The plant will cost $103.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.5%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
You are considering opening a new plant. The plant will cost $97.9 million up front and...
You are considering opening a new plant. The plant will cost $97.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.8%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT