Question

In: Operations Management

QUESTION 2 Consider the following four--?step assembly operation with quality problems. -The first resource has a...

QUESTION 2

Consider the following four--?step assembly operation with quality problems.

-The first resource has a processing time of 7 minutes per unit and one employee doing the operation

? The second resource has a processing time of 4 minutes per unit.  It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step.

? Two workers are staffed for the third resource. No quality problems occur at this resource and the processing time is 17minutes per unit.

? At the fourth and final resource, one operator handles the product. No quality problems exist at this step and the processing time is 12 minutes per unit.

What is the process capacity per hour? (keep two decimal)

Solutions

Expert Solution

The effective processing time at first resource = 7   minutes / unit

Sine 0.79 of all products have to be scrapped, it is only 0.21 of all products pass on as good products to third resource. The second resource has a processing time ( good + bad products together ) of 4 minutes.

Therefore effective processing time of good products at second resource = 4/ 0.21 = 19.047 minutes / unit

Effective processing time at third resource with no quality problem = 17 minutes/ unit

Effective processing time at fourth resource with no quality problem = 12 minutes /unit.

It is the capacity of the bottleneck resource which will decide capacity of the whole process .

The bottleneck resource is the one which takes maximum processing time per GOOD unit.

The bottleneck resource in this case is SECOND   resource which takes 19.047   minutes/ unit

Therefore , overall process capacity = 19.047    minutes/ unit

Hence process capacity per hour = 60 / 19.047 = 3.15

PROCESS CAPACITY PER HOUR = 3.15 UNITS


Related Solutions

Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time...
Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time of 7 minutes per unit and one employee doing the operation ? The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step. ? Two workers are staffed for the third resource. No quality problems occur...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time o...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time of 5 minutes per unit and one employee doing the operation ‐ The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.85 of all products have to be scrapped after this step. ‐ Two workers are staffed for the third resource. No quality problems occur...
Consider the following snapshot of a system that has four resource types: A, B, C, and...
Consider the following snapshot of a system that has four resource types: A, B, C, and D and five processes, P0, P1, P2, P3, and P4. Allocation Max A B C D A B C D P0 3 0 1 5 5 1 1 7 P1 2 2 1 0 3 2 1 1 P2 3 1 2 1 3 3 2 1 P3 0 5 1 0 4 6 1 2 P4 4 2 1 3 6 3 2...
The following diagram shows a four step process that begins with Operation 1 and ends with...
The following diagram shows a four step process that begins with Operation 1 and ends with Operation 4. The rates shown in each box represent the effective capacity of that operation a. Determine the capacity of this process. b. Which action would yield the greatest increase in process capacity: (1) Increase the capacity of Operation 1 by 15%; (2) Increase the capacity of Operation 2 by 10%; and (3) Increase the capacity of Operation 3 by 10%. ( This is...
For problems 3 and 4, consider the following functions that implement the dequeue operation for a...
For problems 3 and 4, consider the following functions that implement the dequeue operation for a priority queue that is implemented with a heap. int[] pQueue; int length; int dequeue() { int node = 1; int value = pQueue[--length]; int maxValue = pQueue[node]; int location = sift(node * 2, value); pQueue[location] = value; return maxValue; } int sift(int node, int value) { if (node <= length) { if (node < length && pQueue[node] < pQueue[node + 1]) node++; if (value...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and...
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as following table. Job Operation 1 (Hours) Operation 2 (Hours) A 10 5 B 7 4 C 5 7 D 3 8 E 2 6 F 4 3 Determine the sequence that will minimize the total completion time for the jobs using Johnson’s rule. Illustrate graphically the throughput time and idle time at the two operations by...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and...
Six jobs are to be processed through a? two-step operation. The first operation involves? sanding, and the second involves painting. Processing times are as? follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D 14 14 E 6 1 F 7 12 A) Using? Johnson's rule for? 2-machine scheduling, the sequence? is: b) For the schedule developed using? Johnson's rule, the total length of time taken to complete the six jobs? (including...
Assembly langugage , please do comment each line or step if possible . Question 2 of...
Assembly langugage , please do comment each line or step if possible . Question 2 of 2. Element wise vector multiplication: [30 marks] Write an assembly language program that performs element wise multiplication of two arrays of size 4 and stores the resultant array back into memory. For Arrays A = [Aw, Ax, Ay, Az] and B = [Bw, Bx, By, Bz], the resultant array C = [Aw*Bw, Ax*Bx, Ay*By, Az*Bz] 1. Reserve and initialize memory for both input arrays...
A component requires two (2) operations to complete it. The first operation has the following information:...
A component requires two (2) operations to complete it. The first operation has the following information: Machining Time = 2.445 min., Handling Time = 1.334 min., Tool Change Time = 21.45 min. which needs to be changed every 1675 pieces with a Tool Cost of $133.00 per tool. The operational cost for the first operation = $116.67 per hour. The second operation has the following information: Machining Time = 1.436 min., Handling Time = 0.849 min., Tool change Time =...
I need a step by step answer for the following question: Four states were randomly selected,...
I need a step by step answer for the following question: Four states were randomly selected, and their members in the U.S. House of Representatives (114th Congress) are noted. At a = 0.10, can it be concluded that there is a dependent relationship between the state and the political party affiliation of its representatives? California Florida Illinois Texas Democrat 39 10 10 11 Republican 14 17 8 25
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT