Question

In: Operations Management

The following diagram shows a four step process that begins with Operation 1 and ends with...

The following diagram shows a four step process that begins with Operation 1 and ends with Operation 4. The rates shown in each box represent the effective capacity of that operation

a. Determine the capacity of this process.

b. Which action would yield the greatest increase in process capacity: (1) Increase the capacity of Operation 1 by 15%; (2) Increase the capacity of Operation 2 by 10%; and (3) Increase the capacity of Operation 3 by 10%.

( This is the diagram below )

Operation 1 (20 units/hr) Operation 2 (18 units/hr) Operation 3 (24 units/hr) Operation 4 (22 units/hr)

Solutions

Expert Solution

a.Bottle neck of the process is the operation with the longest processing time per unit or the process with lowest number of units processed per hour.Hence,Operation #2 is the bottleneck in the process.

Therefore,

Capacity of the process =Capacity of the bottleneck=18 units per hour

b.The correct answer is option 2:Increase the capacity of Operation 2 by 10%

Since the bottleneck of the process is operation 2,increasing the capacity of this operation by 10 % ,would yield the greatest increase in process capacity.

New process capacity would be =1.1*18=19.8 units per hour


Related Solutions

JCPenny entered into a contract with Emma. The contract begins on May 1 and ends on...
JCPenny entered into a contract with Emma. The contract begins on May 1 and ends on November 31, 2020. JCpenny will exchange 100 of their most popular watches at a discount as well as 100 glasses for brand-specific marketing. The regular wholesale price of the shirts is $65. JcPenny expects the cost to produce each mask will be $6. All goods that they sell have a profit margin of about 54%. Being able to carry these exclusive products is important...
QUESTION 2 Consider the following four--?step assembly operation with quality problems. -The first resource has a...
QUESTION 2 Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time of 7 minutes per unit and one employee doing the operation ? The second resource has a processing time of 4 minutes per unit.  It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step. ? Two workers are staffed for the third resource. No quality problems...
Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time...
Consider the following four--?step assembly operation with quality problems. -The first resource has a processing time of 7 minutes per unit and one employee doing the operation ? The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step. ? Two workers are staffed for the third resource. No quality problems occur...
A production process consists of a three-step operation. The scrap rate is 19 percent for the...
A production process consists of a three-step operation. The scrap rate is 19 percent for the first step and 7 percent for the other two steps. a.If the desired daily output is 455 units, how many units must be started to allow for loss due to scrap? (Do not round intermediate calculations. Round up your final answer to the next whole number.) Number of units             b.If the scrap rate for each step could be cut in half at...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time o...
Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time of 5 minutes per unit and one employee doing the operation ‐ The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 0.85 of all products have to be scrapped after this step. ‐ Two workers are staffed for the third resource. No quality problems occur...
Consider a four-step serial process with processing times given in the following list. There is one...
Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process. bullet Step 1: 25 minutes per unit bullet Step 2: 15 minutes per unit bullet Step 3: 30 minutes per unit bullet Step 4: 20 minutes per unit Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 105 units?
1. For the function f (x) = 2x² + 8 use the limit definition (four-step process)...
1. For the function f (x) = 2x² + 8 use the limit definition (four-step process) to find f′(x) . Students must show all steps (more or less four of them) to compute the derivative. Simply giving the derivative of the function will not receive much credit. 2. For the function f (x) = x² + 2x a. Find f′(x) . Students may use derivative rules to find this derivative. Show all work and clearly label the answer below. b....
Which of the following is not a step in the accounting process?
Which of the following is not a step in the accounting process? Multiple Choice  Record relevant transactions and events in a journal. Post journal information to the ledger accounts. Prepare and analyze the trial balance. Analyze each transaction. Verify that revenues and expenses are equal.
Use the four-step process to find the derivative for: You need to use:  
Use the four-step process to find the derivative for: You need to use:  
For the following program descriptions, write step by step pseudo code that shows you understand the...
For the following program descriptions, write step by step pseudo code that shows you understand the problem and what it takes to solve it. The first one is done for you as an example. Please answer the questions in the same format as the example problem below so it is the same. Example #1 Problem A customer is purchasing five items. Design a program where you collect the amount of each item, calculate the subTotal of the items, the tax...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT