In: Operations Management
The effective processing time at first resource = 7 minutes / unit
Sine 0.79 of all products have to be scrapped, it is only 0.21 of all products pass on as good products to third resource. The second resource has a processing time ( good + bad products together ) of 4 minutes.
Therefore effective processing time of good products at second resource = 4/ 0.21 =19.04 minutes / unit
Effective processing time at third resource with no quality problem = 17 minutes/ unit
Effective processing time at fourth resource with no quality problem = 12 minutes /unit.
It is the capacity of the bottleneck resource which will decide capacity of the whole process .
The bottleneck resource is the one which takes maximum processing time per GOOD unit.
The bottleneck resource in this case is second resource which takes 19.04 minutes/ unit
Therefore , overall process capacity = 19.04 minutes/ unit
Hence process capacity per hour = 60 / 19.04 units = 3.15 units
PROCESS CAPACITY PER HOUR = 3.15 UNITS |