In: Finance
Based on the information provided for a one-year project, answer
the following questions.
PV =$100,000 AC =$60,000 BAC=$125,000 ETC = $100,000
Since you have asked a question with numerous sub parts, I will address first five. Please post the balance sub parts as separate question.
This is a fairly formula driven question. Let's address them one by one.
PV = $100,000 AC = $60,000 BAC = $125,000 ETC = $100,000
===================
If 75% of the Planned Value was completed to date, what is the Earned Value of the work completed (round to nearest whole number)?
EV = % complete x Planned Value = 75% x 100,000 = $75,000
====================
What is the Cost Variance (round to nearest whole number)?
Cost Variance, CV = Earned Value, EV – Actual Cost, AC = 75,000 - 60,000 = $15,000
================
What is the Schedule Variance (round to nearest whole number)?
Schedule Variance, SV = Earned Value, EV – Planned Value, PV = 75,000 - 100,000 = - $ 25,000
================
What is the Cost Performance Index (round to 2 decimals)?
Cost Performance Index, CPI = EV / AC = 75,000 / 60,000 = 1.25
===================
What is the Schedule Performance Index (round to 2 decimals)?
Schedule Performance Index, SPI = EV / PV = 75,000 / 100,000 = 0.75
Please post the balance sub parts as separate question.