Question

In: Accounting

Given the following information for a one-year project, answer the following questions. Remember the following terms;...

Given the following information for a one-year project, answer the following questions. Remember the following terms; planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC).

PV = $44,000

EV = $53,000

AC = $45,000

BAC = $140,000

a). Use the formulas provided in Table 1, to determine the project’s cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

Table 1: Earned Value Formulas

Term Formula

Earned value EV = PV to date X% complete

Cost variance CV = EV – AC

Schedule variance SV = EV – PV

Cost performance index CPI = EV / AC

Schedule performance index SPI = EV / PV

Estimate at completion (EAC) EAC = BAC / CPI

Estimated time to complete

Original time estimate / SPI

b). How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

c). Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

d). Use the schedule performance index (SPI) to estimate how long it will take to finish this project

Solutions

Expert Solution

Let us first understand the terms given in the question.

Planned Value: This is the first value in EARNED VALUE MANAGEMENT. Planned value is approved value of the work to be completed in given time.

Actual Cost : This is the second value in EARNED VALUE MANAGEMENT. Actual cost is the total cost incurred for actual work completed to date.

Earned Value : This is the third and last value in EARNED VALUE MANAGEMENT. Earned Value is value of work actually completed to date.

Project Cost Variance : This the difference between Budgeted cost & actual cost.

Schedule Variance : It indicates how much ahead or behind schedule the project is.

Cost Performance Index : It is a measure of the financial effectiveness & efficiency of a project. It represents the amount of completed work for every unit of cost spent.

Schedule Performance Index : It is a measure of the conformance of actual progress (earned value) to the planned progress: SPI = EV / PV.

Now answers to the questions are as follows:

a) Project Cost Variance : EV - AC

Here, EV= $ 53,000 & AC = $ 45000

Hence, CV = $ 53,000 - $ 45,000 = $ 8,000

Schedule Variance : EV - PV

Here, EV = $ 53,000 & PV = $ 44,000

Hence, SV = $ 53,000 - $ 44,000 = $ 9,000

Cost Performance Index : EV/AC

Here, EV= $ 53,000 & AC = $ 45000

Hence, CPI = $ 53,000/ $ 45000 = 1.178

Schedule Performance Index : EV/PV

Here, EV = $ 53,000 & PV = $ 44,000

Hence, SPI = $ 53,000/ $ 44000 = 1.20

b) Schedule variance indicates how much ahead or behind schedule the project is. As Earned value is greater than Planned value, the project is ahead of schedule.

Cost Performance Index : It is a measure of the financial effectiveness & efficiency of a project.

If CPI is greater than 1, then project is under budget.

If CPI is 1, the project is on budget.

If CPI is less than 1, the project is over budget.

As the CPI of the project is 1.178, then the project is under budget.

C) Estimate At Completeion = BAC / CPI, It is the estimate of the forcasted cost of the project, as the project progresses.

Here, BAC = $ 1,40,000 & CPI = 1.178

Hence, EAC = 140000/1.178 = $ 1,18,845.50 (Approx)

As EAC $ 1,18,845.50 is less than planned i.e. $ 1,40,000 , the project is performing better than planned.

d) According to the formula of estimating time to complete this project as below:

12 months/ SPI

hence, 12/1.20= 10 months. It will take 10 months to complete the project.

*********


Related Solutions

Given the following information for a one-year project, answer the following questions. Remember the following terms;...
Given the following information for a one-year project, answer the following questions. Remember the following terms; planned value (PV), earned value (EV), actual cost (AC), and budget at completion (BAC). PV    =      $44,000 EV    =      $53,000 AC    =      $45,000 BAC =    $140,000 a).    Use the formulas provided in Table 1, to determine the project’s cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Table 1: Earned Value Formulas Term Formula Earned value EV =...
Based on the information provided for a one-year project, answer the following questions. PV =$100,000     AC...
Based on the information provided for a one-year project, answer the following questions. PV =$100,000     AC =$60,000     BAC=$125,000    ETC = $100,000 If 75% of the Planned Value was completed to date, what is the Earned Value of the work completed (round to nearest whole number)? What is the Cost Variance (round to nearest whole number)? What is the Schedule Variance (round to nearest whole number)? What is the Cost Performance Index (round to 2 decimals)? What is the Schedule Performance...
Answer the following questions. Remember that you can only enter numbers in the boxes given and...
Answer the following questions. Remember that you can only enter numbers in the boxes given and that decimal places are separated with a dot (not with a comma). Do not leave empty boxes, otherwise partial marks will not be given. Also, enter at least 4 decimals in your answers whenever possible. Suppose you have the following AD and AS equations: ?=82−0.8?Y=82−0.8π (AD equation) ?=−7+1.8?Y=−7+1.8π (Short Run AS equation) ?=49.15Y=49.15 trillions (Long Run output) a) The real GDP in equilibrium the...
Given the following information, answer the following questions for month 12 of this security -15 year...
Given the following information, answer the following questions for month 12 of this security -15 year FRMs, monthly payments -PSA 150 -4.5% mortgage rate, 0.5% servicing fee, 3.75% discount rate - Pool balance at the beginning of month 12: $75,946,124 - The loans were not seasoned before entering the pool C: What is the payment to investors in month 12? Round your answer to the nearest cent.
Given a project with the following characteristics, answer the following questions: You are the project manager...
Given a project with the following characteristics, answer the following questions: You are the project manager of a project to upgrade the generators at cell phone towers. Your project is scheduled to last for 12 months. It is the beginning of month 4. Your crews are to upgrade 8 cell phone towers per month for 12 months. Each generator is planned to cost $40,000 which includes equipment, labor, and fueling costs. You have upgraded 30 cell phone towers and your...
1. Use the following information to answer the next three questions. One year interest rates for...
1. Use the following information to answer the next three questions. One year interest rates for identical investments in Japan and Canada are 7% and 2%, respectively. The current exchange rates for the two currencies are as follows: C$1.25/$, $ .008/¥. What should be the one-year forward rate according to IRP? 2. Suppose the one-year forward rate is ¥106.5/C$. Calculate the actual forward premium/discount, assuming Japan is the home country. Round intermediate steps and your final answer four decimals. Enter...
1.) Use the given information below to answer the following questions. a.) A sample of 25...
1.) Use the given information below to answer the following questions. a.) A sample of 25 lightbulbs was taken and it was found that the mean lifetime of a certain bulb for a movie projector is 520 hours with a standard deviation of 50 hours. The standing assumption of the manufacturing company is that the lifetime of this type pf bulb is no more than 500 hours. Assume a normal distribution. Does the data support the company’s claim at a...
Required information Use the following information to answer questions [The following information applies to the questions...
Required information Use the following information to answer questions [The following information applies to the questions displayed below.] The following information is available for Lock-Tite Company, which produces special-order security products and uses a job order costing system. April 30 May 31 Inventories Raw materials $ 31,000 $ 30,000 Work in process 9,500 18,200 Finished goods 54,000 34,000 Activities and information for May Raw materials purchases (paid with cash) 197,000 Factory payroll (paid with cash) 200,000 Factory overhead Indirect materials...
Given the following input-output table, answer questions a-h. Note that a one word answer is not...
Given the following input-output table, answer questions a-h. Note that a one word answer is not acceptable. For full credit, you must provide explanation for your answers and show how you arrive at them.                              Man Hour Required to Produce Unit of Output                                Country A            Country B                     Good X         3                    12                     Good Y         2                    14             a. Which country has absolute advantage in which good? Why?             b. Which country has comparative advantage in which good? Why?...
Given the following input-output table, answer questions a-h. Note that a one word answer is not...
Given the following input-output table, answer questions a-h. Note that a one word answer is not acceptable. For full credit, you must provide explanation for your answers and show how you arrive at them.                              Man Hour Required to Produce Unit of Output                                Country A            Country B                     Good X         3                    12                     Good Y         2                    14             a. Which country has absolute advantage in which good? Why?             b. Which country has comparative advantage in which good? Why?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT