Question

In: Finance

How does the NPV, IRR and the payback period of an Investment usually react to the...

How does the NPV, IRR and the payback period of an Investment usually react to the following developments (please indicate, UP/DOWN or N/A)?

1. Increasing Investment amount

2. Increasing tax rate

3. Increased annual depreciation due to change of depreciation method

4. Increasing cost of capital

5. Increasing residual value

So I actually Need 15 indications (5*3) - TIA

Solutions

Expert Solution

1.         Payback Period (PBP)

            One of the most popular and widely recognized traditional methods of evaluating capital investment proposal is the payback period. It is the number of years it takes a firm to recover its original investment from net cash flows. The payback period of an investment is the length of time required for the cumulative total net cash flows from the investment to equals to total initial cash outlays.

General Rule – Earlier the better.

2.         Net Present Value (NPV)

            It is the Present value of the projects net cash flows discounted at the company’s cost of capital to the time of the initial capital outlay, minus that initial capital outlay.

General Rule – Higher the NPV, better it is.

3.         Internal rate of Return (IRR)

            IRR is the rate of return at which present value of cash inflows equals to present value of cash outflows.

General Rule – Higher the better.

Impact of various factor on NPV , IRR and payback period provided in below table -

NPV IRR Payback Period Reason
1 Increasing Investment Amount Down Down Up As it increase the cash outflow
2 Increasing Tax rate Down Down Up As it increase the cash outflow
3 Increased Annual Depreciation Up Up Down It will increase the tax shield resulting increase in cash-inflow
4 Increasing cost of capital Down N.A N.A Cost of capital only relevant for NPV. Increase cost of capital reduce the PV of cash inflow.
5 Increasing residual value Up Up N.A Increase the Cash inflow. Not relevant for Payback period as salvage value received at the end of period

1) Internal rate of Return (IRR) is the rate at PV of cash-inflows equals to the PV of cash-outflow, which means IRR depends upon the Cash flows that's why Cost of capital (required rate of return) has no impact on the IRR. Further, Payback period doesn't consider the time value of money that's why cost of capital has no impact on payback period.

2) Payback period is the period in which cash inflows recover the initial capital investment (cash outflow) and salvage cash inflow received at the end of project that's why it has no impact on payback period. If project fails to recover the initial capital investment till end of the project then there would be no payback period for the period.

3) As discussed in Point-1, IRR depends upon the cash flows and residual/salvage is a cash inflow for the project that's why it increases the IRR of the project.


Related Solutions

While NPV and IRR are measures of return of a project/investment. Payback is a measure of...
While NPV and IRR are measures of return of a project/investment. Payback is a measure of risk. Explain what payback tells about a project/investment and how is it calculated.
IN EXCEL< SHOW THE FORMULAS > Determine the Payback period, NPV and IRR for both project...
IN EXCEL< SHOW THE FORMULAS > Determine the Payback period, NPV and IRR for both project A and B (show work). Which Project would you select and why? Be specific. Project A will require an initial investment of $ 200,000 and Project B will require and initial investment of $ 325,000. The cost of capital for both projects is 12%. The cash inflows for the next 5 years are listed below: Project A Project B 0 ($200,000) ($325,000) 1 $50,000...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
Describe NPV, IRR, ARR and Payback Period In a brief paragraph or a few sentences for...
Describe NPV, IRR, ARR and Payback Period In a brief paragraph or a few sentences for each method. These are the 4 most common methods to evaluate capital projects.
5. The NPV and payback period What information does the payback period provide? Suppose you are...
5. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $450,000 Year 3 $425,000 Year 4 $450,000 If...
5. The NPV and payback period Part A What information does the payback period provide? Suppose...
5. The NPV and payback period Part A What information does the payback period provide? Suppose Acme Manufacturing corp CFO is evaluating a project w the following cash Inflows. She does not know the project's initial cost; however he does know that the projects regular payback period is 2.5 years. Year Cash flow 1. $350,000 2. $400,000 3. $400,000 4. $400,000 If the project's weighted average cost of capital (WACC) is 10%, what is its NPV? answer options: $326,990; $299,741;...
8. The NPV and payback period What information does the payback period provide? Suppose you are...
8. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $375,000 Year 2 $500,000 Year 3 $500,000 Year 4 $450,000 If...
7. The NPV and payback period What information does the payback period provide? Suppose you are...
7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $325,000 Year 2 $425,000 Year 3 $500,000 Year 4 $425,000 If...
The NPV and payback period What information does the payback period provide? Suppose you are evaluating...
The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $475,000 Year 3 $400,000 Year 4 $475,000 If the...
7. The NPV and payback period What information does the payback period provide? Suppose you are...
7. The NPV and payback period What information does the payback period provide? Suppose you are evaluating a project with the expected future cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. Year Cash Flow Year 1 $275,000 Year 2 $500,000 Year 3 $450,000 Year 4 $450,000 If...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT