Question

In: Finance

For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each...

For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years. Risk free rate = 1.10%, MRP = 9.5%, Required return = 14.40% Yes excel is fine

Expected cash flows for the four potential projects that Avalon is considering as shown below:                       

Year

Project A

Project B

Project C

Project D

0

-$7,250,000

-$8,500,000

-$6,500,000

-$4,500,000

1

$2,000,000

$1,000,000

$2,000,000

$2,000,000

2

$2,500,000

$1,500,000

$2,000,000

$2,000,000

3

$3,000,000

$2,000,000

$2,500,000

$1,000,000

4

$1,000,000

$2,000,000

$2,500,000

$1,000,000

5

$1,000,000

$1,600,000

$2,000,000

$500,000

6

$1,000,000

$1,600,000

$500,000

7

$1,500,000

8

$1,500,000

9

$1,500,000

10

$1,500,000

I have provided a suggested template for your final answers. Below the grid (and/or next page) is where you should show all your required backup calculations. If you are working this in Excel, feel free to submit your Excel sheet, where the equations in the cells will provide the required backup. Be sure to clearly indicate the required rate of return for each project (you calculated this in Problem 3).    

Year

Project A

Project B

Project C

Project D

Points

Req. Return (use 2 decimals xx.xx%)

4

4a

NPV (to nearest $1)

1

4b

NPV accept/reject

2

5a

IRR (xx.xx%)

1

5b

IRR accept/reject

2

6a

PI (show 2 decimals)

1

6b

PI accept/reject

2

7a

Payback Period (x.x years)

1

7b

Payback accept/reject

Solutions

Expert Solution

NPV is the difference between present value of cash flows and initial investment. If NPV is positive of a project then it will be accepted. If NPV is negative then it will be rejected.

IRR is the internal rate of return at which present value of cash flows are equal to initial investment. If a project's IRR is greater than its required return then it will be accepted or it will be rejected if its IRR is lower than required return.

PI or the profitability index is the ratio of benefits (present value of cash flows) and cost (initial investment). If a project has PI of greater than 1 then it will be accepted and if it is lower than rejected.

PI = present value of cash flows/initial investment

Payback period is the time taken by a project's cash flows to recover its initial investment. if project's payback period is lower than required payback period then it will be accepted. otherwise it will be rejected.

In the below table, we have cumulative cash flows of project A in column C. we can see in column C that project A recovers $4,500,000 in 2 years. remaining initial investment of $7,250,000 - $4,500,000 = $2,750,000‬ it will recover in year 3 from year 3 cash flow of $3,000,000. so payback period of project A is 2 years + $2,750,000/$3,000,000 = 2 years + 0.9 or 2.9 years.

Year Project A Cumu. Cash flow Project B Cumu. Cash flow Project C Cumu. Cash flow Project D Cumu. Cash flow
0 -$7,250,000 -$8,500,000 -$6,500,000 -$4,500,000
1 $2,000,000 $2,000,000 $1,000,000 $1,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000
2 $2,500,000 $4,500,000 $1,500,000 $2,500,000 $2,000,000 $4,000,000 $2,000,000 $4,000,000
3 $3,000,000 $7,500,000 $2,000,000 $4,500,000 $2,500,000 $6,500,000 $1,000,000 $5,000,000
4 $1,000,000 $8,500,000 $2,000,000 $6,500,000 $2,500,000 $9,000,000 $1,000,000 $6,000,000
5 $1,000,000 $9,500,000 $1,600,000 $8,100,000 $2,000,000 $11,000,000 $500,000 $6,500,000
6 $1,000,000 $10,500,000 $1,600,000 $9,700,000 $500,000 $7,000,000
7 $1,500,000 $11,200,000
8 $1,500,000 $12,700,000
9 $1,500,000 $14,200,000
10 $1,500,000 $15,700,000
Req. Return 14.40% 14.40% 14.40% 14.40%
NPV (to nearest $1) -$47,453.00 -$511,987.42 $926,545.19 $506,434.73
NPV accept/reject Reject Reject Accept Accept
IRR (xx.xx%) 14.12% 12.86% 20.08% 19.82%
IRR accept/reject Reject Reject Accept Accept
PI (show 2 decimals) 0.99 0.94 1.14 1.11
PI accept/reject Reject Reject Accept Accept
Payback Period (x.x years) 2.9 5.3 3.0 2.5
Payback accept/reject Accept Reject Accept Accept

Calculations


Related Solutions

. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
. Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback A project has an initial...
. Complete problems: NPV, IRR, MIRR, Profitability Index, Payback, Discounted Payback A project has an initial cost of $60,000, expected net cash inflows of $10,000 per year for 8 years, and a cost of capital of 12%. Show your work. a. What is the project’s NPV? (Hint: Begin by constructing a timeline). b. What is the project’s IRR? c. What is the project’s MIRR? d. What is the project’s PI? e. What is the project’s payback period? f. What is...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$90,000 and expected free cash flows of ​$28,000 at the end of each year for 5 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$80000 and expected free cash flows of ​$25000 at the end of each year for 6 years. The required rate of return for this project is 9 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
​(Payback period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of $70,000 and expected free cash flows of ​$28,000 at the end of each year for 5 years. The required rate of return for this project is 8 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$90,000 and expected free cash flows of ​$22,000 at the end of each year for 7 years. The required rate of return for this project is 9 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$90,000 and expected free cash flows of ​$26,000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$80,000 and expected free cash flows of ​$24,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? 3.33 years b. What is the​ project's NPV​? ____ c. What is the​ project's PI​? _____ d. What is the​ project's IRR​? _____
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT