Question

In: Finance

Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required...

Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 12%.

Cashflow for each year

Project A : Year 0= -2500 Year 1=900 Yaer 2=800 Year 3=1600 Year 4=100 Yaer 5=50 Year 6= 300

Project B Year 0 =-2500 Year 1=50 Year2= 600 Year 3=150 Year 4=900 Year 5= 500 Year 6=2500

Solutions

Expert Solution

NPV:

NPV is calculated by discounting the cashflows

PV = C/(1+r)^n

C - Cashflow

r - Discount rate

n - years to the cashflow

Project A:

NPV = -2500 + 900/(1+0.12)^1 + 800/(1+0.12)^2 + 1600/(1+0.12)^3 + 100/(1+0.12)^4 + 50/(1+0.12)^5 + 300/(1+0.12)^6 = 324.09

Project B:

NPV = -2500 + 50/(1+0.12)^1 + 600/(1+0.12)^2 + 150/(1+0.12)^3 + 900/(1+0.12)^4 + 500/(1+0.12)^5 + 2500/(1+0.12)^6 = $251.98

IRR:

IRR is the rate at which NPV = 0

Project A:

NPV = -2500 + 900/(1+IRR)^1 + 800/(1+IRR)^2 + 1600/(1+IRR)^3 + 100/(1+IRR)^4 + 50/(1+IRR)^5 + 300/(1+IRR)^6 = 0

By trail and error, IRR = 17.91%

Project B:

NPV = -2500 + 50/(1+IRR)^1 + 600/(1+IRR)^2 + 150/(1+IRR)^3 + 900/(1+IRR)^4 + 500/(1+IRR)^5 + 2500/(1+IRR)^6 = 0

By trail and error, IRR = 14.38%

PI:

Profitability Index = (NPV + Initial Investment) / Initial investment

Project A = (324.09 + 2500)/2500 = 1.13

Project B = (251.98 + 2500)/2500 = 1.10

Payback period :

Payback period = A + B/C

Where,
A = Last period with a negative cumulative cash flow;
B = Absolute value of cash flow at the end of the period A;
C = cash flow during the period after A.

Project A:

Year Cashflow (A) Cummulative
0 -2500 -2500
1 900 -1600
2 800 -800
3 1600 800
4 100 900
5 50 950
6 300 1250

Payback period = 2 + 800/1600 = 2.5 years

Project B:

Year Cashflow (A) Cummulative
0 -2500 -2500
1 50 -2450
2 600 -1850
3 150 -1700
4 900 -800
5 500 -300
6 2500 2200

Payback period = 5 + 300/2500 = 5.12 years


Related Solutions

Find out the NPV, IRR and Payback period for each of the following three projects. Assume...
Find out the NPV, IRR and Payback period for each of the following three projects. Assume I=6%.                                                                                                                                    (60 points) Project CF0 CF1 CF2 CF3 CF4 CF5 A -12,000 3000 3000 4000 4000 1000 B -12,000 4000 4000 3000 3000 1000 C -12,000 3000 3000 3000 3000 1000 D -12,000 5000 3000 5000 3000 0 E -12,000 3000 3000 3000 3000 5000 F -12,000 0 0 6000 6000 6000
Find out the NPV, IRR and Payback period for each of the following three projects. Assume...
Find out the NPV, IRR and Payback period for each of the following three projects. Assume I=6%. Please show work and write out answers. Do not put into a table. Thank you    Project CF0 CF1 CF2 CF3 CF4 CF5 A -12,000 3000 3000 4000 4000 1000 B -12,000 4000 4000 3000 3000 1000 C -12,000 3000 3000 3000 3000 1000 D -12,000 5000 3000 5000 3000 0 E -12,000 3000 3000 3000 3000 5000 F -12,000 0 0 6000...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
23. Does the Payback Period, Discounted Payback Period, NPV, IRR, PI ratio and MIRR given you...
23. Does the Payback Period, Discounted Payback Period, NPV, IRR, PI ratio and MIRR given you the same accept/reject decision. Discuss the limitations of the methods that give you a decision different than that of the NPV.
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$90,000 and expected free cash flows of ​$28,000 at the end of each year for 5 years. The required rate of return for this project is 6 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each...
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years. Risk free rate = 1.10%, MRP = 9.5%, Required return = 14.40% Yes excel is fine Expected cash flows for the four potential projects that Avalon is...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$80000 and expected free cash flows of ​$25000 at the end of each year for 6 years. The required rate of return for this project is 9 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
​(Payback period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
​(Payback period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of $70,000 and expected free cash flows of ​$28,000 at the end of each year for 5 years. The required rate of return for this project is 8 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT