Question

In: Finance

You are considering the following two projects. Which project(s)should you choose?ProjectYear 0Cash...

You are considering the following two projects. Which project(s) should you choose?

Project

Year 0

Cash Flow

Year 1

Cash Flow

Year 2

Cash Flow

Year 3

Cash Flow

Year 4

Cash Flow

Discount Rate (r)

A

-$120

$40

$40

$40

$40

15%

B

-$90

$30

$30

$30

$30

15%

Solutions

Expert Solution

We will calculate NPV to select project.

We know that,

NPV = Present value of all the future cash flow - initial cost

Project A:

NPV = 40/(1+0.15)^1 + 40/(1+0.15)^2 + 40/(1+0.15)^3 + 40/(1+0.15)^4 - 120

NPV = -5.80 Answer

Project B:

NPV = 30/(1+0.15)^1 + 30/(1+0.15)^2 + 30/(1+0.15)^3 + 30/(1+0.15)^4 - 90

NPV = -4.35 Answer

Since both projects have negative NPV, I would suggest not to consider any project.

Since, we need to consider one project, you will select Project B as it has higher NPV.


Related Solutions

You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Calculate and choose project/s assuming that these two projects are (1) mutually exclusive OR (2) independent....
Calculate and choose project/s assuming that these two projects are (1) mutually exclusive OR (2) independent. IRR (WACC 6%), specify range. CFs Year A B 0 -2050 -4300 1 750 1500 2 760 1518 3 770 1536 4 780 1554
1: When projects are mutually exclusive, you should choose the project with the: Assuming an interest...
1: When projects are mutually exclusive, you should choose the project with the: Assuming an interest rate of 14%, what is the net present value of an investment with the cash flows indicated in the table? CF0 -$193,000   CF1 $50,235   CF2 $62,850   CF3 $62,850   CF4 $48,910   CF5 $87,415 2- Assuming a firm has unlimited access to funds, what is the proper accept or reject decision when using internal rate of return (IRR)? please make sure so I can read your...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
Nokia has two Projects. Project A and Project B. Which project should be accepted under each...
Nokia has two Projects. Project A and Project B. Which project should be accepted under each measurement. Project A Project B NPV ($) 2578 3842 IRR ($) 12 14 MIRR (%) 10 11 PI 1.2 1.5 Payback Period (years) 3 3.8 Discounted Payback Pd (Years) 4.2 4.8 Nokia's cost of capital is 8%. Its critical payback period is 2 years and the critical discount payback period is 3 years NPV - (Project A be accepted, Project B be accepted, or...
A firm is considering Projects S and L, with the following cash flows: Project L: −$2,150...
A firm is considering Projects S and L, with the following cash flows: Project L: −$2,150 in year 0, $765 in years 1, 2, 3, and 4 Project S: −$1,025 in year 0, $380 in years 1, 2, 3, and 4 These projects are mutually exclusive. The projects are also equally risky with WACC of 6%. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the...
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000​ and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup​ window: Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted.   ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT