Question

In: Finance

You are considering the following two projects. Which project(s)should you choose?ProjectYear 0Cash...

You are considering the following two projects. Which project(s) should you choose?

Project

Year 0

Cash Flow

Year 1

Cash Flow

Year 2

Cash Flow

Year 3

Cash Flow

Year 4

Cash Flow

Discount Rate (r)

A

-$120

$40

$40

$40

$40

15%

B

-$90

$30

$30

$30

$30

15%

Solutions

Expert Solution

We will calculate NPV to select project.

We know that,

NPV = Present value of all the future cash flow - initial cost

Project A:

NPV = 40/(1+0.15)^1 + 40/(1+0.15)^2 + 40/(1+0.15)^3 + 40/(1+0.15)^4 - 120

NPV = -5.80 Answer

Project B:

NPV = 30/(1+0.15)^1 + 30/(1+0.15)^2 + 30/(1+0.15)^3 + 30/(1+0.15)^4 - 90

NPV = -4.35 Answer

Since both projects have negative NPV, I would suggest not to consider any project.

Since, we need to consider one project, you will select Project B as it has higher NPV.


Related Solutions

You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Calculate and choose project/s assuming that these two projects are (1) mutually exclusive OR (2) independent....
Calculate and choose project/s assuming that these two projects are (1) mutually exclusive OR (2) independent. IRR (WACC 6%), specify range. CFs Year A B 0 -2050 -4300 1 750 1500 2 760 1518 3 770 1536 4 780 1554
1: When projects are mutually exclusive, you should choose the project with the: Assuming an interest...
1: When projects are mutually exclusive, you should choose the project with the: Assuming an interest rate of 14%, what is the net present value of an investment with the cash flows indicated in the table? CF0 -$193,000   CF1 $50,235   CF2 $62,850   CF3 $62,850   CF4 $48,910   CF5 $87,415 2- Assuming a firm has unlimited access to funds, what is the proper accept or reject decision when using internal rate of return (IRR)? please make sure so I can read your...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
You are considering two projects with the following cash flows: Project Y Project X Year 1...
You are considering two projects with the following cash flows: Project Y Project X Year 1 $9,500 $6,000 Year 2 $9,000 $6,900 Year 3 $6,900 $9,000 Year 4 $6,000 $9,500 Which one of the following statements is true concerning the two projects given a positive discount rate? A. Project Y has both a higher present value and a higher future value than project X. B. Both projects have the same future value at the end of year 4. C. Project...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
You are considering the following two mutually exclusive projects. The required return on each project is...
You are considering the following two mutually exclusive projects. The required return on each project is 14 percent. Which project should you accept and what is the best reason for that decision? Year Project A Project B 0 −$ 24,000 −$ 21,000 1 9,500 6,500 2 16,200 9,800 3 8,700 15,200 Project A; because it pays back faster Project A; because it has the higher profitability index Incorrect Project B; because it has the higher profitability index Project B; because...
Nokia has two Projects. Project A and Project B. Which project should be accepted under each...
Nokia has two Projects. Project A and Project B. Which project should be accepted under each measurement. Project A Project B NPV ($) 2578 3842 IRR ($) 12 14 MIRR (%) 10 11 PI 1.2 1.5 Payback Period (years) 3 3.8 Discounted Payback Pd (Years) 4.2 4.8 Nokia's cost of capital is 8%. Its critical payback period is 2 years and the critical discount payback period is 3 years NPV - (Project A be accepted, Project B be accepted, or...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT