In: Finance
You are considering the following two projects. Which project(s) should you choose?
Project | Year 0 Cash Flow | Year 1 Cash Flow | Year 2 Cash Flow | Year 3 Cash Flow | Year 4 Cash Flow | Discount Rate (r) |
A | -$120 | $40 | $40 | $40 | $40 | 15% |
B | -$90 | $30 | $30 | $30 | $30 | 15% |
We will calculate NPV to select project.
We know that,
NPV = Present value of all the future cash flow - initial cost
Project A:
NPV = 40/(1+0.15)^1 + 40/(1+0.15)^2 + 40/(1+0.15)^3 + 40/(1+0.15)^4 - 120
NPV = -5.80 Answer
Project B:
NPV = 30/(1+0.15)^1 + 30/(1+0.15)^2 + 30/(1+0.15)^3 + 30/(1+0.15)^4 - 90
NPV = -4.35 Answer
Since both projects have negative NPV, I would suggest not to consider any project.
Since, we need to consider one project, you will select Project B as it has higher NPV.