Question

In: Finance

The Financial Manager of Alantis Company is considering two projects (project A and project B), which...

The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows:

Year

Cash Flow of Project A (in $)

Cash Flow of Project B (in $)

0

-100

-100

1

    10

    70

2

    60

    50

3

    80

    20

Alantis Company’s cost of capital is 10 percent.

Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)

Solutions

Expert Solution


Related Solutions

The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
1.) A company is considering two projects.   Project A Project B Initial investment $300,000 $300,000 Cash...
1.) A company is considering two projects.   Project A Project B Initial investment $300,000 $300,000 Cash inflow Year 1 $60,000 $90,000 Cash inflow Year 2 $60,000 $80,000 Cash inflow Year 3 $60,000 $80,000 Cash inflow Year 4 $60,000 $50,000 Cash inflow Year 5 $60,000 $70,000 What is the payback period for Project B? Select one: a. 2 years b. 5 years c. 3.5 years d. 4 years e. 3 years 2.) Ace Inc. produces custom widgets. The cost structure for...
You are the financial manager of this company. The company is considering a replacement project for...
You are the financial manager of this company. The company is considering a replacement project for an old overhead crane. The old crane is was purchased 5-years go and and originally cost $90,000. It had a useful life of 10-years and is being depreciated on a straight-line basis. The new crane would cost $300,000 and would require an additional $15,000 in net working capital (recovered at the end of year 5). It would be depreciated straight-line over the next 5...
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000​ and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup​ window: Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted.   ...
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000 and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 12 percent. The expected annual free cash inflows from each project are in the popup​ window: .Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted. a....
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
A firm is considering two projects, A and B. Each project will last for 4 years....
A firm is considering two projects, A and B. Each project will last for 4 years. The projects are INDEPENDENT. The projected cash flows for each project are shown below: Year 0 1 2 3 4 Project A -20.00 8.00 8.00 6.00 4.00 Project B -30.00 10.00 10.00 11.00 9.00 The cost of capital for the firm is 10.00%. What is the NPV for project A at the cost of capital? Answer Format: Currency: Round to: 2 decimal places.
There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,900 at the end of year 1; 2,000 at the end of year 2; 5,000 at the end of year 3. Project B's initial cost is 7,500, and subsequent cash flows are 5,000 per year for 3 years. WACC is 8% for both projects. Calculate NPV and IRR for each project, and decide which to recommend.
There are two projects that the company is considering: Project A costs 10,000 to implement today,...
There are two projects that the company is considering: Project A costs 10,000 to implement today, and it brings subsequent cash flows of 5,000 at the end of year 1; 4,000 at the end of year 2; 6,000 at the end of year 3. Project B's initial cost is 12,000, and subsequent cash flows are 6,000 per year for 3 years. WACC is 8% for both projects. a. Calculate NPV and IRR for each project, and decide which one to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT