Question

In: Finance

Nokia has two Projects. Project A and Project B. Which project should be accepted under each...

Nokia has two Projects. Project A and Project B. Which project should be accepted under each measurement.

Project A Project B
NPV ($) 2578 3842
IRR ($) 12 14
MIRR (%) 10 11
PI 1.2 1.5
Payback Period (years) 3 3.8
Discounted Payback Pd (Years) 4.2 4.8

Nokia's cost of capital is 8%. Its critical payback period is 2 years and the critical discount payback period is 3 years

NPV - (Project A be accepted, Project B be accepted, or neither)

IRR - (Project A be accepted, Project B be accepted, or neither)

MIRR - (Project A be accepted, Project B be accepted, or neither)

PI - (Project A be accepted, Project B be accepted, or neither)

Payback pd - (Project A be accepted, Project B be accepted, or neither)

Discounted Payback pd - (Project A be accepted, Project B be accepted, or neither)

Solutions

Expert Solution

It has been assumed that both the projects are mutually exclusive and they cannot occur at same time

1. Net Present value-when there are two projects mutually exclusive than the project having higher net present value is accepted. Project B should be accepted according to net present value.

2. Internal rate of return- when the internal rate of return is higher than cost of capital then project should be accepted and the project having higher margin will be selected and in this case project B will be selected because it have higher margin against cost of capital.

3. MIRR - in case of project having higher MIRR over cost of capital should be selected and project B should be selected.

4. Profitability index- project which will have higher profitability index above 1 will be selected. Hence project B should be selected.

5. Payback period-critical payback period is 2 years and neither of the project have a lower payback period of 2 years or lower so NEITHER of them should be accepted.

6. Discounted payback period is given that critical discounted payback period is 3 years so neither of the projects have a lower payback period than three years so NEITHER of them should be selected.


Related Solutions

g. Determine the PI for each of these projects. Should either project be​ accepted? PROJECT A...
g. Determine the PI for each of these projects. Should either project be​ accepted? PROJECT A PROJECT B Initial outlay -110,000 -110,000 Inflow year 1      10,000        40,000 Inflow year 2        30,000        40,000 Inflow year 3      40,000        40,000 Inflow year 4        60,000        40,000 Inflow year 5        80,000        40,000 g. What is the PI for project​ A? nothing   ​(Round to three decimal​ places.) Caledonia should accept project A because its PI is greater than or equal to 1.00.  ​(Select from the​ drop-down...
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Inital Outlay (105,000.000) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% Your company is considering three independent projects. Given the following cash flow information,...
Calculate the NPV for each project and determine which project should be accepted. Project A Project...
Calculate the NPV for each project and determine which project should be accepted. Project A Project B Project C Project D Initial Outlay (105,000.00) (99,000.00) (110,000.00) (85,000.00) Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00 Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00 Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00 Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00 Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00 Rate 7% 10% 13% 18% NPV = $75,228.32 $77,364.07 -$2,531.00 $69,006.08 Answer: Project B How to show work...
John’s Construction has three projects under way. Each project requires a regular supply of gravel, which...
John’s Construction has three projects under way. Each project requires a regular supply of gravel, which can be obtained from three quarries. Shipping costs differ from location to location, and are summarized in the table. From: Job 1 Job 2 Job 3 Tonnage allowance Quarry A $9 $8 $7 1500 Quarry B $7 $11 $6 1750 Quarry C $4 $3 $12 2750 Job Requirements (tonnes) 2000 3000 1000 6000 Formulate a transportation model (but do not attempt to solve it)...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
The Financial Manager of Alantis Company is considering two projects (project A and project B), which...
The Financial Manager of Alantis Company is considering two projects (project A and project B), which have cash flows as follows: Year Cash Flow of Project A (in $) Cash Flow of Project B (in $) 0 -100 -100 1     10     70 2     60     50 3     80     20 Alantis Company’s cost of capital is 10 percent. Please Calculate the payback, NPV, IRR, and MIRR for both projects. (Show step by step work)
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B....
An entrepreneur has a choice of two mutually exclusive investment projects, Project A and Project B. Each lasts for one time period and the firm has no other projects. Project A will result in a cash flow of £27 million in the good state and £10 million in the bad state. Each outcome is equally likely. Project B will result in a cash flow of £34 million in the good state and zero in the bad state. Each outcome is...
A firm is considering two projects, A and B. Each project will last for 4 years....
A firm is considering two projects, A and B. Each project will last for 4 years. The projects are INDEPENDENT. The projected cash flows for each project are shown below: Year 0 1 2 3 4 Project A -20.00 8.00 8.00 6.00 4.00 Project B -30.00 10.00 10.00 11.00 9.00 The cost of capital for the firm is 10.00%. What is the NPV for project A at the cost of capital? Answer Format: Currency: Round to: 2 decimal places.
There are two projects under consideration by the Rainbow factory. Each of the projects will require...
There are two projects under consideration by the Rainbow factory. Each of the projects will require an initial investment of $34,000 and is expected to generate the following cash flows: First Year Second Year Third Year Total Alpha Project $32,500   $22,000     $5,500   $60,000 Beta Project 8,000   23,000     28,000   59,000 (Click here to see present value and future value tables) A. If the discount rate is 10%, compute the NPV of each project. Round your present value factor to three decimal...
If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?
Considering the following projects.ProjectYear01234ACash flows-$100$35$35$35$35BCash flows-$100$60$50$40$30Project A has WACC = 6.00% while project B has WACC = 8.50%.If these two projects are mutually exclusive, which project should the company accept based on the NPV, IRR, MIRR, payback, and discounted payback period for each project?Would your decision (Your answer from part A) change if these two projects were independent?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT