Question

In: Accounting

Question 8 Queens Construction Company commences construction of a harbour on 1 July 2020. It signs...

Question 8

Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project:

2021

2022

2023

($ M)

($ M)

($ M)

Costs for the year

90

110

120

Costs incurred to date

90

200

320

Estimated costs to complete

210

120

-

Progress billings during the year

100

120

180

Cash collected during the year

90

130

180

The contract is completed as expected on 30 June 2023. Queens Construction Company uses the percentage-of-completion method to account for its construction contract.

REQUIRED

Provide the numbers for the journal entries below. Assume the stage of completion can be reliably determined. Round the percentage complete (%) to one decimal place (i.e, 0.0%) if necessary.  Complete the six blanks below. (You don't need to provide the numbers for "?")

-------------------------------------

Journal entry to record periodic income recognised for 2021, 2022, 2022

Solutions

Expert Solution


Related Solutions

NRE Construction Company commences the construction of specialised fast carriages on 1 July 2019. It signs...
NRE Construction Company commences the construction of specialised fast carriages on 1 July 2019. It signs a fixed-price contract for total revenue of $180million. It was revised to 185 million in 2022. The project is expected to be completed by the end of 30 June 2022. The expected cost at the commencement of construction was $160 million. The expected costs to complete a construction project can change throughout the project. The following data relate to the project: 2020 2021 2022...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for...
Big Construction Company signs a contract on 1 July 2019, agreeing to build a warehouse for Buyer Corporation Ltd at a fixed contract price of $10 million. Buyer Ltd will be in control of the asset throughout the construction process. Big Construction Company estimates that construction costs will be as follows: 2019 2.5 million 2020 $4 million 2021 $1.5 million The contract provides that Buyer Corporation Ltd will make payments on 31 December each year as follows: 2019 $2 million...
Sun City Limited commences construction of a multi-purpose water park on 1 July 2014 for Pretoria...
Sun City Limited commences construction of a multi-purpose water park on 1 July 2014 for Pretoria Limited. Sun City Limited signs a fixed-price contract for total revenues of $50 million. The project is expected to be completed by the end of 2017 and Pretoria Limited controls the asset throughout the period of construction. The expected cost as at the commencement of construction is $38 million. The estimated costs of a construction project might change throughout the project—in this example, they...
On July 1, 2020, Sandhill Company purchased $3,860,000 of Duggen Company’s 8% bonds, due on July...
On July 1, 2020, Sandhill Company purchased $3,860,000 of Duggen Company’s 8% bonds, due on July 1, 2027. The bonds, which pay interest semiannually on January 1 and July 1, were purchased for $3,340,000 to yield 10%. These bonds are classified as available-for sale and they have a fair value at December 31, 2020, of $3,444,400, prepare the journal entry (if any) at December 31, 2020, to record this transaction.
On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp
Construction Contract Accounting as per Percentage-of-Completion Method & Completed Contract Method.  Problem Four: Long-Term Contract  On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gabriella Corp. for a total contract price of S2,000,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated...
PRACTICAL QUESTION    Tiger Construction Ltd signs a contract on 1 May 2018 to build a...
PRACTICAL QUESTION    Tiger Construction Ltd signs a contract on 1 May 2018 to build a theme park. The construction is scheduled to commence on 1 July 2018 and the estimated date of completion is 30 June 2021. The total contract price is $5m and the cost of the park is initially estimated at $4.5m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $ $ $ Costs to date 1,700,000 3,000,000...
Question#1 On December 31, 2014, State Construction Inc. signs a contract with the state of West...
Question#1 On December 31, 2014, State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State Construction anticipates the construction will take three years. The company’s accountants provide the following contact details relating to the project: Contract price $520 million Estimated construction costs $400 million Estimated total profit $120 million During the three-year construction period, State Construction incurred costs as follows: 2015 $ 40 million 2016 $240...
Ltd commences operations on 1 July 2016. One year after the commencement of its operations (30...
Ltd commences operations on 1 July 2016. One year after the commencement of its operations (30 June 2017) the entity presents its first Statement of Comprehensive Income and Statement of Financial Position on 30 June 2017. The statements are prepared before considering taxation. The following extracts are available. Happy Ltd Statement of Comprehensive Income for the year ended 30 June 2017 $ $ Gross Profit 2,550,000 Expenses: Miscellanous expenses 3,000 Rent 165,000 Wages and Salaries 510,000 Selling Expenses 76,000 Finance...
Ltd commences operations on 1 July 2016. One year after the commencement of its operations (30...
Ltd commences operations on 1 July 2016. One year after the commencement of its operations (30 June 2017) the entity presents its first Statement of Comprehensive Income and Statement of Financial Position on 30 June 2017. The statements are prepared before considering taxation. The following extracts are available. Happy Ltd Statement of Comprehensive Income for the year ended 30 June 2017 $ $ Gross Profit 2,550,000 Expenses: Miscellanous expenses 3,000 Rent 165,000 Wages and Salaries 510,000 Selling Expenses 76,000 Finance...
Laura Leasing Company signs an agreement on January 1, 2020, to lease equipment to Metlock Company....
Laura Leasing Company signs an agreement on January 1, 2020, to lease equipment to Metlock Company. The following information relates to this agreement. 1. The term of the non-cancelable lease is 3 years with no renewal option. The equipment has an estimated economic life of 5 years. 2. The fair value of the asset at January 1, 2020, is $76,000. 3. The asset will revert to the lessor at the end of the lease term, at which time the asset...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT