In: Accounting
3. MNO has a job costing system. The following are the manufacturing costs during the month of February:
Materials placed into production |
? |
Direct labor (2,000 hours) |
$ 80,000 |
Plantwide overhead applied |
$ 40,000 |
Cost of goods manufactured |
$200,000 |
MNO applies overhead to production on the basis of direct labor hours. The beginning work in process inventory was $18,000 and the ending work in process inventory was $16,000 (the ending work in process had $15,400 of raw materials and 10 hours of direct labor in it at the end of February.
Required:
A. |
Determine the predetermined plantwide overhead rate for MNO Company. |
B. |
Determine the amounts of materials, direct labor, and plantwide overhead included in the February 28 work in process. |
C. |
Determine the amount of materials placed into production during February. |
A. Predetermined plantwide overhead rate for MNO Company = Plantwide overhead applied / Direct labor hours
= 40,000 / 2,000
= $20 per hour
B. February 28 work in process = $16,000
Amount of materials = $15,400 (as given in the question itself)
Amount of direct labor = 10 hours x (80,000 / 2,000) per hour
= 10 hours x 40 per hour
= $400
Amount of plantwide overhead = 10 hours x 20 per hour
= $200
C. Amount of materials placed into production during February is calculated as under:
Cost of goods manufactured = Manufacturing costs incurred in the current accounting period + Beginning work-in-process inventory - Ending work-in-process inventory
200,000 = Manufacturing costs incurred in the current accounting period + 18,000 - 16,000
or Manufacturing costs incurred in the current accounting period = 200,000 - 18,000 + 16,000 = $198,000
Now,
Manufacturing costs incurred in the current accounting period = Materials placed into production + Direct labor + Plantwide overhead applied
Therefore,
198,000 = Materials placed into production + 80,000 + 40,000
or Materials placed into production = 198,000 - 80,000 - 40,000 = $78,000