please explain what is meant by critical path scheduling and describe the process of creating Gantt charts and Network diagrams
Critical path scheduling:
In the project management, there are various activities involved. The activities duration is known along with dependency which helps to determine the precedence. Basis this, Gantt chart or Network diagrams are plotted to determine the path which takes maximum time. That path is termed as Critical path as it determines the duration for overall project.
Process to form Gantt chart:
The process for Network diagram is same as that Gantt chart with a difference that there are two options:
Basis the ease and requirement, either can developed
Example of Network diagram:
Activity | Activity time |
A | 2 |
B | 4 |
C | 1 |
D | 2 |
E | 3 |
F | 1 |
G | 2 |
H | 1 |
Critical path is: B-D-E-H as it takes maximum time