In: Accounting
Compute the ABC rates based on the following information:
Activity Cost Pool |
(a) Estimated Overhead Cost |
(b) Expected Activity |
|||
Labor related........................... |
$ 5,200 |
800 |
DLHs |
||
Machine related....................... |
1,500 |
2,000 |
MHs |
||
Machine setups........................ |
4,200 |
100 |
setups |
||
Production orders..................... |
1,800 |
50 |
orders |
||
Product testing........................ |
4,800 |
200 |
tests |
||
Packaging............................... |
7,000 |
500 |
packages |
||
General factory........................ |
108,800 |
800 |
DLHs |
||
Compute the single overall predetermined overhead rate based entirely on direct labor-hours:
Compute the cost for completing 100,000 widgets if the direct materials cost was $45,000 and the Direct labor cost was $60,000. They data for activity based costing is below:
Actual Activity |
||
400 |
DLHs |
|
900 |
MHs |
|
20 |
setups |
|
20 |
orders |
|
40 |
tests |
|
200 |
packages |
|