Question

In: Finance

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:

                               Project E Project F

                  Year     Cash Flow     Cash Flow

                   0       -$100,000        -$100,000

                   1          50,000            10,000

                   2          40,000            30,000

                   3          30,000            40,000

                   4          10,000            60,000

If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??

Solutions

Expert Solution

a) Questiion requires to choose alternate proposal in between E and F.

NPV is sum total of discounted cashflows.

Let us first calculate Net Present value of both projects as follows:

Year Actual Cashflows @15% Discounted Cashflows@15%
Project - E Project - F Project - E Project - F
0 -1,00,000 -1,00,000 -1,00,000 -1,00,000
1 50,000 10,000 43,478 8,696
2 40,000 30,000 30,246 22,684
3 30,000 40,000 19,725 26301
4 10,000 60,000 5,718 34,305
NPV (Sum of discounted cashflows) -833 -8,014

Since a positive NPV determine option to be viable, but here we are asked to determine more feaseble option, therefore Project - E is a better option since NPV is less negative here.

Now Let us calculate IRR by using formula of interpolation as follows:-

IRR = Lower Discount Rate + [NPV at Lower rate (Higher Rate - Lower Rate) / (NPV at Lower Rate - NPV at Higher Rate)]

Formulae for IRR :-

First for Project E

At discounting rate of 15% NPV is -833. Let us calculate NPV at 14% rate(on hit and trial basis): -

Year Actual Cashflow Discounted Cashflow
0 -1,00,000 -1,00,000
1 50,000 43,859.65
2 40,000 30778.7
3 30,000 20249.14
4 10,000 5920.8
NPV 808.29

IRR = Lower Discount Rate + [NPV at Lower rate x (Higher Rate - Lower Rate) / (NPV at Lower Rate - NPV at Higher Rate)]

Therefore IRR will be = 14% + {808.29 x (15% - 14%) / [808.29 -(-833]}

= 14% + (0.49)

= 14.49%

Therefore NPV will be 0 at 14.49 discounting rate for project E.

Similarly now let us calculate IRR for Project - F

Here, since NPV is -8,014 we will try disounting with more lower rate, say at 12% and 11%

Year Actual Cashflow Discounted Cashflow @12% Discounted Cashflow @11%
0 -1,00,000 -1,00,000 -1,00,000
1 10,000 8,928.57 9,009.01
2 30,000 23915.81 24348.67
3 40,000 28471.21 29247.655
4 60,000 38131.08 39523.85
NPV -553.33 2,129.18

IRR = Lower Discount Rate + [NPV at Lower rate x (Higher Rate - Lower Rate) / (NPV at Lower Rate - NPV at Higher Rate)]

Therefore IRR will be = 11% + { 2,129.18 x (12% - 11%)/ [2129.18 - (-553.33)]}

= 11% + 0.792

= 11.79%


Related Solutions

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows: Project E Project F Year Cash Flow Cash Flow 0 -$100,000 -$100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING NET CASH FLOWS: COST OF CAPITAL IS 12% YEAR 0 1 2 3 4 X $-2,000 $250 $380 $480 $2,000 Y $-1,800 $1,600 $600 $200 $420 Calculate Project X's DISCOUNT PAYBACK PERIOD (DPB) A. 1.57 B. 1.78 C. 3.47 D. 3.89 E. 5.22
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
Company A is considering the following two mutually exclusive projects. Company A bases their capital budgeting...
Company A is considering the following two mutually exclusive projects. Company A bases their capital budgeting decisions solely on the NPV criteria. (Do not round intermediate calculations. Round your final answer to two decimal places.) Year Project 1 Project 2 0 -$75,000 -$75,000 1 $50,000 $20,000 2 $30,000 $21,000 3 $15,000 $59,000 1. At what required rate of return (%) is Company A indifferent between the two projects? 2. If the required rate of return is less than the crossover...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT