Question

In: Finance

When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...

When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.

Solutions

Expert Solution

Mutually exclusive projects means the firm has to make a decision to select one project and reject another. In Mutually exclusive projects acceptance of one means rejection of other.

In case of mutually exclusive projects, the NPV and IRR could conflict with each other in the ranking of projects. Below are the some reasons of conflict -

1) IRR and NPV may rank projects differently when the projects has unequal life. Since the IRR is as scaled measure it is biased for smaller projects which are more likely to provide higher return than larger projects. In larger projects the NPV will be more the the cash inflows will be for more no. of years. So in case of unequal life IRR and NPV may rank projects differently.

2) When there is time disparity for the cash flows of two different projects IRR and NPV may rank projects differently.

3) IRR and NPV may rank projects differently due to size disparity also. IRR will prefer the project which are smaller in size but NPV will be more of larger investment project.

--->When there is conflict between the NPV and IRR techniques in respect to ranking of the projects, NPV method should be used. IRR mthod is based on assumption that the intermediate cashflows are reinvested at IRR, which is unrealistic.

NPV has realistic reinvestment rate assumption. It assumes all the intermediate cash inflows are reinvested at cost of capital. Hence, NPV is a better technique to be used in case of conflict.

Hope it explains!


Related Solutions

When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
‘Evaluating mutually exclusive projects using the IRR and NPV approaches can be problematic’. Discuss this statement...
‘Evaluating mutually exclusive projects using the IRR and NPV approaches can be problematic’. Discuss this statement with examples.
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows: Project E Project F Year Cash Flow Cash Flow 0 -$100,000 -$100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.52 $260 $15 $10 Project L -$1,000 $0 $250 $380 $811.10 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $0 $250 $400 $775.11 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $5 $240 $380 $844.53 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $896.53 $250 $5 $5 Project L -$1,000 $10 $260 $380 $821.65 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT