Question

In: Finance

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:


Project E Project F

Year Cash Flow Cash Flow

0 -$100,000 -$100,000

1 50,000 10,000

2 40,000 30,000

3 30,000 40,000

4 10,000 60,000


If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??

Solutions

Expert Solution

To determine which Project is better, we will compute the NPV of both the projects. The Project with higher NPV will be better.

Computation of NPV of Project E and Project F

Year

Project E

Project F PVAF @15% PV- Project E PV- Project F
a b c d e=b*d f=c*d
0

-$100,000.00

-$100,000.00

1 -$100,000.00 -$100,000.00
1 $50,000.00 $10,000.00 0.869565217 $43,478.26 $8,695.65
2

$40,000.00

$30,000.00 0.756143667 $30,245.75 $22,684.31
3 $30,000.00 $40,000.00 0.657516232 $19,725.49 $26,300.65
4

$10,000.00

$60,000.00 0.571753246 $5,717.53 $34,305.19
NPV -$832.97 -$8,014.19

NPV of Project E (i.e. -$832.97) is higher than Project F (i.e. -$8014.19). Therefore, Project E is better.

Calculation of IRR of Project E-

IRR is that rate of return where PV of cash inflow = PV of cash Outflow

Using hit and trial method, we get IRR= 14.5% (this is the rate at which PV of cash inflow is approximately equal to PV of cash outflow).

Please upvote the answer if it was of help to you.
In case of any doubt just comment below, I would love to help.


Related Solutions

As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING...
AS A CAPITAL BUDGETING DIRECTOR OF DAYTON CORPORATION, YOU ARE EVALUATING TWO PROJECTS WITH THE FOLLOWING NET CASH FLOWS: COST OF CAPITAL IS 12% YEAR 0 1 2 3 4 X $-2,000 $250 $380 $480 $2,000 Y $-1,800 $1,600 $600 $200 $420 Calculate Project X's DISCOUNT PAYBACK PERIOD (DPB) A. 1.57 B. 1.78 C. 3.47 D. 3.89 E. 5.22
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and...
The director of capital budgeting for Giant Inc. has identified two mutually exclusive projects, L and S, with the following expected net cash flows: Expected Net Cash Flows Year Project L Project S 0 ($100) ($100) 1 10 70 2 60 50 3 80 20 Both projects have a cost of capital of 12 percent. What is Project S's MIRR? What is Project L's MIRR?
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT